A senior planningengineer (Project Scheduling Professional PSP) with 11 years project management experience over a wide variety of projects, with good inter-personnel, communicative and team working skills. Seek environment where my skills and loyalty will be rewarded with career advancement and guidance.

Key skills and qualifications
  • Expert level with Primavera P6 and MS Project.
  • 4D Scheduling and construction simulation for sensitive projects
  • Planning and Scheduling Techniques for High-rise Buildings
  • Repetitive Projects Planning using (LOB Technique)
  • Logistics analysis and construction ability analysis
  • Resources Planning and Management
  • Preparation of multi-contractor programs
  • Cost Control & Earned Value Management
  • Delay analysis and Recovery Planning
  • Claims Preparation & Negotiating
  • Risk Management in Construction Projects
  • Estimation and Quantities Take off.
  • Shopdrawing Production and Review for Civil Construction Work.
  • Supervision and Approval of Construction Work.
  • MEP Construction Planning.
  • Infrastructure Construction Planning.

Career history

-

  • 4/2012 to Present

AMANA-BUILDINGS (DOHA-QATAR)

Senior Planning Engineer

(NEW DOHAINTERNATIONALAIRPORT-Airport Staff Access Control Facility-PKG 6201)(453,000,000 QR)

-Prepare Working Detailed schedules over 5000 activities.

-Prepare Detailed target schedules & Narratives to meet baseline schedule dates

-Review and approve subcontractors programmes & resource allocation planes and materials delivery dates ensure its meet the project’s requirements

-coordination meetings with subcontractors and technical department and construction department to ensure they meet of the project’s requirements

-Develop and maintain the progress/productivity reporting system.

-Prepare the weekly/monthly reports for the project

-Prepare Procurements planes and follow up dates with procurement department specially (Long lead Materials)

-Co-ordinate with the procurement department to update the latest equipment and material delivery dates for incorporation into the schedules.

-Liaise with Estimators and ensure that the man-hours in the schedules and progress databases reflect the current status

-Monitor and report the project’s productivity status, prepare productivity analysis and trends including KPI

-Monitor and report the project’s engineering activities and Materials & Drawing logs to ensure its meets the project’s Target Dates

-Monitor Engineer instruction and Change Order Log to study impacts for the project baseline schedule

  • 11/2009 to 3/2012

ARABTEC – NPC JV Co (Abu Dhabi- UAE)

Senior Planning Engineer (lead Planner for planning team)

(Nation Towers Abu Dhabi-Mixed Use property (Offices-Residential-Hotel-Mall-Ballroom) -TwinTowers (65-floors) with connecting bridge at level 55 and 35,000 m2 Podium)(1, 6,000,000,000 AED)

-Prepare Tender schedules & Master Schedules.

-Prepare baseline detailed schedule over 11000 activities with the planning Team.

-Prepare Detailed target schedules & Narratives to meet baseline schedule dates

-Review and approve subcontractors programmes & resource allocation planes and materials delivery dates ensure its meet the project’s requirements

-Coordination meetings with subcontractors and technical department and construction department to ensure they meet of the project’s requirements

-Develop and maintain the progress/productivity reporting system.

-Prepare the weekly/monthly reports for the project

-Prepare Procurements planes and follow up dates with procurement department specially (Long lead Materials)

-Co-ordinate with the procurement department to update the latest equipment and material delivery dates for incorporation into the schedules.

-Liaise with Estimators and ensure that the man-hours in the schedules and progress databases reflect the current status

-Monitor and report the project’s productivity status, prepare productivity analysis and trends including KPI

-Monitor and report the project’s engineering activities and Materials & Drawing logs to ensure its meets the project’s Target Dates

-Monitor Engineer instruction and Change Order Log to study impacts for the project baseline schedule

-Delay analysis using time impact method and window analysis method showing the concurrent delays and issue claim for time extension

  • 4/2008 to 11/2009

National Project & Construction Co-NPC (Abu Dhabi- UAE)

Senior Planning Engineer

Holyday Inn Hotel –Abu Dhabi 250,000,000 AED

Danet Abu Dhabi Mall –Abu Dhabi 150,000,000 AED

Prepare Tender schedules & Master Schedules for some projects in Abu Dhabi

-Prepare baseline Detailed schedules over 5000 activities .

-Prepare Detailed target schedules & Narratives to meet baseline schedule dates

-Review and approve subcontractors programmes & resource allocation planes and materials delivery dates ensure its meet the project’s requirements

-coordination meetings with subcontractors and technical department and construction department to ensure they meet of the project’s requirements

-Develop and maintain the progress/productivity reporting system.

-Prepare the weekly/monthly reports for the project

-Prepare Procurements planes and follow up dates with procurement department specially (Long lead Materials)

-Co-ordinate with the procurement department to update the latest equipment and material delivery dates for incorporation into the schedules.

-Liaise with Estimators and ensure that the man-hours in the schedules and progress databases reflect the current status

-Monitor and report the project’s productivity status, prepare productivity analysis and trends including KPI

-Monitor and report the project’s engineering activities and Materials & Drawing logs to ensure its meets the project’s Target Dates

-Monitor Engineer instruction and Change Order Log to study impacts for the project baseline schedule

-Delay analysis using time impacted method showing the concurrent delays and issue claim for time extension

  • 2/2007 to 4/2008

Integral Services Company I.S.C.O. (Kuwait)-(Oil and Gas)

Planning Engineer as a resource for KNPC (Kuwait National Petroleum Company)

(OfficeBuilding (Steel Structure) & Labor Hangers and Refinery Shutdown Plan) El Ahmady Refinery

-Responsible for preparing baseline schedules and resource allocation planes and Procurement planes

-Responsible for preparing baseline and target schedules for refinery shutdown process

-Responsible for all reports for clients including (weekly & monthly reports)

-Responsible for erection of office building (steel structure) and Labour Hangers

  • 2/2006 to 2/2007

El TAWFIC for Engineering and Trading Company(Alexandria – Egypt)

Project Engineer & Planning Engineer

(Residential Buildings and El Olimby Club Repairing Work)(1,000,000 EGP)

-Responsible for Supervise construction of 15 storey luxuryBuilding from foundation to handover to clients. From excavation work, CFA Piles, Piles Caps, shuttering, concrete, mechanical and electrical works, Finishing work and Building envelope work.

-Responsible for repairing Work for El Olimby Club including repair of 3 story stadium heavy reinforcement concrete frames and erection of Cabled roof steel structure, mechanical and electrical works, Finishing work and Building envelope work.

-Responsible for preparing baseline schedules and resource allocation in site (labour and machines)

-Responsible for quantities survey ,client invoices and subcontractor payments

-Responsible for all reports for clients including (weekly & monthly reports, as Built drawing)

  • 7/2002 to 2/2006

Engineering Consulting Office (El Dar) Drs. Ibrahim & Aly Eldarwish (Alexandria – Egypt)

Designer engineer

(Wide Varity of Residential Buildings Projects and El Faiom Sugar Factory )

-Prepare Master schedules for Some projects in Alexandria including (Multi-storeyConcreteBuildings , Luxury Villas, Industrial steel structure Buildings ,Infrastructure projects )

-Prepare Bill of quantities and Tender Documents for Some projects in Alexandria including (Multi-storeyConcreteBuildings , Luxury Villas, Industrial steel structure Buildings ,Infrastructure projects

-Prepare & Monitor Quality control planes for some large projects (Simian Saphire development & Liquid Neutral Gas( LNG) with Petrojet-Egypt ,Nubaria Sugar Factory,Nubaria Power Station and Rashid costal protection work)

-Design and supervise wide Varity of Residential Buildings in Alexandria.

-Participate in design and supervise some large industrial projects (El Faiom Sugar Factory and Nubaria Sugar Factory)

-Participate in prepare design drawing and review shop drawing wide Varity of projects.

-Review and approve Main contractor baseline schedules and weekly & Monthly Reports, Procurement Planes, resources planes.

Education and training
  • May2010 to July 2010

Project Management Professional (PMP) Course

-Project Planning & Scheduling

-Resources Planning and Management

-Earned Value Management

-Procurement Management

-Communication Management

-Quality Management

-Risk Management

  • Nov2009 to Mar 2010

Planning Scheduling Professional Certificate (PSP)

AACE International Institute

-Project Planning

-Project Scheduling

-Resources Planning and Management

-Earned Value Management

-Cost Control

-Technical Reports Writing

  • Sep2004 to July 2006

General Construction Engineering Post Graduate Diploma

Faculty of Engineering-Alexandria University, Egypt.

-Project Planning & Control

-Project Quality Control & Quality Assurance

-Construction Methods

-Construction Management

-Earthquake Engineering Design

-Advanced Soil Machines

-Engineering Programming Language (Fortran)

  • Sep1998 to July 2002

B.S.C Civil Engineering

Faculty of Engineering-Alexandria University, Egypt.

-Project Planning & Control

-Steel and Concrete Structural Design

-Construction Methods

-Construction Law and Contract Management

-Infrastructure Project Design & Construction

Computer skills
  • PRIMAVERA P3,P3e,P6 ,P6.8
  • Primavera Contract Management (Expedition) v 13
  • Primavera Risk Analysis(Pertmaster) V 8
  • MS Project 2010
  • AutoCAD 2010,Autodesk Quantity Takeoff, Archicad,Sketchup
  • MS Office Suite(Word,Excel,Powerpoint,Access)
  • EXCEL VBA
  • CSI (Sap ,Etabs ,Safe,orion)
  • Vico Constructor2008(4D Scheduling)
  • NavisWorks Manage 2010 (4D Simulation)

Personal details
  • Date of birth: 20 July 1980
  • License: Egyptian & Kuwait and UAElicense
  • Member of: PMI Institute ,AACE Institute
  • Languages: Arabic - English
  • References: Available on request