World Bank Financed Sichuan Urban Development Project (SUDP)

Mianyang Sub-project Remaining Loan Adjustment-

Roads & Supporting Infrastructure Construction in the Cluster Zone of Relocated Industries Through Post-disaster Reconstruction in Xinglong Area of Science & Education Pioneer Park of Mianyang Science and Technology City

Resettlement Action Plan

Mianyang Science and TechnologyCity
Development and Investment (Group) Co., Ltd.

November 2009

World Bank FinancedSUDP

Mianyang Sub-project Remaining Loan Adjustment-Roads & Supporting Infrastructure Construction in the Cluster Zone of Relocated Industries Through Post-disaster Reconstruction in Xinglong Area of Science & Education Pioneer Park of Mianyang Science and Technology City

Compilation Description

The Resettlement Action Plan (RAP) is of great importance to smooth implementation of Science & Education Pioneer Park Project in Mianyang, Sichuan, especially to those affected by land acquisition and house demolition within the scope of the Project. Local governments, Mianyang Science and Technology City Development Investment (Group) Co., Ltd. and Southwest Municipal Engineering Design & Research Institute of China, which is a design institute, attempt to minimize adverse impact of the Project on local residents through constantly repeated optimum designs. Mianyang Science & Technology City Development Investment (Group) Co., Ltd. has prepared the RAP with the assistance of resettlement specialists from Research Institute of Foreign Capital Introduction and Utilization, SouthwestJiaotongUniversity.

Mianyang Science and TechnologyCity Development
and Investment (Group) Co., Ltd.

November 2009

Contents

Chapter 1Overview

1.1Project description

1.2Preparation of Resettlement Action Plan

1.3Measures to reduce land acquisition and house demolition

1.3.1Planning and design stage of the Project

1.3.2Construction stage of the Project

1.3.3Resettlement Action Plan for land acquisition and house demolition in the Project and implementation stage

Chapter 2Socioeconomic Survey

2.1Socioeconomic overview of project-affected area

2.1.1Socioeconomic conditions of Mianyang City

2.1.2Socioeconomic conditions of Science & Education Pioneer Park

2.1.3Socioeconomic conditions of affected communities

2.2Socioeconomic survey by Southwest Jiaotong University

2.3Socioeconomic characteristics of affected persons

2.3.1Overview

2.3.2Human resources

2.3.3Natural resources

2.3.3.1Land ownership

2.3.3.2Cultivated land, orchards and economic forest

2.3.3.3Water sources

2.3.4Material resources

2.3.4.1Houses and attachments

2.3.4.2Productive assets

2.3.4.3Domestic durable goods

2.3.5Financial resources

2.3.5.1Income of households

2.3.5.2Income sources

2.3.5.3Consumption pattern and deposits

2.3.6Vulnerable groups

Chapter 3Project Impact

3.1Scope of project impact

3.2Material indices of project impact

3.2.1Permanent land acquisition

3.2.1.1Amount of permanent land acquisition

3.2.1.2Analysis on impact of permanent land acquisition

3.3.2Land for temporary use

3.3.3House demolition

3.3.4Project-affected commercial shops

3.3.5Project-affected enterprises

3.3.6Project-affected population

3.3.7Scattered trees, tombs and other attachments

3.3.8Special facilities

Chapter 4Legal Framework and Resettlement Policy

4.1Policy basis

4.2Land acquisition, house demolition and resettlement policies

4.2.1General objectives and principles

4.3Laws and regulations concerned

4.3.1Regulations in Land Administration Law of the People's Republic of China

4.3.1.1Ownership and right of use of land

4.3.1.2.General plans for the utilization of land

4.3.1.3Protection of cultivated land

4.3.1.4Land for construction purposes

4.3.2Regulations concerning Interim Regulations of the People's Republic of China on Farmland Occupation Tax

4.3.3Regulations concerning Decision of the State Council on Deepening Reformation and Strengthening Land Administration (GF [2004] No. 28)

4.3.4Regulations in World Bank OP4.12

4.3.4.1Policy objective

4.3.4.2Resettlement plan

4.3.4.3Social participation and involvement with original residents in the resettlement area

4.3.4.4Socioeconomic survey

4.3.4.5Selection and determination of resettlement areas

4.3.4.6Assessment of and compensation to property loss

4.3.4.7Housing, infrastructure and social service

4.3.4.8Implementation progress, monitoring and assessment

4.3.4.9Preparation

4.3.4.10Implementation and supervision

Chapter 5Compensation Standard and Compensation Budget

5.1Compensation standard

5.1.1Compensation standards for land acquisition

5.1.1.1Compensation standards for permanent land acquisition

5.1.1.2Compensation standard for temporary land acquisition

5.1.1.3Compensation standards for crops

5.1.2Compensation standards for house demolition and the attachments

5.1.2.1Compensation standards for house demolition

5.1.2.3Compensation standards for sparsely scattered trees

5.1.3Compensation standards for infrastructure and special facilities

5.2Estimate of dislocation compensation

Chapter 6Resettlement and Production and Livelihood Development

6.1General principles

6.2Specific measures for resettlement

6.2.1Resettlement measures for land acquisition

6.2.2Resettlement measures for house demolition

6.2.3Resettlement measures for commercial shops

6.2.4Enterprise resettlement measures

6.2.5Resettlement measures for vulnerable groups:

6.2.6Relocation and construction planning for special facilities

Chapter 7Implementation Plan of Resettlement

7.1Procedures of implementation

7.1.1Land acquisition and compensation

7.1.2Production recovery and allowance appropriation

7.1.3House demolition and reconstruction

7.1.4Rehabilitation of special projects

7.2Schedule

7.3Funds appropriation

7.3.1Appropriation principle

7.3.2Organizations in charge of resettlement finance

7.3.3Funds flow

Chapter 8Organizations

8.1Organization frame

8.2Resettlement agency

8.3Responsibilities of organizations

8.3.1Responsibilities of Mianyang Science & Education Pioneer Park Project Leading Group

8.3.2Responsibilities of the Land Acquisition, House Demolition and Resettlement Office of the STCDI Group

8.3.3Responsibilities of the Resettlement Office of the Sub-district Office

8.3.4Responsibilities of communities

8.4Capacity building and staff training

Chapter 9Negotiation, Grievance and Participation

9.1Negotiation

9.1.1Project stakeholders

9.1.1.1Identification of Project stakeholders

9.1.1.2Analysis of major stakeholders

9.1.2Stage, ways and contents of public participation

9.1.3Participation during the mobilization stage

9.1.3.1Mobilization conference of the resettlement plan

9.1.4Public opinion survey

9.1.5Resettlement participation plan during implementation stage

9.2Dissemination and information publication

9.3Grievance channels

9.3.1Collection methods of grievance and complaints

9.3.2Grievance procedures

9.3.2.1Stage I

9.3.2.2Stage II

9.3.2.3Stage III

9.3.2.4Stage IV

9.3.3Principle of handling grievance and complaints

9.3.4Contents and ways of reply

9.3.4.1Reply contents

9.3.4.2Reply ways

9.3.5Recorded grievance and final feedback

Chapter 10Monitoring and Assessment

10.1Internal monitoring

10.1.1Purpose and task

10.1.2Organization and personnel

10.1.3Contents of monitoring

10.1.4Procedures of implementation

10.2Independent external monitoring and assessment

10.2.1Purpose and task

10.2.2Organization and personnel

10.2.3Key indicators of monitoring and assessment

10.2.4Method of monitoring and assessment

10.2.5Procedures

10.2.6Report preparation plan

10.2.6.1Resettlement Action Plan Report

10.2.6.2Progress report of resettlement

10.2.6.3Independent resettlement monitoring and assessment report

Chapter 11Power Matrix

Chapter 12Attachment

12.1Attachment 1Housing area list for the households affected by house demolition

12.2Attachment 2 List for attachments of households affected by house demolition

12.3Attachment 3 MFH [2008] No. 105

Chapter 1Overview

1.1Project description

Project Inspection Team of the World Bank (hereafter referred to as “WB”), who once came to Mianyang to inspect implementation of Mianyang subproject of WB loaned projects, confirmed periodic achievements in Mianyang subproject when exchanging views with Project Office of Sichuan Province. However, Project Manager, Mr. Suzuki, pointed out that the current project implementation had changed significantly compared to Feasibility Study Report which was approved by the WB in October 2006 so that the loans were not enough for all planned projects due to devaluation of USD against the RMB and increase of works paying ratio of WB loaned projects from 70% to 100% after Wenchuan Earthquake on May 12. Meanwhile, he recommended that the Employer not implement Contract Package MK1 and MK2 (Jiuzhou Avenue Flyover and North Section 3 of the 2nd Ring Road) of Science & Education Pioneer Park Project because they were not urgently needed for post-disaster reconstruction.

Mianyang Science and Technology City Development and Investment (Group) Co., Ltd. (hereafter referred to as “STCDI Group”) has analyzed investment of Mianyang subproject, the Science & Education Pioneer Park Project. The results show that only about 40 million yuan will be left after implementation of projects that have commenced and are to commence if the exchange rate is 6.83 and funding gap will reach to 138 million yuan if Contract Package MK1 and MK2 are continued. In addition, as required by the WB, before implementation of Contract Package MK1 and MK2, the municipal government must first construct 2.89km works in Section 4, 2nd Ring Road North with self-raised fund as it promised and submit reports such as Environmental Impact Assessment Report, Resettlement Report and Feasibility Study Report to the WB for approval according to relative requirements of the WB. The process will be rather complicated and it will cost much in early stage. Therefore, China Science and Technology City Committee recommends that:

·Suggestion of the WB Project Manager should be adopted. Loans from the World Bank should not be put into Contract Package MK1 and MK2 of Science & Education Pioneer Park Project, i.e. flyover of Jiuzhou Avenue and Section 2, 2nd Ring Road North.

·If the above two contract packages are not implemented, rest loans will be approximately 12 million dollars (approximately 91.86 million yuan based on the exchange rate of 1:6.83) and will be used in Infrastructure Project in Xinglong Area of Science & Education Pioneer Park within WB loaned projects. Related procedures will be submitted for approval as required by the WB during intermediate adjustment of WB loaned projects by STCDI Group.

·Municipal Development and Reform Commission should be requested to lead this project adjustment and cooperate with the WB, Provincial Development and Reform Commission and Provincial Project Office for confirmation and affirmance.

·After considering both suggestion of the WB and the actual situation, related departments at province and city levels have approved project adjustment suggestion. Hence, loan amount of Xinglong Area is increased to 110 million from more than 50 million.

The Project, WB Loaned Science & Education Pioneer Park Road Construction Project in Mianyang, Sichuan, is a comprehensive one in which road traffic, drainage, landscape projects are integrated. Project plan contents include subprojects such as roads, drainage, landscape and illumination. Road design is as per the planning and horizontal alignment is completely consistent with the planning. Current topography and landform of the Park is relatively complicated. Therefore, vertical elevation of roads is optimally adjusted based on the planning, with earth-stone works balance and quantities of works analyzed and flood control and drainage taken into consideration. Design of drainage works, which is based on master planning, is optimally adjusted as per pipe diameter and master planning after detailed hydrological computation. Main contents of landscape works is road greening. According to study in early stage of the Project and planning data adjustment, main works contents of Xinglong Area are roads of 4.61Km, rainwater and swage pipes of 9.22Km, landscaping, water and soil conservation, etc. Refer to Figure 1 and 2 for status quo of the Project.

Road works of Xinglong Area of Science & Education Pioneer Park mainly include works of 6 roads whose total length is 4607.192m, in which 1# Road 1045.26m, 2# Road 313.973m, 3# Road 1101.052m, 4# Road 625.964, 5# Road 1102.741m, and 6# Road 418.202m. Secondary trunk roads, including 1# Road, 2# Road, 3# Road, 4# Road and 6# Road, are mainly planed to be 26m and 20m in the width. Branch road is 5# Road and planed to be 16m in the width. There will be both sidewalk and traffic lanes on roads. Public buses will be considered after completion. Road traffic networks of Xinglong Area and traffic framework of Science & EducationPioneerPark will be formed after completion of those roads. Refer to Table 1-1 for details about the works.

Table 1-1Road construction scale in Xinglong Area

Description / Construction scale
Width of road (m) / Length of road (m) / Area of road (m2)
1 / 1# Road / 26 / 1045.26 / 27176.76
2 / 2# Road / 26 / 313.973 / 8163.298
3 / 3# Road / 26 / 1101.052 / 28627.352
4 / 4# Road / 20 / 436.25 / 8725
5 / 5# Road / 16 / 1102.741 / 17643.856
6 / 6# Road / 20 / 418.202 / 8364.04

Data source: Feasibility Study Report

Figure 1 (status quo of roads
planned in the Project) / Figure 2 (status quo of roads
planned in the Project)

The Project, WB Loaned Science & Education Pioneer Park Project, is a comprehensive one in which road traffic, drainage, landscape projects are integrated. Total investment of the Project is 113,523,300 yuan. For fund source of the Project, a loan of 16,105,410 dollars (110 million yuan in total) is applied to the World Bank and shortfall and compensation for land acquisition and house demolition will be raised by the Employer. See Table 1-2 for details of works cost.

Table 1-2Works cost of Xinglong Area

NO. / Contract No. / Contract description / Estimated works cost
RMB(× 10, 000 yuan) / Procurement mode / Remarks
1 / MY-LC-01 / 1# Road,2# Road,3# Road,4# Road,5# Roadand6# Road (including road surface, roadbed, pipeline, and illumination) / 8178.31 / NCB / Civil works

Data source: Feasibility Study Report

Science & EducationPioneerPark is under construction now and its construction period is determined to be 2 years preliminarily. Proposed WB loaned projects are to commence in 2010 and the year of 2009 is preparation period. There are design stage and construction stage. In the design stage, shop drawing design is proposed to be completed before August 2009. Construction biding is proposed to be in early August 2010, and construction completion in Jan. 2011 to Dec. 2011, with a construction period of 12 months. See Table 3 roads and works schedule of Xinglong Area for details.

Table 1-3Roads and works schedule of Xinglong Area

NO. / Detailed description / 2009 / 2010 / 2011
6 / 8 / 10 / 12 / 2 / 4 / 6 / 8 / 10 / 12 / 2 / 4 / 6 / 8 / 10 / 12
1 / Project establishment, approval and preliminary design
2 / Construction design and bidding
3 / Work related to house demolition, etc.
4 / Project commencement and infrastructure works completion
5 / Completion of road main body and supporting
6 / Acceptance

Data source: Feasibility Study Report

1.2Preparation ofResettlement Action Plan

Resettlement Action Plan (RAP) of the Project is prepared by Mianyang Science and Technology City Development and Investment (Group) Co., Ltd. with the assistance of Research Institute of Foreign Capital Introduction and Utilization, SouthwestJiaotongUniversity. Southwest Municipal Engineering Design & Research Institute of China is responsible for preparation of feasibility study documents of the Project.

With coordination of Mianyang Science and Technology City Development and Investment (Group) Co., Ltd., relocation office of Mianyang Science & Education Pioneer Park, affected communities and other departments, a group of 4 people from Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University carried out a 10-day socioeconomic survey on areas affected by the Project, providing detailed and practical data and information for preparation of RAP.

1.3Measures to reduce land acquisition and house demolition

1.3.1Planning and design stage of the Project

In construction of the Project, it is inevitable to involve land acquisition, house demolition and ressettlement and to affect orginial production and living conditions of local residents. In planning and design stage of the Project, Design Party and the Employer have taken some effective measures to recude impact of construciton of the Project on local residents.

1)In optimization and comparision of design plans, positive impact of construction of the Project on local social economy is considered as mush as possible and taken as a key factor in optimization and comparision of design plan. Because the Project mainly involves extension based on original projects, land acquisition and house demolition is reduced significantly compared to new road construction.

2)With construction design optimized and construction period shortened, house demolition and construciton and construction time are arranged properly.

1.3.2Construction stage of the Project

1)Publicparticipation system is strengthened. Before construction of the Project, commencement time and construction schedule of the Project are informed in form of bulletin in affected areas of the Project and resettlement areas. In addition, compensation policies of land acquisition, house demolition and resettlement are published for supervision of resettlers and host residents in resettlement areas.

2)Measures to reduce dust are taken. Water is sprinkled on surface of various construction roads in densely populated areas to prevent dust so as to get a clean and cozy environment on construction site and reduce impact of construction on surrounding environment if weather is fine during construction and it is windy. Moreover, Construction Party will adjust transportation route of earth and stone in time and avoid overload in loading and transportation. Construction Party will also take measures to ensure that earth will not drop during transportation to prevent environment tidiness being affected by dropped earth.

3)Waste at construction site is subject to proper disposal. A great deal of domestic garbage and various kinds of waste will be generated everyday at construction site because of long construction period and a great number of construction personnel. The Employer and Construction Party shall clean away domestic waste at construction site in time as required by local environmental sanitation agencies to ensure construction site is tidy and clean and to avoid infectious diseases breeding and spreading.

4)It will be considered to give priority to local materials during construction of the Project. If techniques permit, priority will also be give to local transportation and labors to directly benefit project-affected persons from construction of the Project.

1.3.3Resettlement Action Plan for land acquisition and house demolition in the Project and implementation stage

During implementation stage of land acquisition and house demolition in the Project, the following measures will reduce resettlement risks:

The RAP is prepared for infrastructure projects within scope of WB financed projects.

Collection of basic information will be strengthened to analyze status quo and future development of local social economy in depth. Practical and feasible resettlement measures will be developed based on actual situation in local area to ensure that living standards of affect persons will decrease due to construction of the Project.

With internal and external monitoring strengthened, efficient and smooth feedback systems and channels will be established. And information handling cycle will be shortened as much as possible to have various issues emerged in resettlement implementation solved in time.

Experience and lessons from resettlement of previous WB financed projects in the same area will be reviewed and drawn to reduce adverse impact of resettlement as much as possible.

Chapter 2Socioeconomic Survey

2.1Socioeconomic overview of project-affected area

The Project affects Xinglong Community of Pioneer Park Sub-district Office, MianyangScience & EducationPioneerPark.

2.1.1Socioeconomic conditions of MianyangCity

Mianyang is located at middle and upper reaches of FujiangRiver in northwest of SichuanBasin. Its geographic coordinates are latitude 30°42′N-33°03′N and longitude 103°45′E-105°43′E. Mianyang neighbors NangchongCity on the east,SuiningCity on the south, DeyangCity on the southwest, Aba Tibetan and QiangAutonomousPrefecture on the west, GansuProvince on the north and GuangyuanCity on the northeast. Baoji-Chengdu Railway and National Highway 108 run through the north to the south of Mianyang, with several provincial roads connected to neighboring regions and cities. Mianyang, a science and technology city under construction is a famous culture and science & technology city which has a long history and abundant culture and where modern science and technology and industries are very developed.

Mainyang has jurisdiction over Fucheng District, Youxian District, Anxian County, Santai County, Yanting County, Pingwu County and Beichuan County (6 counties in total) and governs Jiangyou City and Science City Office of People's Government of Sichuan Province on behalf of People's Government of Sichuan Province.There are 9 counties (cities/districts) and 1 county-level office in total in Mianyang, of which there are 127 villages, 121 sub-district offices, 3,458 rural communities, 11 urban sub-district offices and 288 residents' committee of sub-district offices.