Antoine

Taesik

Carissa

Unit cost estimation

We used Payback period method as described in the class material with 5 years of payback period assumption.

Unit cost = Variable cost +

Fixed cost / (P * Q)

P : Payback period

Q : Annual production volume

From the cost component table,

Variable cost: 3.83 [$/unit]

Fixed cost: $69,338

Annual production volume: 115,000 [units]

With a payback period of 5 yr,

Unit cost = 3.95 [$/unit]

Net Present Value calculation

We used the spreadsheet, “Econ DEMO-Stanley Hammer.”

The following table shows the parameter values for our economic analysis model. A period is one quarter of a year, and it gives 28750 units of sales volume per period. For simplicity, we did not consider the fact that the sales volume tends to change as a function of time. The currency unit is $1,000.

Since we are not dealing with the entire product development process, the development, testing, tooling and ramp-up cost are assumed to be the cost of assembly process/line. For Tooling and Ramp-Up cost, the estimated fixed-cost is used. Unit price is assumed to be $8 which is about 60% of US retail price ($13). We assume that the price does not change throughout our analysis periods (20 periods). Unit production cost was calculated above.

We did not assign much of the marketing cost considering the business environment of the clock mfg. company.

The following table summarizes the input values we used in Econ DEMO worksheet.

Investment (first two periods): $47,620

NPV: $888,000

Return on investment: 19

NPV value and Return on Investment turned out to be very high mainly due to the assumption of $8 sales price.

Cost of Parts/ Step per product
Step & Item / Cost/Item (cents)
Step #1
SS1 / $0.05
SS4-sub / $0.10
SS2 / $0.05
SS3 / $0.05
GB1 / $0.50
GB2 / $0.05
BSS1 / $0.05
BSS5 / $0.10
BSS2 / $0.20
BSS3 / $0.05
BSS4 / $0.05
SUM / $1.25
Step #2
GB3 / $0.25
GB3 / $0.25
FC3 / $0.10
FC4 / $0.10
FC5 / $0.20
Wires / $0.0014
SUM / $0.90
Step #3
FC2 / $0.05
FC1 / $0.15
BC1 / $0.15
BC2 / $0.05
BC3 / $0.10
BC4 / $0.05
Screws / $0.02
SUM / $0.57
Step #4
BC5 / $0.05
FC7 / $0.05
FC8 / $0.05
FC9 / $0.05
FC10 / $0.05
FC6 / $0.15
Screws / $0.02
SUM / $0.42
Total Material Cost per Product / $3.14
Labor Costs/Station
Hourly wage / $2.00
Vacation benefit / $0.04
Sick leave (1 day/month = 12/year) / $0.04
(assumption: if not sick gets more vacation)
Health & medical insurance/year / $0.83
Total labour cost per hour / $2.91
Daily labor cost for 8+1 operators / $210
Daily production volume / 383.33
Labor cost per unit / $0.55
Variable Cost / Quantity / Cost / unit
(work 50 weeks/year & 2300 cycles/week)
Workstation #1
Parts / $1.2500
8 oz. Bottles of Drip Oil / 1 every 500 cycles @$4/each / $0.0080
towel / 1 every 4600 cycles (2 weeks) @$2.50/tool / $0.0005
pen / 1 every 9216 cycles (2 months) @ $1/pen / $0.0001
laundry for towel / 1 every 384 cycles (1 day) @$.1/towel / $0.0003
$1.2589
Workstation #2
Parts / $0.9014
Soldering Alloy / $0.0100
$0.9114
Workstation #3
Parts / $0.5700
Glue / 2 every 768 cycles (2 days) @ $10/each / $0.0260
$0.5960
Workstation #4
Parts / $0.4150
$0.4150
Other Variable Costs
Labor cost / $0.5472
Energy costs / $0.0522
Shipping costs / $0.0500
$0.6494
Total Variable Cost (per unit) / $3.8308
Fixed Costs
Fixed Installation Costs
Purchase of Facilities and land to house assembly process / $30,000
Shelving for the storage room / $1,000
Company @ $25/hr (parts included in the price per hour)
Build 5 workbenches / 5 hours/bench / $625
5 feeders / 1 hour/feeder / $125
Bins (one for part and one to replenish the part) / 74 total @ $30/bin / $2,220
Tool costs
Step 1 Cast Iron Bell Fixture / $25
Step 1Tool for Ring Placement / $10
Step 1 Hammer / $5
Step 1 Hook for towel / $1
Step 1 Clipboard / $5
Step 2 Soldering irons / $132
Step 3 Electric screw drivers / $60
Step 4 Power supply (for inspection) / $100
Step 4 Electric screw drivers / $30
Cart / $10,000
Other costs
Insurance / $5,000 a year * payback period of 5 years / $25,000
Total Fixed Costs / $69,338
Unit Cost Calculation
Payback Period / year / 5
Yearly production volume / units / 115,000
Unit Cost / $/unit / $3.951
$0.12

x

Part 6b: Discrete event simulation of the line

The Cell Sim software was used to simulate the whole assembly line designed so far.

The actual floor layout and processes were simplified in order to become compatible with the software. In order to simplify the assembly model, parts were grouped in four categories, depending on where they are delivered on the plant (parts for the subsystem subassembly, for the soldering, for the clock assembly and for the front face). The graph would have been very hard to understand with a total of 32 different parts. The assembly model includes four “machines” (workstations actually), each with only once process. Their details follow and can also be visualized on the screen pictures in the next page.

MACHINES

1. Subsystem Assembly:

Input: “parts for subsystem assembly” from the part storage room

Process: proc1, assemble each subsystem

Output: queue formed by the feeders to step 2

Mean time: 69.94sec

Standard deviation: 5sec (normal distribution)

2. Soldering station: (4 different ones)

Input1: feeders from 1

Input 2: “parts for soldering” from part storage room

Process: proc1, solder subsystems and other parts together

Output: queue formed by the feeders to step 3

Mean time: 224sec

Standard deviation: 20sec (normal distribution)

3. Clock Assembly station: (2 different ones)

Input 1: feeders from 2

Input 2: “parts for clock assembly” from part storage room

Process: proc1, assemble soldered subsystems on front casing and close the clock

Output: queue formed by the feeders to step 4

Mean time: 135.14sec

Standard deviation: 13sec (normal distribution)

4. Front face and testing:

Input 1: feeders from 3

Input 2: “parts for front face” from Part storage room

Process: proc1, assemble hands and test the completed clock

Output: final product storage room

Mean time: 57.31sec

Standard deviation: 15sec (normal distribution)

QUEUES

Part storage room (4 items)

Parts for subsystem assembly, initial stock: 100

Parts for soldering, initial stock: 100

Parts for clock assembly, initial stock: 100

Parts for front face, initial stock: 100

Feeders from 1 to 2 (1 item)

Proc1 from Subsystem assembly, capacity 10, initial stock 0

Feeders from 2 to 3 (1 item)

Proc 1 from Soldering stations, capacity 10, initial stock 0

Feeders from 3 to 4 (1 item)

Proc1 from clock assembly, capacity 10, initial stock 0

Final product storage room (1 item)

Proc 1 from front face & testing, that is the completed clock, capacity 100, initial stock 0

No failure mode or scrap queues were introduced to simplify the model.

Here are a few results from a simulation with pace of 75 seconds and 100 cycles.

  • The bottleneck of the assembly line is the subsystem assembly station, utilization percentage is 100% as long as there are some input in the part storage room, and starving time is negative through the whole sequence. The reason for this is fairly simple: this station has the highest process time in the chain. Soldering stations have an average utilization ratio of 87, 83, 80 and 73% (it seems that when there are several workstations in parallel the algorithm assigns more work in the reverse order of the stations), the clock assembly stations 96 and 95% and the front face 78%.
  • Queues in between stations were already assumed of small capacity, but they never actually have more than one item in because the assembly is designed to flow constantly.
  • With a pace of 75 seconds, which was the assumed cycle time in the previous reports, derived from an assumed annual production volume of 115,000, it can be seen that the final product storage room fills quicker than the number of steps. That is because 75 seconds is higher than 69.94 seconds, the longest through-put time of the assembly, for the first workstation.

If the pace is lowered to 69.94 seconds, which is the lowest possible to avoid permanent starving of soldering stations, one clock is exactly produced at each cycle. This means that from our design, even with uncertainty of non zero standard deviations in the process times, annual production volume could be increased without changing anything to the floor layout and time efficiency increased. From 115,000 units with a cycle time of 75 seconds, production could reach 300*8*3600 / 69.94 = 123,500 clocks per year.