SITE MONITORING REPORT

Please find detailed below the report for the site monitoring undertaken on 23 Oct 2012. If you should have any queries or require any photographs taken on site please do not hesitate to contact me.

File Ref: 11 421 353 / Date: 23 Oct 2012 / Visit no: 2 of 4
Monitoring Officer: Claire Tomalin
Tel No: 01245 437541 / Time on site: 10:00 / Time off site: 11:30
Site Co-ordinator: Claire Tomalin / Tel No: 01245 437541
Site Name: Highwood Quarry, Little Easton
Operator: SRC
Site Representative: John Hilton - SRC
Permission no’s:
ESS/65/06/UTT & S106 legal agreement
ROMP Due: March 2026
Constraints:
Weather: Dry / Windy / Rain / Snow
Noise: Acceptable/ Not acceptable / N/A
Approach Roads: Dry / Dusty / Wet / Muddy / Flooded
Ground: Dry / Dusty / Wet / Damp / Muddy / Flooded
Access: Obstructed / Not Obstructed / Mud on Road / Ice
Wheel Cleaning: Washer / Spinner / Sweeper / N/A
Hose: In use / Not in Use / N/A
Machinery: Working / Not working / N/A
In correct position: Yes / No / N/A
Stockpiles: N/A
Bunds: Height/Weeds/Maintenance
Actions from last site visit:
Complete access ASAP and cease use of alternative accesses.
Comment: Access complete and in use
Install compensation borehole
Comment: Borehole installed
Submit Non-Material Amendment for revised soils/overburden locations
Comment: NMA submitted
Carry out noise monitoring and submit results ASAP
Comment: Still outstanding, submit as matter of urgency
Put in place protective fencing around retained trees
Comment: Still awaited
Progress diversion of PROW and install appropriate signage
Comment: Formal diversion being progressed by PROW of way team. Some signage on site and more proposed including information board
Form northern bund as soon as crop removed and soils dry & fable.
Comment: Northern bund being formed, not topsoiled as yet.
Plant groups of trees along BW20 and hedgerow on northern boundary in next available planting season.
Comment: Details of tree planting submitted.
Inspection results summary:
Access & Haul Road
The site access road complete and in use. There is a low point where water was partially across the haul road, drainage in this area needs addressing, so as to prevent any flooding in the future. JH has realised that gates opened outwards when they should open inwards.
B Lodge & garden
Refurbishment work on B Lodge continuing.
Extraction/Plant Area
Plant area stripped of overburden and plant in place and in commissioning phase. Office/weighbridge and mess facilities and staff parking in place. PROW fencing in place to direct users away from the site.
Planting & Screening
Hedgerow on northern boundary adjacent Bund 7 and planting of groups of trees along BW20, required before end of planting season. Concrete airfield road removed adjacent to Bund 7.
Water Management
Two silt lagoons have been formed and a fresh water lagoon. Additional fresh water drainage lagoon being created in the north of the site, this is within the NMA. Water from dig being dewatered into River Roding, query as to whether this should require a discharge licence from EA.
Compliance with Conditions/Clauses
Permission No. / Condition/ S106 clause No. / Scope of Condition and Action to be taken / Action to be taken by Operator or MPA/WPA
Officer
ESS/65/06/UTT / 3.2.1 / Water Monitoring & flow compensation scheme required prior to commencement – scheme submitted / On-going discussion between operator & MPA
ESS/65/06/UTT / 3.2.1 / Installation of compensation borehole required prior to commencement / Complete, clause to be discharged
ESS/65/06/UTT / 3.2.3 / Assessment Park Road Drain required prior to commencement– details submitted / To be discharged by MPA
ESS/65/06/UTT / 3.4.2 / Public Rights Of Way diversion – application submitted being processed by ECC PROW team / PROW progressing
ESS/65/06/UTT / 3.7 / Monitoring of deer populations from commencement – deer monitoring scheme submitted / To be discharged by MPA
ESS/65/06/UTT / 4 / Operator advised of commencement on 26 March 2012. / Operator to advice of first export of mineral and in future commencement of picture framing
ESS/65/06/UTT / 8 / Submission of measures to keep access clean – details submitted / To be discharged by MPA
ESS/65/06/UTT / 13 / Noise monitoring at 3 monthly intervals. 1st set of results outstanding / Carry out and or submit results as matter of urgency
ESS/65/06/UTT / 26 / Details of picture framing – details submitted / Subject to discussion with MPA
ESS/65/06/UTT / 29 / Dust management / To be discharged by MPA
ESS/65/06/UTT / 31 / Advanced planting details – details submitted / To be discharged by MPA
ESS/65/06/UTT / 33 / Retained trees require to be protected with fencing. / Operator
ESS/65/06/UTT / 45 / Details of maintenance of buffer zone – details submitted by operator / To be discharged by MPA
ESS/65/06/UTT / 49 / Warning signs for PROW – required to be installed / Operator
ESS/65/06/UTT / 62 / Bird management / Please submit bird records to MPA
Actions to be taken before next site visit:
Carry out noise monitoring and submit results ASAP
Put in place protective fencing around retained trees
PROW install appropriate signage. SRC considering putting in information sign with PROW/Permissive paths and interpretation of site. Welcomed by MPA.
JH hoping to sponsor roundabout, discussing with UDC/ECC
Bund 7 under construction but required to have gently outward face of 1:3 which did not appear to be the case on site.
Further explanation required with respect to the purpose of the additional balancing pond in the water management scheme and operator to speak to EA re discharge of water from void to ditch which leads to River Roding.
Note: The actions noted in this report are required in order to ensure adequate progress is made and to avoid potential enforcement action against a breach of planning control.