(a) whether all the power projects during the current Five Year Plan are being implemented as per the schedule fixed for the private companies in all parts of the country;

(b) how many power projects have been given to private companies in the country including West Bengal; and

(c) what is the time schedule fixed for completion of these power projects?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER,

COAL AND NEW & RENEWABLE ENERGY

( SHRI PIYUSH GOYAL )

(a) to (c): 55 thermal power projects and 14 hydro power projects have been given to private companies in the country during the 12th Five Year Plan. Out of these, one thermal power project is in West Bengal. The State-wise and project-wise details of commissioned projects/units and original/anticipated schedule of the balance projects/units is given at Annex-IA for thermal projects and Annex-IB for hydro projects.

********

ANNEX-IA

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO.1218 TO BE ANSWERED IN THE RAJYA SABHA ON 09.03.2015.

***********

(A) PRIVATE SECTOR THERMAL POWER PROJECTS COMMISSIONED DURING 12TH PLAN
S.No / State / Project Name / Implenting Agency / Unit No. / Capacity
(MW) / Commission-ing Date
1 / AP / Painampuram TPP / Thermal Power Tech Corporation Ltd / U-1 / 660 / 02.07.2015
2 / AP / SimhapuriTPP / Madhucon Projects Ltd / U-2 / 150 / 7.2.2012
3 / AP / Thamminapatnam TPP-I / Meenakshi Energy Pvt. Ltd / U-1 / 150 / 9.9.2012
U-2 / 150 / 17.04.2013
4 / Chhattisgarh / Akaltara (Naiyara) TPP / KSK Mahandi Power Company Ltd / U-1 / 600 / 13.08.2013
U-2 / 600 / 22.082014
5 / Chhattisgarh / AvanthaBhandar TPP, / Korba West Power Co. Ltd. / U-1 / 600 / 31.03.2014
6 / Chhattisgarh / Baradarha TPP / D.B. Power Ltd / U-1 / 600 / 23.02.2014
7 / Chhattisgarh / Kasaipalli TPP / ACB India Ltd. / U-2 / 135 / 21.06.2012
8 / Chhattisgarh / Ratija TPP / Spectrum Coal & Power Ltd / U-1 / 50 / 02.04.2013
9 / Chhattisgarh / Salora TPP / M/s VandanaVidyut / U-1 / 135 / 4.10.2014
10 / Chhattisgarh / Tamnar TPP ( Raigarh) / O.P.Jindal / U-1 / 600 / 3.10.2014
U-2 / 600 / 30.03.2014
11 / Gujarat / Mundra UMTPP / Tata Power Co. / U-2 / 800 / 25.07.2012
12 / Gujarat / Salaya TPP / Essar Power Gujarat Ltd. / U-2 / 600 / 13.06.2012
13 / Haryana / Jajjar TPP (MahatamaGandhi TPP) / CLP Power India Pvt. Ltd / U-2 / 660 / 04.11.2012
14 / Jharkhand / Mahadev Prasad TPP Ph-I / Adhunik Power Co.Ltd / U-1 / 270 / 19.11.2012
U-2 / 270 / 29.03.2013
15 / Maharashtra / Amravati TPP Ph-I / Ratan India Power Pvt Ltd. / U-1 / 270 / 25.03.2013
U-2 / 270 / 2/17/2014
U-3 / 270 / 29.01.2015
16 / Maharashtra / Bela TPP-I / IEPL / U-1 / 270 / 20.03.2013
17 / Maharashtra / Butibori TPP Ph-II / Vidarbha Industries Power / U-1 / 300 / 17.08.2012
18 / Maharashtra / DhariwalInfracture TPP / DhariwalInfracture (P) Ltd / U-1 / 300 / 11.03.2013
U-2 / 300 / 28.05.2014
19 / Maharashtra / EMCO Warora TPP / EMCO Energy Ltd.(GMR) / U-1 / 300 / 02.07.2013
U-2 / 300 / 27.08.2013
20 / Maharashtra / GEPL TPP / GEPL / U-1 / 60 / 09.08.2012
U-2 / 60 / 28.04.2012
21 / Maharashtra / Nasik TPP Ph-I / Ratan India Nasik Power Pvt Ltd. / U-1 / 270 / 25.02.2014
22 / Maharashtra / Tirora TPP Ph-I / Adani Power Ltd / U-1 / 660 / 09.11.2012
Adani Power Ltd / U-2 / 660 / 25.03.2013
23 / Maharashtra / Tirora TPP Ph-II / Adani Power Ltd / U-1 / 660 / 06.10.2013
24 / MP / Bina TPP / Bina Power Supply Co. / U-1 / 250 / 08.12.2012
U-2 / 250 / 31.03.2013
25 / MP / Sasan UMPP / Reliance Power Ltd. / U-2 / 660 / 18.12.2013
U-3 / 660 / 30.05.2013
26 / Orissa / Derang TPP / JITPL / U-1 / 600 / 05.10.2014
27 / Orissa / Kamalanga TPP / GMR / U-1 / 350 / 28.03.2013
U-2 / 350 / 28.09.2013
U-3 / 350 / 21.03.2014
28 / Orissa / Sterlite TPP / Sterlite Energy Ltd. / U-4 / 600 / 25.04.2012
29 / Punjab / Rajpura TPP ( Nabha) / Nabha Power Ltd / U-1 / 700 / 24.01.2014
U-2 / 700 / 7.06.2014
30 / Punjab / Talwandi Sabo TPP / M/s Sterlite / U-1 / 660 / 17.06.2014
31 / Rajasthan / Jallipa-Kapurdi TPP / Raj West Power / U-5 / 135 / 02.05.2013
U-6 / 135 / 3/3/2013
32 / WB / Haldia TPP-I / M/s Haldia Energy Ltd. / U-1 / 300 / 14.01.2015
U-2 / 300 / 16.02.2015
(B) PRIVATE SECTOR THERMAL POWER PROJECTS UNDER CONSTRUCTION FOR COMMISSIONING DURING 12TH PLAN
S. No / State / Project Name / Implementing
Agency / Unit No / Capacity
(MW) / Original Commiss-ioning
Schedule / Anticipated Commiss-ioning Schedule
1 / AP / Bhavanpadu TPP / M/s East Coast Energy Ltd. / U-1 / 660 / Oct-13 / Mar-17
U-2 / 660 / Mar-14 / Oct-17
2 / AP / NCC TPP / NCC Power Projects Ltd / U-1 / 660 / Mar-15 / Apr-16
U-2 / 660 / Jun-15 / Aug-16
3 / AP / Painampuram TPP Corporation Ltd / Thermal Power Tech / U-2 / 660 / Aug-14 / Jun-15
4 / AP / Thamminapatnam TPP-II / Meenaksha Energy Ltd. / U-3 / 350 / May-12 / Aug-16
U-4 / 350 / Aug-12 / Nov-16
5 / AP / Vizag TPP Corp. Ltd / Hinduja National Power / U-1 / 525 / Jun-13 / Sep-15
U-2 / 525 / Sep-13 / Dec-15
6 / Chhattisgarh / Akaltara (Naiyara) TPP / KSK Mahandi Power Company Ltd / U-3(2nd) / 600 / Dec-12 / Dec-15
7 / Chhattisgarh / Balco TPP / Bharat Aluminium Co. Ltd / U-1 / 300 / Feb-11 / Apr-15
U-2 / 300 / Nov-10 / Jun-15
8 / Chhattisgarh / Bandakhar TPP / M/s Maurti Clean Coal &Power Ltd / U-1 / 300 / Dec-12 / Mar-15
9 / Chhattisgarh / Baradarha TPP / D.B. Power Ltd / U-2 / 600 / Jul-13 / Aug-15
10 / Chhattisgarh / Binjkote TPP / M/s SKS Power Generation
(Chhattisgarh) Ltd. / U-1 / 300 / Mar-13 / Dec-15
U-2 / 300 / Nov-13 / Mar-16
U-3 / 300 / Feb-14 / 17-18
11 / Chhattisgarh / LancoAmarkantak
TPS-II / LAP Pvt. Ltd. / U-3 / 660 / Jan-13 / 17-18
U-4 / 660 / Mar-13 / 17-18
12 / Chhattisgarh / Nawapara TPP / M/s TRN Energy Pvt. Ltd. / U-1 / 300 / Dec-13 / Jan-16
U-2 / 300 / Apr-14 / Apr-16
13 / Chhattisgarh / Salora TPP / M/s VandanaVidyut / U-2 / 135 / Sep-11 / Apr-15
14 / Chhattisgarh / Singhitarai TPP / Athena ChhattisgarhPower Ltd. / U-1 / 600 / Jun-14 / Mar-16
15 / Chhattisgarh / Swastic TPP / M/s ACB / U-1 / 25 / Jun-12 / Mar-15
16 / Chhattisgarh / Uchpinda TPP / RKM Powergen Pvt. Ltd / U-1 / 360 / May-12 / Apr-15
U-2 / 360 / Nov-12 / Jul-15
U-3 / 360 / Feb-13 / Dec-15
17 / Jharkhand / Mata shriUsha TPP-Ph-I / M/s Corporate Power Ltd / U-1 / 270 / May-12 / 17-18
U-2 / 270 / Jun-12 / 17-18
18 / Maharashtra / Amravati TPP Ph-I / Ratan India Power Pvt Ltd. / U-4 / 270 / Feb-12 / Mar-15
U-5 / 270 / Mar-12 / Sep-15
19 / Maharashtra / LancoVidarbha TPP / LancoVidarbha / U-1 / 660 / Jan-14 / 13th Plan
U-2 / 660 / May-14 / 13th Plan
20 / Maharashtra / Nasik TPP Ph-I / Ratan India Nasik Power Pvt Ltd. / U-2 / 270 / Apr-12 / Mar-15
U-3 / 270 / Jun-12 / Jun-17
U-4 / 270 / Aug-12 / Nov-17
U-5 / 270 / Oct-12 / Mar-18
21 / MP / Anuppur TPP Ph-I / MB Power MP / U-1 / 600 / Apr-13 / Mar-15
U-2 / 600 / Aug-13 / Jul-15
22 / MP / Gorgi TPP ( DB Power) / D.P Power ( MP) Ltd / U-1 / 660 / Jun-13 / 13th Plan
23 / MP / Seioni TPP Ph-I / Jhabua Power Ltd / U-1 / 600 / Mar-13 / Aug-15
24 / Orissa / Ind Bharat TPP ( Orissa) / Ind. Bharat / U-1 / 350 / Jun-15 / Jun-15
U-2 / 350 / Sep-15 / Sep-15
25 / Orissa / KVK Nilanchal TPP / KVK Nilachal / U-1 / 350 / Dec-11 / Feb-17
26 / Orissa / LancoBabandh TPP / LancoBabandh Power Ltd / U-1 / 660 / Apr-13 / 17-18
27 / Punjab / Goindwal Sahib TPP / GVK Power / U-1 / 270 / Apr-13 / Oct-15
U-2 / 270 / Oct-13 / Feb-16
28 / Punjab / Talwandi Sabo TPP / M/s Sterlite / U-2 / 660 / Jan-13 / Mar-15
U-3 / 660 / May-13 / Jul-15
29 / TN / Tuticorin TPP (Ind- Barath / IBPIL / U-1 / 660 / May-12 / Sep-17
30 / UP / Prayagraj (Bara ) TPP / Prayagraj power Gen.Co. Ltd(J.P.Power Ventures) / U-1 / 660 / Feb-14 / Oct-15
U-2 / 660 / Jul-14 / Jan-16
U-3 / 660 / Dec-14 / Apr-16
# - Work held up / RO/DM- Reverse Osmosis / Demineralised
HT- Hydro Test / GTG- Gas Turbine Generator
BLU- Boiler Light UP / STG- Steam Turbine Generator
TG- Turbine Generator / EDTA- Ethylene Damien Tierra Acetic Acid
AWPH- Ash Water Pump Home / RWPH- Raw Water Pump Home
BOP- Balance of Plant / HRSG- Heat Recovery Steam Generator
SBO- Steam Blowing Off / BTG- Boiler Turbine Generator
CHP- Coal andling Plant / NGT- National Green Tribunal
EPC- Engineering Procurement & Construction

*************

ANNEX-IB

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO.1218 TO BE ANSWERED IN THE RAJYA SABHA ON 09.03.2015.

***********

S. No. / Name of Scheme / State / Implementing
Agency / Capacity
(MW) / Original
Commissioning
Schedule / Actual / Anticipated Commissioning Schedule
A. / PRIVATE SECTOR HYDRO POWER PROJECTS COMMISSIONED DURING 12TH PLAN
1 / Budhil , U1-2 / Himachal Pradesh / LANCO / 70.00 / 2005-06 / 2012-13
2 / Chujachen ,U1-2 / Sikkim / GATI / 99.00 / 2004-05 / 2013-14
B. / PRIVATE SECTOR HYDRO POWER PROJECTS UNDER CONSTRUCTION FOR COMMISSIONING DURING 12TH PLAN
1 / Sorang, U1-2 / Himachal Pradesh / HSPCL / 100.00 / 2012-13 / 2015-16
2 / Tidong-I, U1-2 / Himachal Pradesh / NSL TIDONG / 100.00 / 2013-14 / 2016-17
3 / TangnuRomai, U1-2 / Himachal Pradesh / TRPG / 44.00 / 2014-15 / 2016-17
4 / Shrinagar, U1-4 / Uttarakhand / AHPCL / 330.00 / 2005-06 / 2015-16
5 / PhataByung, U1-2 / Uttarakhand / LANCO / 76.00 / 2013-14 / 2016-17
6 / SingoliBhatwari, U1-3 / Uttarakhand / L&T / 99.00 / 2015-16 / 2016-17
7 / Maheshwar, U1-10 / Madhya Pradesh / SMHPCL / 400.00 / 2001-02 / 2015-17
8 / Teesta St.III, U1-6 / Sikkim / TssetaUrja / 1200.00 / 2011-12 / 2014-16
9 / Teesta St. VI, U1-4 / Sikkim / LANCO / 500.00 / 2012-13 / 2016-17
10 / Rangit-IV, U1-3 / Sikkim / JAL Power / 120.00 / 2012-13 / 2016-17
11 / Jorethang Loop, U1-2 / Sikkim / Dans Energy / 96.00 / 2012-13 / 2014-15
12 / Bhasmey, U1-3 / Sikkim / Gati Infrastructure / 51.00 / 2012-13 / 2016-17

***********