Table 4.1: the Age of Participants

Age / 19 / 20 / 21 / 22 / 23 / 24 / 25
Frequency / 3 / 12 / 14 / 12 / 10 / 9 / 0

Table 4.1: The age of participants

Year / Faculty / Total
FKASA / FKM / FKEE / FKKSA / FSKKP / FKP / FPT
1 / 0 / 2 / 2 / 0 / 1 / 0 / 0 / 5
2 / 13 / 5 / 1 / 2 / 3 / 0 / 1 / 25
3 / 2 / 2 / 3 / 4 / 4 / 0 / 0 / 15
4 / 4 / 3 / 2 / 3 / 3 / 0 / 0 / 15
19 / 12 / 8 / 9 / 11 / 0 / 1 / 60

Table 4.2: The education information of participants

Course / Frequency
Civil Engineering / 19
Mechanical Engineering / 8
Mechanical & Manufacturing Engineering / 0
Mechanical &Automotive Engineering / 4
Electrical (Electronics) Engineering / 2
Electrical (Power System) Engineering / 6
Chemical Engineering / 2
Chemical (Gas Technology) Engineering / 6
Chemical (Biotechnology) Engineering / 1
Computer (Software) Engineering / 7
Computer ( Computer System & Network) Engineering / 4
Manufacturing / 0
Manufacturing (Mechetronics) / 0
Occupational Safety and Health / 0
Industrial Technology Management / 1
Project Management / 0
Total / 60

Table 4.3: The courses of participants

No. / Statement / Strongly Disagree / Disagree / Agree / Strongly Agree / Total
1 / The construction delay is caused by improper planning. / 3 / 7 / 26 / 24 / 60
2 / The construction delay is caused by poor site management. / 1 / 3 / 41 / 15 / 60
3 / The construction delay is caused by inexperienced contractors. / 4 / 13 / 24 / 19 / 60
4 / The construction delay is caused by client's late payment. / 2 / 15 / 37 / 6 / 60
5 / The construction delay is caused by communication problems among parties. / 3 / 21 / 24 / 12 / 60
6 / The construction delay is caused by mistakes during the construction stage. / 2 / 15 / 29 / 14 / 60

Table 4.4: The statistics on causes of delay

No. / Statement / Rank / Total
1 / 2 / 3 / 4 / 5 / 6
1 / Time lost in shifting personal effects to the new hostel. / 7 / 3 / 15 / 13 / 7 / 15 / 60
2 / Lack of trust on the credibility of UMP providing facilities to students. / 6 / 8 / 10 / 11 / 12 / 13 / 60
3 / Experienced emotional distress and uneasiness throughout the whole construction period. / 7 / 10 / 9 / 6 / 14 / 14 / 60
4 / Time used in adapting to the new surroundings. / 9 / 14 / 6 / 10 / 17 / 4 / 60
5 / Have difficulty concentrating on studies before moving to the new hostel. / 15 / 12 / 9 / 10 / 6 / 8 / 60
6 / Money wasted in buying appliances or necessities to clean the new room. / 16 / 13 / 11 / 10 / 4 / 6 / 60

Table 4.5: The statistics on effects of delay

Figure 4.6: The major causes of delay construction

Figure 4.7: The effects that arose due to delay construction