AMCP/7-WP/__

AERONAUTICAL MOBILE COMMUNICATIONS PANEL

WORKING GROUP C

Montreal, Canada

15-19 October 2000

Agenda Item 2: Overview of Recent Developments

STATUS OF RELATED ACTIVITIES IN RTCA

Presented by Brent Philips

1  INTRODUCTION

1.1  Activities in RTCA related to air/ground communications systems of interest to the AMC Panel have continued since the last report to WGC/1 (October 2000). This paper is an update of progress and document completions since that time.

2  DISCUSSION

2.1  The following are summaries of the status of communications-related products of RTCA and EUROCAE/RTCA. Previously approved products of each working body are not listed.

RTCA SC-165 -- AMSS (SATCOM)

AMS(R)S Data Link MASPS DO-270 approved 10 Oct 2001

(Generic for all systems)

DO-210D Change No. 2 SC-165 completed 3 Oct 2001

(GSO AMSS MOPS) PMC consideration 28 Nov 2001

DO-262 Change No. 1 SC-165 completed 3 Oct 2001

(NGSS AMSS MOPS) PMC consideration 28 Nov 2001

RTCA SC-172/EUROCAE WG47 -- Future VHF Digital Communications

MOPS, VDL Mode 3 DO-271 approved 12 October 2001

DO-224A MASPS Change No. 1 PMC approved 12 Oct 2001

MOPS, VDL Mode 2

Physical Layer only EUROCAE ED-92 approved ~ Jan 2001

Complete MOPS SC-172 completion Dec 2000

(EUROCAE test procedures proposal

under evaluation; may delay MOPS)

DO-224A MASPS Change No. 2 future work being assessed

RTCA SC-186 -- ADS-B

MOPS for 1090 MHz ADS-B DO-260 approved 13 Sep 2000

Application of Airborne Conflict DO-263 approved 14 Dec 2000

Management: Detection, Prevention

and Resolution

DO-260 (1090 MHz MOPS) Change #1 SC-186 completion Dec 2001

MASPS for Airborne Separation SC-186 completion June 2002

Assurance

MOPS for UAT SC-186 completion June 2002

MOPS for Airborne Surveillance and SC-186 completion June 2002

Separation Assurance Processing (ASSAP)

MASPS for Traffic Information SC-186 completion Mar 2002

Service, Broadcast

RTCA SC-188 -- HF Data Link

MOPS DO-265 approved 14 Dec 2000

MASPS SC-188 completion 19 Nov 2001

RTCA SC-189/EUROCAE WG-53 -- Air Traffic Services Safety and Interoperability Requirements

Guidelines for Approval of the DO-264 approved 14 Dec 2000

Provision and Use of ATC

Supported by Data Communications

RTCA SC-194 -- ATM Data Link Implementation

Concepts For Services Integrating DO-269 approved 12 June 2001

Flight Operations and Air Traffic

Management Using Addressed

Data Link

Future work: Next meetings 5-8 November 2001

WG1 Data Link Operations Concept and

Implementation Plan

WG2 Flight Operations and ATM Integration

WG3 Human Factors

RTCA SC-195 -- Flight Information Services (FIS) Communications

MASPS for FIS/B DO-267 approved 15 Mar 2001

DO-267 Change No. 1 SC-195 completed Oct 2002

RTCA SC-198 -- Next-Generation Communications (NEXCOM)

Response to the Report of the RTCA DO-273 approved 12 Oct 2001

Chairman's Committee on NEXCOM

Next-Generation Air/Ground Communi- DO-274 approved 12 Oct 2001

cations (NEXCOM), Principles

of Operation

Revised ToR adding: PMC approved 12 Oct 2001

· Principles of Operation for · SC-198 completion Jan 2002

VDL-3

· Transition plan for VDL-3 · SC-198 completion Mar 2003

Implementation

- - - - -

3