Ningbo New Countryside Development Project (NNCDP) Procurement Plan

I.General

1. Project information:

  • Country:The People’s Republic of China
  • Borrower:The People’s Republic of China on-lending to Ningbo Municipal Government
  • Project Name:Ningbo New Countryside Development Project
  • Project Number:P106956
  • Project Implementing Agency (PIA):

Fenghua City Investment Company ,

Ningbo Rural Wastewater Office

  • Project components:
  • ChunhuTownship Development Demonstration
  • Ningbo Rural Wastewater Management
  • Technical Assistance

2. Bank’s approvalDate of the procurement Plan [Original: April 8, 2011; Revision 1: 2011, Revision 2: August, 2012, Revision 3: August 2, 2013,Revision 4:October29,2013]

  1. Date of General Procurement Notice: August 31st 2009
  2. Period covered by this procurement plan: October 2013~ December 2014
II. Goods and Works and non-consulting services.
  1. Prior Review Threshold:

Procurement Type / Procurement Thresholds Proposed / Procurement Method / Prior Review Thresholds Proposed
Works / ≥US$25 million / ICB / All contracts
<US$25 million / NCB / First two NCB works contracts by each PIU irrespective of value and all contracts ≥US$ 15 million
<US$200,000 million / Shopping / N/A
Goods / ≥US$3 million / ICB / All contracts
US$3 million / NCB / First two NCB goods contracts by each PIU irrespective of value and all contracts ≥US$ 3 million
<US$100,000 / Shopping / N/A
  1. Prequalification.Post-qualification will apply to all the contracts.
  2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: No CDD components are proposed in this project.
  3. Reference to (if any) Project Operational/Procurement Manual:

Detailed provisions can be found in the procurement manual prepared by Ningbo PMO.

  1. Any Other Special Procurement Arrangements:

The project includes no components which are the subject of no-objection to retro-active financing.

  1. Procurement Packages with Methods and Time Schedule

See appendix 1.

III. Selection of Consultants
  1. Prior Review Threshold:

Procurement Type / Procurement Thresholds Proposed / Procurement Method / Prior Review Thresholds Proposed
Consulting Services / ≥US$300,000 / QCBS/QBS / All contracts
<US$300,000 / CQS / First contract for each selection method and all contracts ≥ US$ 300,000
asper paragraph. 3.8-3.10 of the Guidelines / Single source selection of Firm Consultant / All contracts
asper paragraph. 5.6 of the Guidelines / Single source selection of Individual Consultant / ≥ US$20,000
asper paragraph. 5.1-5.6 of the Guidelines / Individual consultants / Only in exceptional cases e.g. long term TA
  1. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $0.5 million equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
  2. Any Other Special Selection Arrangements:

The project includes no special selection arrangement.

  1. Consultancy Assignments with Selection Methods and Time Schedule

See appendix 1.

Appendix 1: Procurement Packages with Methods and Time Schedule

Updated Procurement Plan for NingboRural Wastewater Treatment Project

Contract NO. / Content / Base Cost (Y M) / Base Cost (US$ M1) / Procurement Method / Prequalifi-cation / Bank Review / Expected Bid-opening Date / Starting Date / Estimated Duration (in days)
NCWW.CP1-1 / Fenghua,4 villages / Planed / 7.78 / 1.18 / NCB / NO / Prior / 2010/3/3 / 2010/3/31 / 180
Actual / 6.48 / 0.98 / NCB / NO / Prior / 2010/5/5 / 2010/7/19 / completed
NCWW.CP1-2 / Ninghai,3villages / Planed / 5.32 / 0.8 / NCB / NO / Prior / 2010/3/3 / 2010/3/31 / 180
Actual / 4.52 / 0.68 / NCB / NO / Prior / 2010/6/11 / 2010/8/20 / completed
NCWW.CP1-3 / Xiangshan,2villages / Planed / 5.99 / 0.91 / NCB / NO / Prior / 2010/3/3 / 2010/3/31 / 180
Actual / 6.26 / 0.95 / NCB / NO / Prior / 2010/6/9 / 2010/8/20 / completed
NCWW.CP1-4 / Yuyao,5villages / Planed / 10.38 / 1.58 / NCB / NO / Prior / 2010/3/3 / 2010/3/31 / 180
Actual / 8.09 / 1.23 / NCB / NO / Prior / 2010/6/10 / 2010/9/16 / completed
NCWW.CP1-5 / First Batch household connection / 3.47 / 0.53 / NBF / NO / 2010/9/19 / completed
NCWW.CP2-1 / Fenghua,6 villages / Planed / 8.76 / 1.32 / NCB / NO / Prior / 2011/5/1 / 2011/6/1 / 270
Actual / 6.91 / 1.04 / NCB / NO / Prior / 2011/10/25 / 2011/12/29 / completed
NCWW.CP2-2 / Ninghai,9villages / Planed / 20.62 / 3.12 / NCB / NO / Post / 2011/6/1 / 2011/7/1 / 270
Actual / 20.03 / 3.03 / NCB / NO / Post / 2011/11/17 / 2012/2/24 / completed
NCWW.CP2-3-A / XiangshanⅠ,5villages / Planed / 8.4 / 1.27 / NCB / NO / Post / 2011/6/1 / 2011/7/1 / 270
Actual / 7.94 / 1.2 / NCB / NO / Post / 2011/11/23 / 2012/3/9 / completed
NCWW.CP2-3-B / XiangshanⅡ,4villages / Planed / 10.25 / 1.56 / NCB / NO / Post / 2011/6/1 / 2011/7/1 / 270
Actual / 9.16 / 1.39 / NCB / NO / Post / 2011/11/25 / 2012/1/13 / completed
NCWW.CP2-4 / Yuyao,5villages / Planed / 30.08 / 4.56 / NCB / NO / Post / 2011/6/1 / 2011/7/1 / 270
Actual / 23.81 / 3.61 / NCB / NO / Post / 2011/11/29 / 2012/3/21 / completed
NCWW.CP2-5 / Second Batch household connection / 7.57 / 1.15 / NBF / NO / 2012/2/13 / completed
NCWW.CP3-1 / Fenghua11 villages / Planed / 20 / 3.17 / NCB / NO / Prior / 2012/8/15 / 2012/9/30 / 270
Actual / 14.8 / 2.35 / 2012/8/14 / 2012/10/28 / Under construction
NCWW.CP3-2-A / Ninghai East5villages / Planed / 16.74 / 2.66 / NCB / NO / Prior / 2012/9/30 / 2012/10/30 / 270
Actual / 12.07 / 1.92 / 2012/11/29 / 2013/4/10 / Under construction
NCWW.CP3-2-B / Ninghai West5villages / Planed / 12.19 / 1.93 / 2012/9/30 / 2012/10/30 / 270
Actual / 7.56 / 1.2 / 2012/11/29 / 2013/3/19 / Under construction
NCWW.CP3-3 / Xiangshan6villages / Planed / 21.73 / 3.45 / 2012/9/30 / 2012/10/30 / 270
Actual / 19 / 3.02 / 2012/11/29 / 2013/3/19 / completed
NCWW.CP3-4 / Yuyao3villages / Planed / 16.54 / 2.63 / NCB / NO / Post / 2013/1/15 / 2013/2/15 / 270
Actual / 11.85 / 1.88 / NCB / NO / Post / 2013/1/15 / 2013/4/10 / Under construction
NCWW.CP3-5 / Third batch household connection / 6.34 / 1.01 / NBF / NO / 2012/9/25 / 270
NCWW.CP4-1-A / Fenghua5 villages / Planed / 6.49 / 1.06 / NCB / NO / Post / 2013/9/1 / 2013/10/15 / 270
Actual / 4.29 / 0.7 / 2013/11/7 / 2014/2/8 / Under construction
NCWW.CP4-1-B / Fenghua5 villages / Planed / 10.11 / 1.65 / 2013/9/1 / 2013/10/15 / 270
Actual / 5.88 / 0.96 / 2013/11/7 / 2014/2/8 / Under construction
NCWW.CP4-2-A / Ninghai 5 villages / Planed / 19.17 / 3.13 / NCB / NO / Prior / 2013/9/1 / 2013/10/15 / 270
Actual / 13.31 / 2.18 / 2013/11/5 / 2014/2/10 / Under construction
NCWW.CP4-2-B / Ninghai 4 villages / Planed / 19.23 / 3.14 / 2013/9/1 / 2013/10/15 / 270
Actual / 10.29 / 1.69 / 2013/11/5 / 2014/2/10 / Under construction
NCWW.CP4-3-A / Yuyao 3villages / Planed / 10.06 / 1.64 / NCB / NO / Post / 2013/9/1 / 2013/10/15 / 270
Actual / 6.94 / 1.14 / 2013/11/12 / 2013/9/28 / Under construction
NCWW.CP4-3-B / Yuyao 3villages / Planed / 17.79 / 2.90 / 2013/9/1 / 2013/10/15 / 270
Actual / 8.98 / 1.47 / 2013/11/12 / 2013/9/28 / Under construction
NCWW.CP4-4 / Fourth batch household connection / 14.05 / 2.29 / NBF / NO / 2013/10/15 / 270
NCWW.CP2013-1 / Xiangshan 3villages / Planed / 17.2 / 2.81 / NCB / NO / Post / 2013/11/25 / 2013/12/25 / 270
Actual / 10.31 / 1.69 / 2013/12/5 / 2014/2/18 / Under construction
NCWW.CP2013-2 / Xiangshan 3villages Household connection / 2.45 / 0.4 / NBF / NO / 2013-12-25 / 270
NCWW.CP2014-1 / Jiangbei 4villages / 15.91 / 2.60 / NCB / NO / Prior / 2014-3-10 / 2014-4-10 / 270
NCWW.CP2014-1-A / jiangbei 4 villages household connection / 2.59 / 0.42 / NBF / NO / 2014-4-10 / 270
NCWW.CP2014-2 / Fenghua 6 villages / 8.94 / 1.46 / NCB / NO / Post / 2014-3-10 / 2014-4-10 / 270
NCWW.CP2014-2-A / Fenghua 6 villages household connection / 1.38 / 0.23 / NBF / NO / 2014-4-10 / 270
Sub-total Contract Packages / 281.18 / 44.39