Sample of Ramp-Up Plan
PROJECT MANAGEMENT
- Set Up Regular Project Team Meetings
- Prepare Project Plan
- Write Business Requirements
- Obtain Signoff for Business Requirements
PROCEDURES - Prudential
- Develop DRAFT Procedures for each aspect
- SME Review & Signoff of DRAFT Procedures
- Final Procedures Completed
- Final Procedures Published
PROCESS
- Identify all impact areas
- Assign Process Map accountabilities
- Facilitate preliminary training discussion
- Prepare grid with all process changes and impact
- Prepare staff impact doc for mgmt & staff
- Conduct Risk Assessment
- Finalize processes that will move to the vendor
- Facilitate Meeting with to obtain approval on process changes
- Determine licensing impacts associated
- Solution any licensing impacts associated
- "Prepare Implementation Plan (Which processes, when)"
- Attempt to obtain approximate volume numbers
- Request Prompt Changes (BRD)
- Request Routing Changes (BRD)
- Solution any manual steps that need to remain in the Home Office
HUMAN RESOURCES (VENDOR)
- Team Leaders & Quality Leaders
- Source for New Hires (Team Leaders/Quality Leaders
- Pre-Screen Resumes
- Complete Applications
- Complete Pre-Employment Testing
- Conduct Interview Process
- Evaluate Candidates
- Make Contingent Offers
- "Conduct Drug Test/Education/Background Checks, "
- Process New Hired Supervisors
- Associates
- Source for New Hires (Interviewers)
- Pre-Screen Resumes
- Complete Applications
- Complete Pre-Employment Testing
- Conduct Interview Process
- Evaluate Candidates
- Make Contingent Offers
- "Conduct Drug Test/Education/Background Checks, "
- Process New Hires
- Hire IT Support Staff
- Determine process for change management
QUALITY
- Quality - Technology (Monitoring System)
- Finalize application to be used for audio-visual recordings (I.e. Verint Ultra Select)
- Finalize reporting tools to be used (I.e. Cognos)
- Forward requirements for Quality Monitoring equipment
- Complete Administrative Set-up
- Implement Technology
- Finalize application to be used for Call Evaluation input
- Develop & Implement Cognos Reporting Cubes
- Quality - Resources
- Prudential Resources - required to support start-up)
- Determine resource requirements to review vendor calls
- Identify Resources to Review Vendor Calls
- Communicate to Resources to Review Vendor Calls
- Train Pru resources to review vendor calls
- Vendor Resources - required to support start-up
- Determine requirements to facilitate feedback on vendor calls & manage quality
- Identify resources to facilitate feedback & manage quality
- Train XX to access call evaluations & facilitate feedback sessions
- Prudential Resources - required to support post-start-up
- Determine requirements to review vendor calls (Pru Resources)
- Develop plan for Pru Call Coaches after vendor starts to review their own calls
- Vendor Resources - required to support post-start-up
- Determine requirements to review vendor calls (Vendor Resources)
- "Develop Plan to identify resources to review vendor calls, manage quality performance on-site"
- Quality - Process
- Evaluate AU calls using combined Call Coach evaluation
- Assess Call Quality review process/goals/results for both programs
- Define Call Quality review program process & goals for The vendor
- Ensure quality results are reported on AU scorecard
- Define review process for start-up
- Establish quality assessment meetings after live date
- Implement Call Quality Review process
- Develop and finalize transition plan for post-start-up
- Conduct Risk Assessment (Quality & Learning)
TRAINING
- Determine Requirements for Training
- Conduct Needs Analysis (Training)
- Identify Technology for Interactive (non-production) Training
- Identify All Required Training Access
- Secure Required Training IDs
- Complete the ID Profiles
- Deliver Training Ids to the vendor
- Confirm Testing Profiles Before Training
- Develop E-Learning
- Identify/Hire Programming Resources
- Determine Scope
- Obtain Screen Prints
- Document Lesson Requirements
- Quality Review & Submit to Programmer
- Programming
- Update Lessons
- Quality Review Programming
- Submit to Knowledge Planet for Integration
- Conduct Lesson Walk-through
- Test simulated lessons in production
- Define Requirements for Training Room
- Prudential to provide documentation for the training room requirements to The vendor
- Confirm Requirements are Met
- Prepare Training Materials
- Review Process Flows
- Ensure Consistency between Procedures and Training Program
- Design Curriculum
- Design Curriculum (Week-1)
- Design Curriculum (Week-2)
- Design Curriculum (Weeks-3 & 4)
- Secure Screen Prints
- Identify Training Technology Needs
- Determine Medical Terminology Program/Materials
- Determine training needs/plan for application
- Integrate xxx into Training Curriculum
- Partner with The vendor to ensure preparedness for xxx training
- Define plan for use of Desktop Screen Capture in Training
- Identify Access Requirements for Desktop Screen Capture
- Obtain Access to Calls in Desktop Screen Capture
- Walk-through Calls in Desktop Screen Capture
- "Screen, Select & Catalog Calls for Training"
- Develop Role Plays
- Develop Role Plays for Week-2 of Training
- Develop Role Plays for Week-3 of Training
- Develop Role Plays for Week-4 of Training
- Draft Training Schedule
- Confirm Length of Training
- Prepare Assessment Report
- Finalize - Training Schedule
- Schedule Train-the-Trainer Sessions
- Schedule Train-the-Trainer Sessions for Week-2 of Training
- Schedule Train-the-Trainer Sessions for Week-3 of Training
- Schedule Train-the-Trainer Sessions for Week-4 of Training
- Communicate Procedure for Switching Machines between Training & Production
- Copy/Ship Training Materials
- Copy/Ship Week-1 Training Materials
- Copy/Ship Week-2 Training Materials
- Copy/Ship Week-3 Training Materials
- Copy/Ship Week-4 Training Materials
- Conduct Train-the-Trainer Sessions
- Conduct Train-the-Trainer Sessions for Week-2 of Training
- Conduct Train-the-Trainer Sessions for Week-3 of Training
- Conduct Train-the-Trainer Sessions for Week-4 of Training
- Define transition & Training Plans for Phase-I CSRs moving into Phase-II
- Resources required to Support Training
- Identify Trainer(s) & Mentors
- Identify Trainer(s) & Mentors for Weeks-1-3 of Training
- Identify Trainer(s) & Mentors for Week-4 of Training
- Identify Mentors for Nest
- Identify the vendor Individual Who Will Participate in Training
- Communicate Requirements for Mentor Support During Nest
- Communicate Mentor Resources for Live Calls in Training
- Conduct Mentor Orientation
- Confirm Travel Plans for Trainers & Mentors (Weeks 1 & 2)
- Confirm Travel Plans for Trainers & Mentors (Weeks 3 & 4)
- Confirm Travel Plans for Trainers & Mentors (Weeks 5 & 6)
- Confirm Travel Plans for Trainers & Mentors (Weeks 7 & 8)
- Confirm Availability of Training Region
- Build Records for use in Training
- Trainer Verification of Training Region Functionality
- Update Curriculum to Reflect Training Policies in Training Region
- Train Class
- Deliver Training
- Prepare Evaluation Report
- MANAGEMENT TRAINING
- Establish Training Delivery Plan & Schedule
- Deliver Training
- Management Lotus Notes Training
- Conduct Risk Assessment (Training)
- Training (The vendor)
- Determine Number of Training Classes
- Determine Time and Size of Class
- Determine Location of Classes
- Confirm Length of Training
- Develop xxx Training Curriculum
- Provide Roster of New Hires
- Set up Training Room Per Requirements
- Confirm Receipt of Training Materials
- Identify Trainer(s) to Conduct xxx
- Develop Training Curriculum and Orientation For the First Two Days of Training
- Prepare Trainers for Delivery of Orientation and xxx Training
- Identify the vendor Management to Attend Training
- Conduct Training for the vendor Team Managers
- Define and Communicate to Prudential TM (Team Manager) Role in Training Class
PROCEDURES
- Review Existing Procedures
- "Identify ""Workaround"" Procedure Gaps"
- Identify Gaps Within New Process Flow
- Develop Draft Procedures
- Incorporate Scripting into Procedures
- Confirm Procedure Database Vehicle
- Ensure Vendor Access to Database
- Develop end-to-end Change Management Process
- Finalize end-to-end Change Management Process
- Add Vendor Processes to Pru Procedures
- Vendor Review Draft Procedures
- Finalize Draft Procedures
- Review / Test Draft Procedures by Representatives & Call Coaching
- Complete Final Procedures
- "Review ""generic"" Call Center Procedures & Determine which are needed for xxxx"
- Conduct Risk Assessment (Procedures)
PROCESS
- Provide script for the AT&T Network & PBX Announcements
- Establish Complaint / Escalation Process
- Review and revise process maps
- Finalize Process Delivery Maps
- Review process maps for application flow inconsistencies
- Confirm documented procedures are in place for all pieces of process
- Conduct Risk Assessment (Process)
- Finalize process that moves to the vendor (Phase-1)
- Finalize process that moves to the vendor (Phase-2)
- Prepare grid with all process changes and impact
- Confirm changes to end call scripting
- Determine Lotus Notes Access
- Lotus-Notes Access in Business Requirements
- "Determine Vendor Communication Tool (Agents, RUs)")
- Manual Processes
- Request a generic Lotus-Notes mailbox for The vendor - Management Team
- Determine vendor role vs. Pru
- Determine impact to Operations
- Facilitate discussion with Operations
- Determine Pru process vs. the vendor
BOC & Workforce Management
- Preliminary - Staffing Model
- Site visit a xxx customer that is using ACD & Call Logging functionality
- Provide the vendor with an online copy of the staffing model
- Forward requirements for call logging equipment
- Forward requirements for Call Management Software and how it integrates with the Phone Switch
- Ongoing - Staffing Models
- Preliminary - Shift Requirements
- Finalized - Shift Requirements
- Call Routing Tests
- Develop Real-Time Overview Procedures
- Staffing Requirements for Quality Reviews
- Deliver Call Center Management Training to Vendor
- Training on Vendor's ACD
- Develop Vendor Scorecard
- Deliver Data Requirements for xxx
- Develop Database Report from xxx Data
- Conduct Risk Assessment (BOC & Workflow Mgmt.)
- "Workforce Management (WFM, The vendor)"
- Procure Staffing Requirements from Prudential
- Determine WFM Resource Requirements
- Determine Training Needs for WFM Resource
- Hire WFM Resource
- Determine WFM Software to be Utilized
- Purchase / Program WFM Software
- Deliver Contract & Purchase Agreement to WFM for The vendor
OPERATIONS
- Confirm Hours of Operation
- Confirm Hours for JAX Operations
- Identify Call Types for Phase-I
- Define requirements for storage of recorded calls
- Identify Pru to Vendor "transfer method.
- The vendor to validate Staffing Models to ensure the accurate staffing numbers
- Determine requirements for upfront messaging and prompts for 800#
- "Define requirements for printers, faxes, copiers, etc."
- Key Performance Indicators
- Establish Key Performance Indicators
- Meet with The vendor & Communicate Key Performance Indicators
- Gain Management Approval of Key Performance Indicators
- Finalize Key Performance Indicators with Executive Approval
- Review Key Performance Indicators with The vendor
- Establish Reporting Requirements & Process
- Set up a separate account number for THE VENDOR Language Line
- Request Production IDs
- Deliver Production IDs to the vendor
- Ensure Interpretation Functionality (Language Line)
- Determine Call Recording Requirements
- Define Vendor Recording Procedures
- Develop Associate Scorecard
- Obtain template from Risk Management
- "Communication (Systems problems, procedural changes, escalated calls, Sys. Release information)"
- Business Continuation Plan (BCP)
- Review Current PRU Plan
- Develop BCP Strategy (Phase-I)
- Develop BCP Strategy (Phase-II)
- Present Vendor Plan (Phase-I)
- Signoff on Vendor Plan (Phase-I)
- Identify Key Remedy Contact for Vendor
- Notify Ops Assurance of project & timeline
- Conduct Risk Assessment (Operations)
RISK ASSESSMENT
- Initiate discussion with Risk Management to determine their involvement
- Initial meeting with Risk Management's representative to discuss plans for the Risk Assessment
- Populate template with high level categories that will be assessed
- Introduce template and expectations to the various teams. Also identify any additional high-level categories
- Teams to fully populate template
- Combine templates into one document
- Distribute template to team
- "Review template, Identify Gaps & add Privacy related items"
- Presentation to Project Managers and Project Owner
VENDOR - MANAGEMENT
- Establish Primary Contact List for xxx/PRU Functions
- Determine if Prudential pricing for Dell can be passed on to The vendor
- Provide list of key functions& contacts for Prudential & The vendor
- Notify xxx that the vendor will place ad
- Send interview process used by the Call Center
- Forward Solution/Hiring data & Process/Associate Checklist to The vendor
- "Provide information on vendors for testing e.g. math and reading comprehension tests, etc."
- Determine if it is OK for The vendor to conduct their own background checks. They do not do their own drug test – they are sent out
- Develop Vendor Scorecard
- Identify/Select Relationship Manager
- Identify Operations Liaison
- "Set up weekly operations meeting with vendor to discuss process, quality and productivity, etc"
- Ensure legal review for Desktop Licensing Agreements
- Care in the contract for arrangement with Overland Data Systems for: IT Room & Vendor Equipment
- Ensure the expenses for 800# is invoiced to the vendor
- Ensure costs associated with Lotus-Notes costs are included in pricing model & Business Case
- "Share philosophies for hiring leadership i.e. how, when, etc."
- Ensure contract considers coverage & indemnification as it relates to Prudential owned equipment
- Establish Monthly and Quarterly Review Process
- Contract
- "Establish Discounts, Penalties and Incentives"
- Complete Draft of Contract
- Obtain Contract Approval
- Conduct Risk Assessment (Vendor Mgmt.)
- Schedule first Quarterly Review of Vendor Performance
- Schedule Operational Review of Vendor
SYSTEMS / TECHNOLOGY
- Project Management
- Compile CTS Project Costs
- Receive budget approval
- Rescope
- Re-approve
- Compile Complete Costs (Essential)
- Create Cost Grid
- Prepare Application Development Costs
- Complete Cost Grid
- Approve Costs
- Compile Complete Costs (Non-Essential)
- Walkthru Business Requirements
- Prepare Application Development Costs
- Complete Cost Grid
- Approve Costs
- Compile Complete Costs CSONET Feedback (Non-Essential)
- Walkthru Business Requirements
- Prepare Application Development Costs
- Complete Cost Grid
- Approve Costs
- Establish meeting schedule
- Establish contact list
- Notify 4CSO of New Site
- Facilitate Physical Security Meeting
- Conduct Risk Assessment
- Provide Letter of Intent and Contract Support
- Facilitate Runbook Completion
- Change Management
- Meet with Release Mgmt and problem Mgmt
- Meet with Ops. Assurance on Problem Reporting
- Include xxx in Change Mgmt Process
- Determine Model Office Role for xxx Going Forward
- Implement 4CSO Process for xxx
- Project Closeout
- Training Support & Environment - Systems
- Identify and Document Training Business Requirements
- Review Training Requirements
- Provide capability for BCBT Bitmap Capture
- Receive Detailed Test Case Plan
- Provide Systems Support for Creating Test Cases
- Identify and Document Options for Training Environment
- Select Training Environment Recommendation
- Conduct Technical Training Meeting with Desktop Support
- Develop Training Environment Problem Reporting Process
- Develop Script for Production to Training Switching
- Create and Walkthrough Proposal xxx
- Review Proposal with xxx
- Build Script
- Build Out Training Environment
- Systems Test - Training Environment
- Systems Test - Training Ids
- Telecommunications
- Voice
- Provide RRN# for provisioning 800#
- Order 800 #
- Receive 800 #
- Install 800#
- Test
- Determine if Transfer Connect is needed
- Data
- Define Requirements
- Define Carrier
- Order Circuits
- Identify Hardware
- Acquire HW from Stock
- Confirm who is extending T1's from basement
- Confirm power supply requirements for Network
- Provide 4 crossover Cat5 cables between 2nd and 3rd floor switches
- Delivery of 2 T1s and POTS line
- Provide static IP for NAT
- Configuration of Cisco Equipment
- Ship Cisco Equipment to xxx
- Install Cisco Equipment
- Testing of both T1 circuits
- Make Go/No Decision to bring in Server Ops
- Server Infrastructure
- Application / Data
- Define Requirements
- Place Hardware Order
- Receive Hardware
- Build/Configure Hardware
- Ship Racks to xxx
- Ship Servers to xx
- Provide Segment information to Server Ops
- Receive Servers in xx
- Confirm power requirements
- Install Hardware and restore apps
- Setup 2 print queues
- Configure SMS Distribution
- Test
- Remove Unneeded Print Queues (If Necessary)
- Desktop Infrastructure
- Define Requirements
- Confirm Dell Extended Pricing to xxx
- Identify Hardware
- Order 1 Evaluation Machine
- Receive Machine
- Evaluate/Test Newer Desktop Model
- Place Hardware Order
- Receive Hardware
- Configure/Install Hardware
- Train Xxx Technical Specialist on Prudential
- Test
- Desktop Integration
- Preliminary assessment of DLL's
- Procure / Build Xxx Server
- Deliver Xxx Server to Prudential
- Facilitate Integration Meeting to discuss Xxx & Voice Apps
- Integrate Xxx Application
- Integrate Live Monitoring SW (CSO Image)
- Integrate Reporter Pro (CSO Image)
- Manual Installation of Reporter Pro on CTS Images (JAX/EHO)
- Manual Installation of Reporter Pro on CTS Images (Other Sites?)
- UAT Desktop Regression Testing
- UAT Desktop July Release
- "Test Xxx, Voice Print & Inter Tel Apps against live back end"
- Business Continuation Risk Assessment Issues
- Request Xxx BC Information
- Receive Xxx BC Information
- Security Exception for Xxx Password
- Information Security
- Conduct Security Risk Assessment
- Request Additional Security Information Xxx
- Receive Additional Xxx Security Information
- Define Security Requirements
- Mainframe requirements
- Restricted Lotus Notes with identifier
- Underwriter Sig File Update
- SOD/PIWD access (determine domains)
- Identify Special Global Groups
- "Research other secondary application requirements (Batch codes, Ace, Aids/Vista)"
- On-Site Xxx Technician Requirements
- Creation Of Training Ids
- Creation of Ids
- Create W2K accounts
- Update Underwriter Sig File Update
- Update SOD/PIWD Access
- Assign any special Global Group for server/share access
- Update all identified secondary application requirements
- Creation of Production Ids
- Secure Tech Production Ids
- Creation of Ids
- Create W2K accounts
- Create Lotus Notes
- Update Underwriter Sig File Update
- Update SOD/PIWD Access
- Assign any special Global Group for server/share access
- Update all identified secondary application requirements
- Add Supervisor users to Global Group for access to Verint
- Training
- Application Development / Integration
- Essential (Day-1) Changes
- Workflow Route Changes
- Define and Document Route Change Requirements
- Prepare Route Change Systems Specifications
- Develop Route Changes
- QA Route Changes
- UAT Route Changes
- Production Installation Route Changes
- Prudential - Xxx Integration (if necessary)
- Identify & Document - Business Requirements
- "Identify Systems Integrations Needs (data, timing,…)"
- Document Problem/Solution Recommendation
- Select Recommendation
- Document Business Requirements
- Schedule Project
- Systems Specifications
- Systems Specifications Walkthru Signoff
- Systems Code & Unit Testing
- Systems Testing
- Integration Testing with The vendor
- Update Installation Coordination Database
- Production Implementation
- Review Requirements
- Prepare Estimate and Scheduling Options
- Business Approval
- System Code & Unit Test
- QA (Quality Assurance)
- UAT (User Acceptance Testing)
- Evaluate Risks of the current transmission vehicle
- Business Operations Support
- Provide Xxx Feed information to BOC
- Provide copy of the Inter-Tel Databases
- Provide ability to link directly to the Inter-Tel databases
- Build Data Transmission Layer
- Live Test
TECHNOLOGY - THE VENDOR