REPAIR GEOTHERMAL CONDENSER WATER SYSTEMSOLICITATION N40085-18-R-8404

ATTACHMENT A

PRICE SCHEDULE FORM

Offerors must provide pricing for the following including all labor, materials, supervision and equipment for:

CLIN DESCRIPTION / PRICE ($)
0001 / BASE BID REPAIR GEOTHERMAL CONDENSER / WATER SYSTEM IN BUILDINGS 230, 232, AND 137 / QTY / UNIT / UNIT PRICE / AMOUNT
Repair Geothermal Condenser / Water System in Buildings: 230, 232, and 137; all work complete and in accordance with drawings and specifications but not including the work indicated or specified under CLIN 0002. / *See CLIN 0001 total next page
0001AA / REPAIR GEOTHERMAL / CONDENSER WATER SYSTEM IN BUILDING 230
/ QTY / UNIT / UNIT PRICE / AMOUNT
Repair Geothermal/Condenser Water System in Building 230; all work complete and in accordance with drawings and specifications but not including the work indicated or specified under CLIN 0001AB, 0001AC, 0001AD or 0002. / 1 / LS / $______/ $______
0001AB / REPAIR GEOTHERMAL / CONDENSER WATER SYSTEM IN BUILDING 232 / QTY / UNIT / UNIT PRICE / AMOUNT
Repair Geothermal/Condenser Water System in Building 232; all work complete and in accordance with drawings and specifications but not including the work indicated or specified under CLIN 0001AA, 0001AC , 0001AD or 0002. / 1 / LS / $______/ $______
0001AC / REPAIR GEOTHERMAL / CONDENSER WATER SYSTEM IN BUILDING 137 / QTY / UNIT / UNIT PRICE / AMOUNT
Repair Geothermal/Condenser Water System in Building 137; all work complete and in accordance with drawings and specifications but not including the work indicated or specified under CLIN 0001AA, 0001AB, 0001AD or 0002. / 1 / LS / $______/ $______
0001AD / REMOVAL OF ASBESTOS / QTY / UNIT / UNIT PRICE / AMOUNT
Removal of asbestos containing loose insulation from crawl space in Building230; all work complete and in accordance with drawings and specifications but not including the work indicated or specified under CLIN 0001AA, 0001AB, 0001AC or 0002. / 3 (est.) / CU YD / $______/ $______
*TOTAL FOR CLIN 0001 (0001AA, 0001AB, 0001AC, and 0001AD) / $______
0002 / OPTION 1 – DEMOLITION OF EXISTING BASE MOUNTED HEATING HOT WATER PUMPS / QTY / UNIT / UNIT PRICE / AMOUNT
Demolition of two existing base mounted heating hot water pumps and provision of two base mounted heating hot water pumps including associated valves and controls for Building 137; all work complete and in accordance with drawings and specifications. / 1 / LS / $______/ $______
TOTAL FOR CLIN 0002 / $______
TOTAL FOR CLIN 0001 AND 0002 / $______

GENERAL BID NOTES

a. Award will be made on the total sum of Contract Line Items. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.

b. The Government reserves the unilateral right to award CLIN 0002 to theContractor at the proposed price within 90 calendar days after thecontract award. A firm fixed proposed price is required for CLIN 0001 (to include 0001AA, 0001AB, 0001AC and 0001AD) and CLIN 0002. No provision is made for economicprice adjustment. If Options are exercised, the contract completiondate remains the same.

c. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206 (b) not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise the Option(s).

d. The Government may reject an offer as nonresponsive if it is materiallyunbalanced as to prices for the basic requirement and the optionquantities. An offer is unbalanced when it is based on pricessignificantly less than cost for some work and prices which aresignificantly overstated for other work.

e. If CLIN 0002 is exercised, additional bonding and consent of surety isrequired. Consequently, the Performance Bond must reflect 100 percentof the aggregate amount of all Items.

Offerors must complete the following:

Offers providing less than 90calendar days for Government acceptance of the Base Bid and all Options after the date offers are due will not be considered and will be rejected.

COMPANY NAME:

OFFER ACCEPTANCE PERIOD:

AMENDMENTS ACKNOWLEDGED:

Signature of OfferorDate