Template
Schedule of disturbance for mining activities
Environmental Protection Act 1994
Schedule of disturbance for mining activities
This template should be used to present the calculations when proposing the amount of financial assurance under the Environmental Protection Act 1994. This template has been designed for use by environmental authority holders who undertake mining resource activities, and to allow for the varying phases of rehabilitation and the associated costs.
1Related documents
This template should be used in conjunction with the guideline Financial assurance under the Environmental Protection Act 1994 (ESR/2015/1758[1]). Related forms include:
- Application for a decision about the amount and form of financial assurance payable (ESR/2015/17541);and
- Application to amend or discharge the financial assurance held for an environmental authority (ESR/2015/17521).
2Explanatory notes
This section provides further details and definitions to assist EA holders completing the schedule of disturbance table overleaf.
- Disturbance category—Each row should include the activity type that will result in significant disturbance.
- Rehabilitation category—Outlines the appropriate steps of rehabilitation for which an annual cost will apply.
- Established—Once the rehabilitation work has been completed it is expected that responsibility for the rehabilitated area continues to require management (e.g. weeding) for a period of 3 years, after which the area may be considered successfully rehabilitated and rehabilitation work is no longer needed. Information on what the department considers successful rehabilitation can be found in the guideline Rehabilitation requirements for mining projects (ESR/2016/18751).
- Unit rehabilitation costs—This column should be used to record the cost of carrying out rehabilitation work in dollars ($) per hectare (ha) of disturbance.
- For disturbance categories the costs should be associated with all activities necessary to stabilise and re-establish the landform, this should include removal of infrastructure, excavation or back filling.
- For rehabilitation categories the costs should be associated with stabilising topsoils and establishing vegetation and should include recontouring landform, re-establishing soil profiles, seeding and management of established vegetation (weeding/fencing).
Page 1 of 4 • ESR/2016/1903 • Version 1.02 • Effective: 31 MAY 2013Department of Environment and Science
Template
Schedule of disturbance for mining activities
June 2017 / June 2018 / June 2019Area category / Unit rehabilitation cost ($/ha) / Area (ha) / Rehabilitation cost ($000s) / Area (ha) / Rehabilitation cost ($000s) / Area (ha) / Rehabilitation cost ($000s)
A=Total lease area (A = B + C + D) / 4 500 / 4 500 / 4 500
B=Undisturbed area / 3 209 / 3 013 / 2 613
C=Cleared area / 180 / 200 / 245
D=Total area of significant disturbance (D = D1 + D2 + D3) / 1 111 / 1 287 / 1 642
D1=Disturbance category
Active pit / 33 000 / 240 / 7 920 / 245 / 8 085 / 260 / 8 580
Tailings / 28 000 / 100 / 2 800 / 110 / 3 080 / 115 / 3 220
Rejects/low grade ore / 22 000 / 22 / 484 / 25 / 550 / 28 / 616
Waste rock / 22 000 / 300 / 6 600 / 325 / 7 150 / 440 / 9 680
Infrastructure / 8 000 / 280 / 2 240 / 280 / 2 240 / 300 / 2 400
Stripped topsoil / 1 000 / 105 / 105 / 120 / 120 / 155 / 155
Contaminated land remediation / 5 000 / - / 2 / 10 / 3 / 15
Other:
D2=Rehabilitation category
Recontoured / 4 600 / 15 / 69 / 35 / 161 / 80 / 368
Topsoiled but not seeded / 2 000 / 2 / 4 / 23 / 46 / 28 / 56
Seeded / 260 / 12 / 3.1 / 65 / 16.9 / 140 / 36.4
Established / - Year 0 / 130 / 18 / 2.3 / 22 / 2.9 / 36 / 4.7
- Year 1 / 130 / 15 / 2 / 18 / 2.3 / 22 / 2.9
- Year 2 / 130 / 2 / 0.3 / 15 / 2.0 / 18 / 2.3
Site investigation report costs (if needed)
D3=Successfully rehabilitated / 0 / 2 / 17
T=Total Rehabilitation Cost / 20 230 / 21 466 / 25 136
MM=Maintenance and monitoring (5%) / 1 012 / 1 073 / 1 257
PM=Project Management (10%) / 2 023 / 2 147 / 2 514
CPI (3% of Total Rehab Cost) / 607 / 644 / 754
G=GST—10% of costs(T+MM+PM) if not included above / 2 327 / 2 469 / 2 891
Annual rehabilitation cost ($000s) / 26 199 (notmax) / 27 799
(not max) / 32 552
(max)
Page 1 of 4 • ESR/2016/1903 • Version 1.02 • Effective: 31 MAY 2013Department of Environment and Science
Template
Schedule of disturbance for mining activities
Disclaimer
While this document has been prepared with care it contains general information and does not profess to offer legal, professional or commercial advice. The Queensland Government accepts no liability for any external decisions or actions taken on the basis of this document. Persons external to the Department of Environment and Science should satisfy themselves independently and by consulting their own professional advisors before embarking on any proposed course of action.
Approved:31 May 2013 / Enquiries:
Permit and Licence Management
Ph. 1300 130 372 (select option 4)
Ph:13 QGOV (13 74 68)
Fax. (07) 3330 5875
Email:
Page 1 of 4 • ESR/2016/1903 • Version 1.02 • Effective: 31 MAY 2013Department of Environment and Science
[1]This is the publication number, which can be used as a search term to find the latest version of the publication at