1 / 03.06.13 / LD-193, Pitampura / Two rooms constructed at SF, brick walls, slab and columns demolished and made property unusable at ongoing stage.
2 / A-4/29, Paschim Vihar / Demolished the chajja on Mpl land at GF and also demolished the parapet walls and remove the railing at FF at ongoing stage.
3 / 04.06.13 / H-6, Udyog Nagar / Demolished the brick walls and also removed the tin shed in the shape of rooms at SF at ongoing stage.
4 / 31, Subh Enclave, Pitampura / Demolished/removed completely the shade which was holded & welded with M.S hollow pipe frame, covering the whole terrace at ongoing stage.
5 / 05.06.13 / CC-6B, Shalimar Bagh / Demolished/punctured projection on Mpl land at ongoing stage.
6 / CC-6C, Shalimar Bagh / Demolished/punctured roof slab of room at rear side balcony at ongoing stage.
7 / 116A, Kavita Colony / Demolished the front open space covered by RCC roof along with internal brick wall also at SF whereas the remaining portion in this property is old & occupied at ongoing stage.
8 / 06.06.13 / 1824, Multani Mohalla, Rani Bagh / Roof slab of top floor demolished/punctured at ongoing stage.
9 / AN-23B, Shalimar Bagh / Demolished/removed one slab & walls in front court yard with the help of gas cutter at ongoing stage.
10 / 07.06.13 / G&JU-93D, Pitampura / Demolished/removed all side walls over flat No. G&JU-93D at ongoing stage.
11 / RZF-43, Nihal Vihar / Demolished/removed the brick walls at GF completely at ongoing stage.
12 / RZF-18, Nihal Vihar / Demolished the projection in front at Mpl land at stilt floor and ground floor at ongoing stage.
13 / 10.06.13 / GH-14/417, Paschim Vihar / Demolished all new constructed wall in the shape of room in the front court yard at ongoing stage.
14 / GH-14/702, Paschim Vihar / Demolished newly constructed partition wall at ongoing stage.
15 / WZ-77, HariSinghPark / Demolished the projection on Mpl land at rear back side on stilt floor & ground floor and also cut the reinforcement at stilt floor with the help of gas cutter at ongoing stage.
16 / WZ-78, HariSinghPark / Demolished the projection on Mpl land at rear back side on stilt floor and cut the reinforcement with the help of gas cutter at ongoing stage.
17 / WZ-40, HariSinghPark / Demolished the projection on Mpl land at rear back side on ground floor at ongoing stage.
18 / 11.06.13 / B-10, Brij Vihar / Sealed under unauthorized construction.
19 / H.No. 143, gali No. 9, ShalimarBaghVillage / Demolished the brick walls at second floor in the shape of rooms at ongoing stage.
20 / 12.06.13 / BW-73D, Shalimar Bagh / Remove centering/shuttering in rear
court yard at ongoing stage.
21 / 12.06.13 / BW-73C, Shalimar Bagh / Demolished /remove the roof slab in rear court yard and made unusable at ongoing stage.
22 / H.No. 252, Pkt-I, Paschim Puri / Slab of one room constructed at the terrace of house cut down with the help of gas cutter & one toilet also demolished at ongoing stage.
23 / H.No. 229, Pkt-I, Paschim Puri / Slab of one room constructed at the terrace cut down with the help of gas cutter at ongoing stage.
24 / 13.06.13 / AD-62C, Pitampura / Demolished/removed all sides and partition wall at ongoing stage.
25 / WP-123B, Pitampura / Demolished/punctured projections on Mpl land. File No. 108/B/UC/RZ-I/13 dated 21.05.13 (Regular action).
26 / WP-123C, Pitampura / Demolished/punctured projections on Mpl land. File No. 108/B/UC/RZ-I/13 dated 21.05.13 (Regular action).
27 / 428, Rishi Nagar, Rani Bagh / Roof slab of one room at TF demolished/punctured at ongoing stage.
28 / 14.06.13 / A-5/362, Paschim Vihar / Demolished the projection on stilt floor and reinforcement cut with the help of gas cutter at ongoing stage.
29 / 17.06.13 / 89, LIC Colony, Paschim Vihar / Demolished the roof slab of rear opening at ground floor at ongoing stage.
30 / 99, Apna Ghar Society / Demolished roof slab of one room and roof slab of kitchen by way of cutting reinforcement steel using gas cutter. File No. 111/B/UC/RZ-I/12 dated 22.08.12 (Regular action).
31 / 18.06.13 / 97, Apna Ghar Society / Demolished roof slab of one room constructed at/on extended balcony in rear set back. File No. 81/B/UC/RZ-I/13 dated 01.02.13 (Regular action).
32 / Adj. to A-84, gali No. 5, ShivRamPark, Nihal Vihar / Demolished the projection and brick wall of front room at first floor at ongoing stage.
33 / Opposite to C-39, gali No. 5, ShivRamPark, Nihal Vihar / Demolished the projection in front and also demolished the brick wall of bathroom at projection at ongoing stage.
34 / 19.06.13 / J-38, Udyog Nagar / Demolished one bathroom newly constructed in front set back at ongoing stage.
35 / 20.06.13 / AG-140, Shalimar Bagh / Demolished/punctured roof slab in front side and one room at second floor at ongoing stage.
36 / 21.06.13 / H.No. 379 Block RZ-R, Nihal Vihar / Demolition roof slab partition wall of top floor was demolished and SF was punctured and made unusable at ongoing stage.
37 / 24.06.13 / WZ-844, Rishi Nagar, Rani Bagh / Demolished/ punctured roof slab at third floor and demolished partition walls at ongoing stage.
38 / WZ-480, Rishi Nagar, Rani Bagh / Demolished shuttering and all partition wall at FF at ongoing stage.
39 / 25.06.13 / GH-5&7/1152, Paschim Vihar / Remove c/s and demolish four column on the roof top of 1152 at ongoing stage.
40 / GH-13/312, Paschim Vihar / Demolish/punctured roof slab of one room at one point. File No. 87/B/UC/RZ-I/13 dated 05.03.13 (Regular action).
41 / 248, gali No. 3, ShalimarBaghVillage / Demolish the projection on ground floor & first floor on MplLand at ongoing stage.
42 / P.No 97A, ShalimarBaghVillage / Demolish the roof slab of one room at ground floor and also demolish the parapet walls at ongoing stage.
43 / 26.06.13 / A-5/114C, Paschim Vihar / Demolished one bathroom at top floor including walls at ongoing stage.
44 / A-5/113C, Paschim Vihar / Demolished roof slab of one room at top floor at ongoing stage.
45 / G&JU-93D, Pitampura / Room extended adjacent to mumty was demolished. File No. 104/B/UC/RZ-I/13 dated 29.04.13 (Regular action).
46 / 27.06.13 / BG-6/230B, Paschim Vihar / Demolish the construction carried out at BG-6/230B first floor completely . The construction was carried out up to roof level in the shape of brick work RCC column, fixing of chokets & windows etc. at ongoing stage.
47 / 28.06.13 / NP-10B, Pitampura / Demolished the roof slab of two room at roof top of flat No. NP-10B & reinforcement has been cut with the help of gas cutter. File No. 107/B/UC/RZ-I/13 dated 21.05.13 (Regular action).

JULY-2013

Sl. No. / Date / Property No. / Details of Action Taken at ongoing stage/misuse.
1 / 01.07.13 / GH-13/312, Paschim Vihar / Demolish roof punctured at one point and reinforcement cut by the gas cutter at two points. File No. 87/B/UC/RZ-I/13 dated 05.03.13 (Regular action).
2 / WZ-562, Rishi Nagar, Rani Bagh / Demolished roof punctured and removed partition wall at third floor at ongoing stage.
3 / 02.07.13 / KH.No. 282, gali No. 4, Indl. AreaShalimarVillage / Demolished the brick walls in the shape of room and also remove the shuttering on third floor at ongoing stage.
4 / A-6/91C, Paschim Vihar (Top floor) / Demolished roof slab of flat at ongoing stage.
5 / 03.07.13 / MU-49, Pitampura / Demolished slab on rear set back and room at IVth floor at ongoing stage.
6 / C-462, Ashok Mohalla, Nangloi / Demolished/punctured roof slab of basement floor at ongoing stage.
7 / 04.07.13 / BG-6/354, GF, Paschim Vihar / Demolished the front portion of DDA flat, covered in the shape of kitchen at ongoing stage.
8 / AD-7D, Shalimar Bagh / Demolished the roof slab of one room by way of cutting reinforcement. File No. 117/B/UC/RZ-I/12 dated 12.09.12 (Regular action).
9 / 05.07.13 / E-41, Mangolpuri Indl. Area-II / Demolished RCC projections & stair case on Mpl land, beyond the sanction building plan at ongoing stage.
10 / RZG-128, Mandir wali gali, Nihal Vihar / Roof slab at third floor and partition wall was demolished at ongoing stage.
11 / 08.07.13 / AD-54C, Pitampura / Demolished two room and roof slab & reinforcement has been cut with the help of gas cutter at roof top at ongoing stage.
12 / H-19, Udyog Nagar / Demolished the brick walls in the shape of boundary and also remove the windows in the second floor at ongoing stage.
13 / 09.07.13 / 99, Apna Ghar Society / Demolished roof slab of remaining portion and cut reinforcement by gas cutter and demolished partition walls. File No. 111/B/UC/RZ-I/12 dated 22.08.12 (Regular action).
14 / GH-5&7/811, Paschim Vihar / Demolish roof slab at shaft area. File No. 105/B/UC/RZ-I/13 dated 15.05.13 (Regular action).
15 / GH-5&7/812, Paschim Vihar / Demolish the walls and one toilet with bathroom at terrace and punctured roof slab at shaft area. File No. 106/B/UC/RZ-I/13 dated 15.05.13 (Regular action).
16 / 10.07.13 / BA-59, Shalimar Bagh / Demolished/punctured the roof slab in the shape of room and also demolished the parapet walls above the slab on SF at ongoing stage.
17 / Flat No. 23 & 24, Adrash Apartment, Paschim Vihar / Demolish projection on Mpl land at GF and reinforcement cuted down by gas cutter at ongoing stage.
18 / Flat No. 25, Adrash Apartment, Paschim Vihar / Demolish projection on Mpl land at GF and reinforcement cutted down by gas cutter at ongoing stage.
19 / 11.07.13 / Khasra No. 72/4, saini, Nihal Vihar / Projection on Mpl land demolished at ongoing stage.
20 / 11.07.13 / C-256, Chandan Vihar, Nangloi / Slab of GF has been cut down with the help of gas cutter at ongoing stage.
21 / JU-12C, Pitampura / One room and toilet was demolished at ongoing stage.
22 / 12.07.13 / 473, Pkt-I, Paschim Puri / Demolished completely a room at TF and demolished partition walls at SF at ongoing stage.
23 / 15.07.13 / BK-1/63, Shalimar Bagh / Demolished projection on Mpl land at stilt floor at rear set back at front set back at ongoing stage.
24 / 16.07.13 / D-806, Saraswati Vihar / Demolished brick walls, partition walls in the shape of bathroom on each floor beyond sanction building plan at ongoing stage.
25 / 17.07.13 / RZG-57, Nihal Vihar / Column and partition wall were demolished at ongoing stage.
26 / RZS-250, Nihal Vihar / Column and chajja of building has been demolished at ongoing stage
27 / 18.07.13 / 47C, Ekta Apartment / Extended room of flat has been demolished at ongoing stage.
28 / 19.07.13 / AD-95C, Pitampur / Demolished the roof slab of room constructing of roof top of lat at ongoing stage.
29 / AD-71C, Pitampura / Demolished the roof slab of room constructing of roof top at ongoing stage.
30 / JD-39D, Pitampura / Demolished the roof slab of two rooms constructing at roof top of flat at ongoing stage.
31 / JD-38D, Pitampura / Demolished the roof slab of room constructing at roof top of flat at ongoing stge.
32 / 22.07.13 / 67, Rishi Nagar, Rani Bagh / Demolished partition walls and punctured projection on MplLand at second floor and removed partition wall at third floor at ongoing stage.
33 / 337, gali No. 6, ShalimarVillage / Demolished the projection on SF at ongoing stage.
34 / 335, gali No.6, ShalimarVillage / Demolished the projection on GF at ongoing stage.
35 / 330, gali No. 6, ShalimarVillage / Demolished the projection on GF &FF at ongoing stage.
36 / 331, gali No.6, ShalimarVillage / Demolished the projection on GF at ongoing stage.
37 / 23.07.13 / GH-14/511, Paschim Vihar / Demolished the roof slab in front court yard at ongoing stage.
38 / GH-14/512, Paschim Vihar / Demolished the roof slab in front court yard at ongoing stage.
39 / GH-14/881, Paschim Vihar / Demolished the roof slab and projection on Mpl land at ongoing stage.
40 / GH-14/882, Paschim Vihar / Demolished roof slab and projection on Mpl land at ongoing stage.
41 / 24.07.13 / A-11, New Multan Nagar / Removed/demolished partition walls constructed at stilt floor. No. 209/B/UC/RZ-I/12 dated 17.12.12 (Regular action).
42 / FIU-170, Pitampura / One room completely demolished with wall top slab and partition wall at fourth floor at ongoing stage.
43 / FIU-171, Pitampura / Two room completely demolished at fourth floor at ongoing stage.
44 / FIU-172, Pitampura / One room at IVth floor wall, door are demolished and top roof punctured made unusable at ongoing stage.
45 / 25.07.13 / A-2/58, Paschim Vihar / Demolished the projection and brick wall of room partly. File No. 135/B/UC/RZ-I/13 dated 21.06.13 (Regular action).
46 / BG-6/298D, Paschim Vihar / Demolished partly the roof of room.File No. B-I/WZ/UC/12/47 dated 27.01.12 (Regular action)
47 / 26.07.13 / WP-240A, Pitampua / Punctured the roof slab at rear court yard at ongoing stage.
48 / 29.07.13 / B-83, Mangolpuri Indl. Area-II / Demolished column with reinforcement & brick wall at GF at ongoing stage.
49 / 47, Jyoti Apartment / Sealed under unauthorized construction.
50 / 30.07.13 / BP-3, Shalimar Bagh / Demolished the projection on MplLand at rear side at ongoing stage.
51 / 31.07.13 / 247, Rishi Nagar, Rani Bagh / Demolished/punctured roof slab of third floor and removed partition walls at ongoing stage.
52 / B-85/1, Rishi Nagar, Rani Bagh / Demolished roof slab of third floor and projection on Mpl land at TF at ongoing stage.

AUGUST -2013

Sl. No. / Date / Property No. / Details of Action Taken at ongoing stage/misuse.
1 / 01.08.13 / AS-14, Shiva Enclave / Demolished/punctured roof slab of one room at ongoing stage.
2 / B-117, LaxmiPark, Nangoi / Slab of second floor punctured & one toilet demolished at ongoing stage.
3 / 02.08.13 / BJ-6, East Shalimar Bagh / Demolished the brick walls and windows in front set back in the shape of bathroom on GF, FF & SF at ongoing stage.
4 / U&V-69D, Shalimar Bagh / Sealed under unauthorized construction.
5 / CB-11D, Shalimar Bagh / Sealed under unauthorized construction.
6 / LU-37, Pitampura / One room on fourth floor was completely demolished and one room made unusable at ongoing stage.
7 / 05.08.13 / 585, PKT-I, Paschim Puri / Demolished partly the RCC slab at second floor. File No. 136/B/UC/RZ-I/13 dated 21.06.13 (Regular action)
8 / 586, PKT-I, Paschim Puri / Demolished partly the RCC slab at second floor. File No. 137/B/UC/RZ-I/13 dated 21.06.13 (Regular action)
9 / 585 & 586, PKT-I, Paschim Puri / Demolished completely the one room at 4th floor and brick walls at 3rd floor at ongoing stage.
10 / B-679, Jawalapuri / Demolished walls at terrace of FF & shuttering of projection removed at ongoing stage.
11 / WP-53C, Pitampura / Back, side & font wall removed. File No. 123/B/UC/RZ-I/12 dated 13.09.12 (Regular action)
12 / 06.08.13 / BB-58D, Shalimar Bagh / Demolished roof slab at rear open court yard and slab made unusable at ongoing stage.
13 / BB-64D, Shalimar Bagh / Demolished/removed c/s & remove partition walls at rear court yard at ongoing stage.
14 / 07.08.13 / LP-11F, Pitampura / Demolished projection at back side and partition wall which was newly constructed at ongoing stage.
15 / RZB-95, Nihal Vihar / Top roof of second floor was completely demolished at ongoing stage.
16 / 08.08.13 / 751, Rani Bagh / Demolished projection and partition wall at SF at ongoing stage.
17 / 12.08.13 / A-6/279D, Paschim Vihar / Demolished/punctured roof slab of two room at top floor at ongoing stage.
18 / C-32, Punjabi Basti, Nangloi / Demolished slab of second floor at ongoing stage.
19 / 13.08.13 / B-92, Gali No. 8, ShalimarBaghVillage / Demolished the projection on MplLand and parapet wall at SF at ongoing stage.
20 / LU-39, Pitampura / Excess coverage from third floor roof was demolished at ongoing stage.
21 / 14.08.13 / C-185, Ekta Enclave / Demolished extended room of flat at ongoing stage.
22 / B-3/13, DDA Janta flat, Jwala Heri, Paschim Vihar / Sealed under misuse.
23 / 16.08.13 / 77, Tarun Enclave / Demolished RCC projection on MplLand at stilt floor & GF at ongoing stage.
24 / BR-65C, Shalimar Bagh / Demolished the roof slab and remove the c/s on chajjas and walls and doors /windows at ongoing stage.
25 / 19.08.13 / LD-36, Pitampura / Punctured the roof slab of front court yard & projection at ongoing stage.
26 / E-52 & E-57, Adhyapak Nagar / Column, partition wall and slab was demolished at ongoing stage.
27 / 21.08.13 / 364, Rishi Nagar, Rani Bagh / Demolished/punctured at third floor and MplLand at ongoing stage.
28 / GH-5&7/332, Paschim Vihar / Demolished back side projection on MplLand at rear court yard and reinforcement cut by the gas cutter. File No. B/UC/WZ-II/11/376 dated 04.07.11 (Regular action)
29 / GH-5&7/331, Paschim Vihar / Demolished back side projection on MplLand at rear court yard and reinforcement cut by the gas cutter. File No. B/UC/WZ-II/11/375 dated 04.07.11 (Regular action)
30 / GH-5&7/330, Paschim Vihar / Demolished the back side projection on MplLand at rear court yard and reinforcement cut by the gas cutter. File No. B/UC/WZ-II/11/374 dated 04.07.11 (Regular action)
31 / 22.08.13 / A-4/403, Paschim Vihar / Roof slab of two rooms at third floor is demolished/punctured at ongoing stage.
32 / MU-42, Pitampura / Demolished ground floor & railing.File No. 128/B/UC/RZ-I/12 dt. 19.09.12 (Regular action)
33 / MU-43, Pitampura / Demolished ground floor & railing.File No. 129/B/UC/RZ-I/12 dt. 19.09.12 (Regular action)
34 / MU-44, Pitampura / Demolished ground floor & railing.File No. 130/B/UC/RZ-I/12 dt. 19.09.12 (Regular action)
35 / 23.08.13 / 86, Shakti Vihar / Demolished RCC projection beyond sanction building plan at stilt floor & ground floor at ongoing stage.
36 / 26.08.13 / LD-37, Pitampura / Demolished the roof slab of side court yard. File No. 142/B/UC/RZ-I/13 dt. 01.07.13 (Regular action)
37 / 1364,Rani Bagh / Demolished/remove all partition wall at FF and demolished the projection at Mpl land at all floors at ongoing stage.
38 / 27.08.13 / AD-88C, Shalimar Bagh / Demolished one wall and remove door & window in balcony and remove wall toilet, which deviated standard building plan by DDA flats at ongoing stage.
39 / AM-78, Shalimar Bagh / Demolished projection at rear side on MplLand at stilt floor at ongoing stage.q
40 / AM-107, Shalimar Bagh / Demolished projection at rear side on MplLand at stilt floor at ongoing stage.
41 / MU-42, Pitampura / Parking floor and ground floor was demolished and reinforcement was cut with the help of gas cutter. .File No. 128/B/UC/RZ-I/12 dt. 19.09.12 (Regular action)
42 / MU-43, Pitampura / Parking floor and ground floor was demolished and reinforcement was cut with the help of gas cutter. .File No. 129/B/UC/RZ-I/12 dt. 19.09.12 (Regular action)
43 / MU-44, Pitampura / Parking floor and ground floor was demolished and reinforcement was cut with the help of gas cutter. .File No. 130/B/UC/RZ-I/12 dt. 19.09.12 (Regular action)
44 / 29.08.13 / 1349, Rani Bagh / Demolished/removed shuttering and punctured roof slab of third floor at ongoing stage.
45 / B-7, Main Market, ShalimarVillage / Demolished the roof slab of FF in the shape of room and also demolished the brick walls and doors raising above the FF at ongoing stage.
46 / 30.08.13 / GH-13/160, Paschim Vihar / Demolished roof slab of room, toilet, kitchen at the roof top of 160 and also remove walls at ongoing stage.
47 / GH-14/434, Paschim Vihar / Demolished front court yard roof and made unusable at ongoing stage.
48 / GH-14/435, Paschim Vihar / Demolished front court yard roof and made unusable at ongoing stage.
49 / BG-6/298D, Paschim Vihar / Demolished completely the remaining portion.File No. B-I/WZ/UC/12/47 dated 27.01.12 (Regular action)