Project Title –Project Progress Report

Name of Project : Project Progress Report
Project Name: / <name of project>
Completed by: / Reporting period: / To:
Date Completed: / Next Board meeting:
/ Headlines:
Reasons for change or lack of change:
If only one box gets read, it will be this one! It should include:
  • A brief explanation of the current status and trend since last period.
  • The one or two other tings that you really need others to know (both positive and negative)

Key Achievements / Next Period
Note the main achievements (typically this would be 3-6 bullet points – only include the detail that the programme needs to know about).
Use this box to note significant planned milestones that have been delivered and any unplanned (reactive) ones. / Main activities only – the Programme Office does not need to know about everything, just significant milestones, expected outcomes or communications events.
Slippage and remedial action / Issue or concerns
This should include:
  • Slippage that impacts upon benefit realisation or other workstreams or programmes.
  • Remedial action planned or on-going
  • Expected resolution date
N.B. slippage should have been reported to the Programme Office as soon as it is identified, to allow for an impact assessment to be carried out. / Note issues or concerns that are current or anticipated in the immediate future. It should include:
  • Major updates on already logged risk and issues.
  • Significant risks that are new or about to be realised (i.e. about to become an Issue
  • New problems or concerns (with the expectation that at the next meeting these will be either satisfactorily resolved or developed into formal risks / issues.
Note: this box should not simply be a list of key risks or issues from existing registers. Risks and issues should continue to be managed through maintained risk & issue registers and discussion at appropriate boards.

Key to Traffic Lights

Red / Highly problematic - requires urgent and decisive action.
Amber / Red / Problematic - requires substantial attention, some aspects need urgent attention.
Amber / Green / Mixed - aspect(s) require substantial attention, some good.
Green / Good - requires refinement and systematic implementation.