WCU Design and Construction Department oversees the development of design and documentation for each project at West Chester University and establishes the standards to be incorporated into each project. In addition to these standards, Design Professionals shall prepare documentation of a project for implementation in accordance with these pre-established standards, and the requirements of Commonwealth of Pennsylvania, Pennsylvania State System of Higher Education (PASSHE or ‘the System’), and the Pennsylvania Department of General Services documentation standards (see respective websites for details).
On each project, theDesign Professional shallsubmitthe design checklist (attached herein), alongwith thedeliverablesattheend of eachdesignphaseforUniversity’sreview.Thestatusof eachitemshallbeindicated on the design checklist,with acheckmarkmeaningtheitem hasbeensubmitted, or a written statement of justification for those items not included.
Eachitem requiredinapreviousphaseshallbefurtherdevelopedandsubmittedas partof thesubsequentphases.Submissions shall be made at the conclusion of each of the following phases (unless otherwise noted in the Professional’s contract):
-Programming/Planning Phase
-Sketch Design (may be omitted at the discretion of the University)
-Schematic Design Phase
-Design Development Phase
-Construction Documentation Phase
-Pre-Final Documentation Phase
-Final Documentation Phase
The following transmittal / checklist shall be completed and attached to each submission package in quantities as stipulated:
Page - 1
SCHEMATIC PHASE / DESIGN DEVELOPMENT PHASE / CONSTRUCTION DOCUMENTPHASE
GENERALCRITERIA
Schematic level design drawings
Scopeofworknarrative including outlineofrelevant specification sections
Comparisonofcapacitiesi.e.programmed space sfvs.designsf.
Listofapplicablebuildingcodes
Buildingcodereviewdescribingcomplianceformajorcodeissuesandbuilding systems
Listofanticipatedvariancerequests
Anticipatedbuildingandspaceoccupancy criteria
Lifesafetyegressplanswithidentificationof securityandaccesspoints
LEEDlevel goals and LEEDchecklist
Verificationstatementindicatingthedesign complieswiththeestablished WCU project program and cost criteria
MunicipalzoningandLandDevelopment review (if applicable)
Completion ofDEPplanningmodule(if applicable)
Additional information as determined by Professional (please identify) / Design development drawings
Outline specification including specific relevant specification sections
Final Land Development plans (if applicable)
Descriptionofconstructionphasing
Descriptionofproposedoccupancywithin constructionzone
Descriptionofwater/vaporbarrier
characteristicsofbuilding envelope (roofandexteriorwall) construction
Energymodeling study
ListingofDesigncriteria issueswhichdonotcomplywith WCUDesignGuidelines or program direction
SchematicPhaseReviewcommentsand responses, highlighting unresolveditems
Additional information as determined by Professional (please identify) / 50% construction drawings
95% construction drawings
100% construction drawings
Specification (see section below)
Documentsasrequiredbybuildingcodestoshowallowablemaximum capacity / egressineachroom
Listofallcoderequirements and relevant variancesfor project
If multiplealternates,provideclear indicationofthescopeofeach and estimated project impact (cost or time)
Identificationofconstructionphasing (if applicable)
Designdevelopmentor previous submittal reviewcommentsandresponses highlighting unresolveditems
UpdatedListofdesign criteria/concepts/details etc.whichdonot complywithWCUDesignGuidelines or program direction
Confirmation of LEED criteria(attach score sheet)
Additional information as determined by Professional (please identify)
WCU Design Submissions & Deliverables
(REV 2/2018)
page2 of 10
SCHEMATIC PHASE / DESIGN DEVELOPMENT PHASE / CONSTRUCTION DOCUMENTPHASE
SPECIFICATIONS
Systemandmaterialnarrativedescription
Listofanticipateddivisionsandsections
Initial list of anticipatedsolesourcespecifieditems
Additional information as determined by Professional (please identify) / Outlineorpreliminaryspecificationsindicating projectspecificfeaturesofmajorconstruction materials, major equipment, and preliminary componentmaterials
Refined listofsolesourceitems
product spec sheets of specific materials proposed for inclusion in project
Additional information as determined by Professional (please identify) / Completeproduct specification including proposed modifications to PASSHE Division One components
Confirmation of receipt of Sole Source approvals from PASSHE / State.
Additional information as determined by Professional (please identify)
SITE WORK
Siteplansincl. existingand new conditions
Building/ project outlines
Siteentrances, roadsdriveways
General parking,service vehicles, special useADAspaces
Loadingdock, serviceentrance locationswithtrashcompactoraccess routeandservicevehicle andcustodialaccess
Busstop/ shelter(ifapplicable)
Waste/recyclingcollection areas
Walkwaylocations
Siteutilities
Emergencyvehicleaccess,codecompliance,firedept.connection
Securityduringconstruction
Preliminarygradingplan
Stormwatermanagementplan
Preliminarysitelightingplan
PennDOTHighwayOccupancyPermit
Additional information as determined by Professional (please identify) / Design development site plans including all information previously provided and as supplemented herein
Final grading plan
Final stormwater management plan
Permanentexteriorsignage
Parking,roadwayplans/ elevations
Vehicularandpedestriantrafficcontrols
GradingPlan(s)
SiteLightingplans,equipmentcutsheets,andphotometrics
detailsof site fixturesand quipment
Utilityplans,elevationsdetailsforlocal governingagencyapproval
Soilerosionandsedimentationcontrolplans during andpostoccupancy
Sitelogisticsplan i.e. contractor mobilization,preliminarylimitofcontract,contractor accessandsite
Additional information as determined by Professional (please identify) / Final site plans including updates to all previous documentation and as supplemented herein
Finallimitofcontract
Areatrafficplanifmajorwalkways/ roadwaysareimpacted
Sitedevelopmentphasingplan
Constructionsiteaccess and utilization plan
Stagingarea
Constructionsignage
Sitedetailsincludinghardscape
Profilesforundergroundutilities
PipeSizes
ConnectionDetails
Final Land Development approvals from governing municipality
Additional information as determined by Professional (please identify)
WCU Design Submissions & Deliverables
(REV 2/2018)
page2 of 10
SCHEMATIC PHASE / DESIGN DEVELOPMENT PHASE / CONSTRUCTION DOCUMENTPHASE
LANDSCAPING
Schematic level landscape plans incl. existingand new conditions
LandscapingConcept
ExistingIrrigation
Additional information as determined by Professional (please identify) / Design development site plans including all information previously provided and as updated
IrrigationPlan
Landscape details and elevations
Preliminary plant schedules
Additional information as determined by Professional (please identify) / Final landscape plans including updates to all previous documentation and as supplemented herein
Protectionofexistingtreesandsignificantplantingsduringconstruction
Soilpreparationandplantingspecifications
LandscapeIrrigationDetailsandlegends
Additional information as determined by Professional (please identify)
STRUCTURAL
Structuralschematicplansincl existing and new conditions
Writtendescription,proposedmaterials, foundationtypes,designcriteria,designloads
Additional information as determined by Professional (please identify) / Foundationplan
FloorFramingplan/details
Roof framing plan/details
Large scale framingplansatuniqueareas
Schedules/details
StructuralSections
Additional information as determined by Professional (please identify) / Final structural drawings including updates to all previous documents and as supplemented herein
Beam,columnandslabschedules /details / notes / calculations
MEP equipmenthousekeepingpads
Additional information as determined by Professional (please identify)
BUILDINGEXTERIOR ENVELOPE
Exterior elevations showing new and/or existing conditions w/ materialdesignations
Overallbuildingcrosssections
Rooflayout
List of major building materials
Perspectives / renderingsforWCU review
Additional information as determined by Professional (please identify) / buildingelevations
Wallsections w/ parapet & coping details
Roofanddrainageplan
Exteriorentrances, window/fenestration details
Expansionjointlocations
Largescalebuildingcrosssections
Additional information as determined by Professional (please identify) / Final exterior elevations including updates to all previous documents
Roofdetails
ExteriorDetails
FlashingDetails
Controljointlocationanddetails
Additional information as determined by Professional (please identify)
SCHEMATIC PHASE / DESIGN DEVELOPMENT PHASE / CONSTRUCTION DOCUMENT
PHASE
INTERIOR COMPONENTS
Floorplans
Demolitionplansifapplicable.
Proposedroomnumberingschemetocomply w/ WCU standards
Areauseidentificationandsq. footage
Volumeanalysis
Mechanica,electricalservice areas
Preliminarylayoutofmajorspaceswithfixed equipment
Additional information as determined by Professional (please identify) / Design development drawingsincl info previously provided as updated
Updated floorplans
Large scale plans for special areasincl labs, classrooms, special teaching areas, toilet rooms, janitor closets/custodial equipment storage, breakrooms, kitchenettes
Interiorelevations and details
Reflectedceilingplans and details
Walltypes,fireratings,smokecontrolzones
Plan for removal of hazardous materials
Fixedseatinglayouts
servingkitchenareas
Preliminary equipment/furniturelayouts
Casework / fixed equipment plans & details
Preliminaryfinish schedule
Preliminarydoor/hardwareschedule w/ narrative electronic security hardware
Additional information as determined by Professional (please identify) / Final interior construction plans including updates to all previous documentation and as supplemented herein
Additional large scale plans, interiorelevations & details as required
Final finishschedules
Final doorhardwareschedules
Roomsignage
Scheduleofproposedmoveableequipment notindicatedonthecontractdocuments, but required prior to move-in
Scheduleofspecialty fixtures/equipment including lab, kitchen and relatedfixtures, whereapplicable
Final schedule of room and Identificationsignage.
Details as required for project specifics (identify)
ELEVATORS
Elevator & equipmentroomlocations
BasisofDesignDescription
Emergencypowerdetermination
Additional information as determined by Professional (please identify)
/ Elevatorshaftplans & details
Equipmentdescription
Additional information as determined by Professional (please identify) / Final plans including updates to all previous documents and as supplemented herein
Plan/details ofshaft, sumppits, equipment, car, door/frame details, support details, interior details
Descriptionofcontrolsandfixtures
ACCESSIBILITYREQUIREMENTS
Accessibleentrancelocations
POdoorlocations
Areasof Refuge / Updatedverificationdesignis incompliance withADAAGand WCU requirements / Updatedverification final designis incompliance withADAAG WCU requirements
WCU Design Submissions & Deliverables
(REV 2/2018)
page2 of 10
SCHEMATIC PHASE / DESIGN DEVELOPMENT PHASE / CONSTRUCTION DOCUMENTPHASE
HVAC
BasisofDesignforallsystemsincludingstrategiesto meetHVACgoals
Initialenergy calculations,forEnvelopePerformancecompliancereport
InitialASHRAE55ThermalComfortAnalysis– documentingintegratedthermalenvelopeand HVACdesign
Single linediagramsforeachair,hydronic, steam, condensate,andallothermaterials requiredtodescribethefundamentalconcept forthe mechanicalsystems
Indicationoftheamountofredundancyforall majorpiecesof mechanicalequipment
Schematicplans,sections,elevationsshowing majorequipmentlocations,andairintakeand dischargelocations
GrossHVACzoning, typicalindividualspacezoning,andoperatingschedulesofzoned areas.
Analysisof existingutilitiesandorHVAC infrastructurewithsummarylistingofrequired upgradestosupportnewwork
InitialASHRAE55ThermalComfortReview
Additional information as determined by Professional (please identify) / Design development documents including all information previously provided and updated
Preliminarycalculationsandloadsummaries with breakdownsformajorareas,subsystems andequipmentloads
Buildingairflowdiagramshowing inter-relationshipofairhandlersexhaustfans, ductrisers,and ductmainsandprimary dampers
Buildinghydronicandheatingsystem diagramsshowinginter- relationshipofheating/coolingequipment,heatexchangers,pumps,pipe risersandmainsandisolationand controlvalves
Locationsofaircontroldevicesi.e.damper alongwithshaftaccessrequirements
Ductlayoutoftypicalspaces w/ specialattentiontoclassroom/specialty areadesignrequirements forairdistributionandnoise
schedulesfor majorpiecesof equipment
Equipmentlocations, large scaleplans,sections,andelevations.
Documentation of system/equipment maintenance andservicerequirements
locationsoffiredampers, smokedampers,combinationF/Sdampers, andaircontroldeviceswithaccessprovisions
Controldiagramsforall mechanicalandplumbingsystems
Outlineofmajorcontrolsequenceof operation
Soundandvibrationcontrolanalysis, attenuationrequirements,andmethodsfor control
Additional information as determined by Professional (please identify) / Final mechanical systemdrawings including updates to all previous submissions and as supplemented herein
Indicateductsizesandairflowquantities relativetoeachroomincludingCFMinand outofalldoors
Detailedpipingandductdesignshowingallsizes, expansioncompensationand structuralsupportrequirements
Locationofcontrolpanels,transformers,lab airvalves,volumecontrolboxes,thermostats andcontrolvalves
Large scaleplansandsectionsshowingcoordinatedsystemsinconstrictedareas
Equipmentdetailsinclstructuralsupport andvibrationsisolationmethods
penetrationandsleevedetails
Spacezoningdiagrambysystem
Connectiontocampus firealarmandHVAC control andsecuritysystems
Finalequipmentschedules
Detailedcontroldrawings,includingclear differentiationoftraderesponsibilityfor controlpower,fireandcontrolpowerwiring
Detailedsequenceofoperationswithspecific setpointsforallcontrolloopsincluding connectiontofirealarm,campuscontroland securitysystems
Final designCalculations
FinalEnergymodeling
FinalHVACportionofEnergyPerformance complianceReport
Additional information as determined by Professional (please identify)
WCU Design Submissions & Deliverables
(REV 2/2018)
page2 of 10
SCHEMATIC PHASE / DESIGN DEVELOPMENT PHASE / CONSTRUCTION DOCUMENTPHASE
PLUMBINGPING
Singlelinediagramforeach plumbing system component incldomestic,sanitary,storm,gas, RO/DI,vacuum,processedwaterandother materialstodescribethefundamentalconcept forallplumbingsystems
Watersupply,stormand sanitaryleads
Majorequipmentlocations
Restroomlocations
Listofanyspecialsanitarywasteproducts
Listofrecommendedredundancy requirements
Additional information as determined by Professional (please identify) / Design development documents including all information previously provided and updated
Updateddesigncriteriaforplumbingsystemsincludingsetpoints,waterquality levelsetc.
Preliminaryfloorplansofmechanicalrooms with allcomponentsand serviceaccess
Preliminarypipingplanswithindicationof requiredserviceaccessareas
Meterlocations
backflowpreventionlocations
Fixtureschedules
Equipmentschedules(majorequipment)
Determineneedforpretreatmentofsanitarywaste
Additional information as determined by Professional (please identify) / Final plumbing drawings including updates to previous submissions as supplemented herein
Floorplansw/allcomponentsserviceaccess
Detailedpipingdesignw/pipesizes indicated
Foundationdrainlayout
Typicalplumbingdetailsincludingstructural supportrequirements
Equipmentpiping, penetrationsleevedetail
Waterriserdiagram,includingassumedfixture countsperfloorconnection
Waste/ventriserdiagramsincludingfixturecountsperfloorconnection
Designcalculations
Additional information as determined by Professional (please identify)
FIREPROTECTION(MECHANICAL)
Singlelinediagramsforfireprotection systemandnotationsasrequiredto describethefundamentaldesignconceptfor the system
Confirmation ofadequacyofserving utility
Locationofmainutilityconnection
Firepumpneedassessment,coordinatedwith Plant Operations and WCU EnvironmentalHealthandSafety
Sprinklerpiping layout
Proposedlocationsof firedepartment connectionsandtestheaders
Additional information as determined by Professional (please identify) / Design development system performance documents including all information previously provided and updated
Preliminarypipingplans
Preliminaryfloorplansofmechanicalrooms withallcomponentsandrequiredservice accessdrawntoscale
Additional information as determined by Professional (please identify) / Final fire protection systemdrawings including updates to all previous submissions and as supplemented herein
headerandriser layouts w/indicationofservices accessarea
Pipingdesignw/pipesizes, locationofzonevalves,drainshoseconnectionpoints
Designcalculations & criticalzonecalculation
Typicalsprinklerinstallationdetailsincluding structuralsupportdetails
Penetrationdetails
Additional information as determined by Professional (please identify)
WCU Design Submissions & Deliverables
(REV 2/2018)
page10 of 10
SCHEMATIC PHASE / DESIGN DEVELOPMENT PHASE / CONSTRUCTION DOCUMENTPHASE
ELECTRICALPOWERDISTRIBUTION
Electricaldemolition (if applicable)
Single linediagramswithequipmentratings
Manholeductbank buildingentry location
Exteriorequipmentlocations
Substation,generatorandelectricroom
locations as applicable
SubstationgeneratorandATSdescriptions
Preliminarysubstationandgeneratorroom plans
Panelnumberingschemes
Lightningprotectionanalysis
Specialsystemsandequipmentlistings
Additional information as determined by Professional (please identify) / Design development system performance documents including all information previously provided and updated
Manhole,ductbankandbldgentryplans/details
Normalpowerriserdiagramwithcircuit breaker,fuse,conduit,wiresizesandupdatedsinglelinediagram
Emergencypowerriserdiagramwithcircuitbreaker,fuse,conduit,andwiresizes
Groundingriserdiagram
Preliminaryfaultcurrentandcoordination
Substationstandarddetails
Listofequipmentproposedtobeonemergencyorstandbypower
ElectricalLoadcalculations
Preliminarypanelschedules
TypicalPanelarcflashandcolorcodelabels
Electricalequipmentlocationplans
Typicalelectricaloutletlocationplans
Planfortemporarypowerduringconstruction
Additional information as determined by Professional (please identify) / Final electrical powerdrawings including updates to all previous submissions as supplemented herein
Detailsofpowerservicetobuilding
Powerplans,includingprimarycable,raceways,feederconduits,electricalloads, duplexspecialreceptacles,branch circuitrydesign
EmergencyPowersystemplans.
Controlsanddetails
Connectionstootherbuildingsystems includingfirealarmsystems, HVACsystems,BASsystems,LAN
Detailsofnon-standardelectricalinstallations
Conduitandwiresizesforservices,feeders, andspecialbranchcircuits
Notesidentifyinglocationsof separateand sharedneutrals
SwitchgearandMCCelevations
Groundingdetails
Roofandpenetrationdetails
Settingsforcontractorfurnishedequipment
Additional information as determined by Professional (please identify)
WCU Design Submissions & Deliverables
(REV 2/2018)
page10 of 10
SCHEMATIC PHASE / DESIGN DEVELOPMENT PHASE / CONSTRUCTION DOC PHASELIGHTING
Generaldrawingnotes
Proposedlightlevels
Fixture,lampandcontrolsdescription
Preliminaryinterior and outdoor lightingplans
Additional information as determined by Professional (please identify) / Design development system documentsincl all information previously provided as updated
Interiora/ exterior lightingandcontrolplans
Fixturetypesandschedules
Controlsystemsandcontroldevicedescriptions
Typicalphotometriccalculations
Dimming,daylightingwithcalculationsandlowvoltagecontrolzonesdocumentation
Proposedlightingfixturecatalogcuts
EnergyCodeCalculations
Additional information as determined by Professional (please identify) / Final lightingdrawings w/updates to all previous submissions as supplemented herein
Interiorandexteriorlightingplansincl controlsystems,devices,lightingpanels, switchingandcircuiting, sequenceofoperations, schematicsandwiring diagrams
Installationdetailsstructuralsupport
Normaland Emergency lightingphotometrics
conduit/wiresizesfor lightingbranchcircuits
Additional information as determined by Professional (please identify)
FIREALARM
SystemDescription coordinated with campus proprietary system
FApanellocations
PreliminaryFAdeviceandappliancelocation plans / RiserDiagram
FApanel,device,andappliancelocationplans
Additional information as determined by Professional (please identify) / Final fire alarm drawings including updates to previous submissions as supplemented herein
DetailedFApanel,deviceandappliancelocationplansincludingductdetectors,fire / smokedampers,sprinklerflowtamper switches,monitorandcontrolmodules,door holdopens,doorlockreleases
Strobelightcandelaratings
DetailstoHVAC,firepump,fire suppression,electronic door systems
Detailedsequencesofoperations
Additional information as determined by Professional (please identify)
SCHEMATIC PHASE
CO / DESIGN DEVELOPMENT PHASE
MMUNICATIONS (VOICE,DATA, VID VID / CONSTRUCTIONDOCUMENT
PHASE
EO)
OMMUNICATIONS(VOICE,COMMUNICATIONS(VOICE,DATA,ANDVIDEOSYSTEMS)DATA,ANDVIDEOSYSTEMS)
SummaryofAccessandsecurityneeds
Manholeductbankandbuildingentry locations
TNSspacelocationplan
Riserdiagram
Preliminarycabletrayplans / Listofequipmentandpreliminarylayoutof telecommspaces
BackboardlocationsinTNSspaces
Racewayandgroundingriserdiagrams
ConduitandCabletraylayoutandsizes
Materialcutsheets
Typicalvoicedataandvideooutletlocations
Emergencyphonelocationsandtype
Courtesyphonelocations / Detailedvoicedataandoutletlocations
Detailsofservicetothebuilding
Floorboxschedule
Conduit,outletbox,andfloorboxinstallation
PoweroutletlocationsintheTNSspaces
FinalEquipmentracklocationintheTNS
spaces
SECURITY(AccessControlsSurveillanceandSecurityAlarms)
Systemdescriptions.AccessControls,
SurveillanceandSecurityAlarms
PanelLocations,rackandwallspace requirements
PreliminaryDeviceLocationPlans
NarrativeofSecuritySystemsneeds / RiserDiagrams
EquipmentlocationPlans
ElectronicSecurityEquipmentClosetLayout
EmergencyPhoneLocationsandtype / Detailedequipmentlocationplans
Equipmentschedules(includingalldevice specificationsandelectronicsecuritysystem specifications)
Concealedandexposedraceways
WiringDiagrams(Showquantity,typed,and spliceandterminationlocations)
InstallationDetails(Mustincludefielddevice installationdetails)
DetailedSequencesofOperations
Tradecoordinationdiagramsshowingclearly theresponsibilityofeachtradecontractor responsibleforsecuritysysteminstallation
PROJECT COST
Initial CostEstimate / Updatedcostestimate / UpdatedCostEstimate
WCU Design Submissions & Deliverables
(REV 2/2018)
page10 of 10