10541 Remove and Install Pole Structures Using Live Line Glove and Barrier Procedures up to 33Kv

10541 Remove and Install Pole Structures Using Live Line Glove and Barrier Procedures up to 33Kv

10541 version 5

Page 1 of 4

Remove and install pole structures using live line glove and barrier procedures up to 33kV

Level / 5
Credits / 20

PurposePeople credited with this unit standard are able to: plan and prepare for live line glove and barrier work up to 33kV; displace and reinstate conductors on pole structures using live line glove and barrier procedures up to 33kV; remove and erect electricity network poles; and report work on pole structures using live line glove and barrier procedures up to 33kV.

Subfield / Electricity Supply
Domain / Electricity Supply - Live Work
Status / Registered
Status date / 18 September 2009
Date version published / 21 May 2010
Planned review date / 31 December 2014
Entry information / Prerequisites: compliance with the minimum requirements of industry codes of practice for live work; Unit 10521, Install and replace electricity network pole structures; Unit 10538, Inspect, test, and clean live line tools and equipment; Unit 10542, Demonstrate knowledge of live line theory and procedures; or demonstrate equivalent knowledge and skills.
Recommended: Unit 24746, Rig electrical network structures.
Accreditation / Evaluation of documentation and visit by NZQA and industry.
Standard setting body (SSB) / Electricity Supply Industry Training Organisation
Accreditation and Moderation Action Plan (AMAP) reference / 0120

This AMAP can be accessed at http://www.nzqa.govt.nz/framework/search/index.do.

Special notes

1This unit standard is intended for, but not restricted to, workplace assessment.

2Safety of personnel and plant must be a priority throughout the assessment. If the safety requirements are not met the assessment must stop.

3Performance and work practices in relation to the elements and performance criteria must comply with all current legislation, especially the Electricity Act 1992, and any regulations and codes of practice recognised under that statute; the Health and Safety in Employment Act 1992; and the Resource Management Act 1991. Electricity supply industry codes of practice and documented industry procedures include the Safety Manual – Electricity Industry (SM-EI) (2004) (Wellington: Electricity Engineers’ Association). A full list of current legislation and industry codes is available from the Electricity Supply Industry Training Organisation, PO Box 1245, Hamilton 3240.

4The phrase in accordance with industry requirements is implicit in all elements and performance criteria in this unit standard.

5Industry requirements include all asset owner requirements; manufacturers’ specifications; and enterprise requirements which cover the documented workplace policies, procedures, specifications, business, and quality management requirements relevant to the workplace in which assessment is carried out.

6Entry into live work is conditional on the trainee meeting the minimum requirements of NZECP 46:2003: New Zealand Electrical Code of Practice for High Voltage Live Line Work (Wellington: Ministry of Consumer Affairs).

7Pole types, structures and configurations may include but are not limited to:

types – concrete, wood, steel;

structures – single, double;

configurations – angle, intermediate, termination.

Elements and performance criteria

Element 1

Plan and prepare for live line glove and barrier work up to 33kV.

Performance criteria

1.1Work requirements are established.

Rangeinspection requirements, site information, plans, procedures, approvals.

1.2Tools and equipment are inspected and cleaned.

1.3Working platforms are inspected and placed.

1.4Safe working zone is established.

Element 2

Displace and reinstate conductors on pole structures using live line glove and barrier procedures up to 33kV.

Rangeinclude but are not limited to – cranes, elevated work platforms (EWPs), auxiliary arms.

Performance criteria

2.1Conductors are displaced using mechanical support glove and barrier procedures.

2.2Conductors are reinstated using mechanical support glove and barrier procedures.

Element 3

Remove and erect electricity network poles.

Performance criteria

3.1Pole holes are excavated.

Rangemechanical, manual.

3.2Poles are removed.

3.3Poles are erected.

Rangeconcrete, breast and toe blocks, direct back fill, imported back fill, soil strenghtened.

3.4Worksite is reinstated.

Element 4

Report work on pole structures using live line glove and barrier procedures up to 33kV.

Rangemay include but is not limited to – live work permit, authorisations, log book, plant and equipment history, test reports and results, service report.

Performance criteria

4.1Reported information is complete, concise, and legible.

4.2Information is recorded in the required format and filed within the scheduled time frame.

Please note

Providers must be accredited by NZQA, or an inter-institutional body with delegated authority for quality assurance, before they can report credits from assessment against unit standards or deliver courses of study leading to that assessment.

Industry Training Organisations must be accredited by NZQA before they can register credits from assessment against unit standards.

Accredited providers and Industry Training Organisations assessing against unit standards must engage with the moderation system that applies to those standards.

Accreditation requirements and an outline of the moderation system that applies to this standard are outlined in the Accreditation and Moderation Action Plan (AMAP). The AMAP also includes useful information about special requirements for organisations wishing to develop education and training programmes, such as minimum qualifications for tutors and assessors, and special resource requirements.

Comments on this unit standard

Please contact the Electricity Supply Industry Training Organisation if you wish to suggest changes to the content of this unit standard.

 New Zealand Qualifications Authority 2019