HVAC / Roofing Projects

Biella:

  • Contractor has installed nailers/insulation/ OSB / paper at sloped roof areas of

Building “D”. Gutter installation is underway.

  • Contractor has installed cap sheet at building “D” mechanical well.
  • Building “B” tear-off of shingles and flat is complete, installation and dens-deck has been installed in mechanical well and base sheet is schedule to follow next week.
  • Tear off of roof area “C” shingles is underway.


Insulation, OSB sheathing and paper complete and gutter installation underway on Building D roof. /
Mechanical well of building D cap sheet installed

Contractor has installed insulation and dens-deck in mechanical well of roof area B /
Contractor has completed tear off of shingles on building B and is in process of installing perimeter nailers

Hidden Valley:

  • Building “A” mechanical well and hog valleys tear off is complete and dried in.
  • Shingles have been installed on Portable Buildings “B”, “F” (portables), J1, K1, L1 and partial installation on Building “A”.
  • Contractor is installing cap sheet in well B7. Mechanical well A7 has been dried in.
  • Contractor is in process of tearing off breezeway roofs


Shingle roofs complete at portable buildings / Buildings A1, roof shingles installation complete.


Mechanical well B7 cap sheeting being installed. /
Building A undershot roof tear off is complete

Slater:

  • Henris Roofing has dried in 100% of the “F2” roof area and is installing cap sheet
  • ALCAL Roofing continues to install the high roof membrane. Detail work remains and they

are scheduled to be complete by 7/7/16.

  • Henris has completed tear off and dry in of 25% of the north roof.


Area F2 cap sheet installation in the field is underway / Gym high roof field is complete. Alcal has installed DensDeck on parpapet walls and smoke hatch curbs
Roof Area F2 at street side of gym (north) has been torn off, insulation, Dens-Deck and base sheeting installed
/
Roof Area F2 cap sheeting installation underway

Piner:

  • Tear-off of upper and lower roof areas of Building “F” complete.
  • Tear-off of Building “D” complete.
  • Installation of insulation, Dens-Deck, and base flashing at Building “D” is underway.
  • Installation of Insulation and Den-Deck at Building “F” high roof is underway.
  • Installation of insulation and Dens-Deck of building “F” lower roofs is scheduled for next week.
  • Installation of membrane over base flashing of Building “D” is scheduled for next week.


Building “F” high gym roof insulation and Dens-Deck installation underway /
Parapet wood nailer installation complete on Building F

Building “D” base flashing in the field complete, detail work around equipment is underway. Membrane installation is scheduled for next week /
Insulation, Dens-Deck and base flashing installation of field of bldg. “D” complete. Contractor is detailing around rooftop equipment.

Charter of the Arts:(Move to be completed 6/30/17)

Phase II:

  • Roof Paint in progress this week anticipated to be complete by mid next week.
  • Interior punch items corrected this week.
  • Project slated to be complete next week.

Phase III

  • Contractor was on hold for most of this week due to roof painting occurring for Phase II.
  • Traffic rated utility boxes installed within paving areas.
  • Contractor to re-mobilize next week.

New Utility Boxes Painting of Roofs

Bark placed on side of campus Site graded and sprinklers installed.

Monroe Modular HVAC Replacement & Roof Replacement:

  • Held Pre-Construction meetings with both the Roofing & HVAC contractors on 6/22/17.
  • HVAC contractor mobilized on 6/23/17. Started demo.
  • Coordination meeting between two contractors to be scheduled.
  • Roofing contractor will not start work until July 17th as it will only take 3-5 days to complete

their scope of work.

______

Stadium Projects at High Schools:

Piner Lights:

  • Plans into Division of State Architect for approval.
  • Preparing bid documents.

Maria Carrillo Field:

  • Interviews were held with multiple turf vendors with turf selection committee.
  • Turf Committee unanimously selected Act Global with Kaya Group.
  • Director reviewed all product data & background and found acceptable.
  • Final Design Review Meeting took place with Site Administration 6/21/17 all design

elements were captured per sites request.

Facilities is currently determining best delivery method.

______

Cook / Via Esperanza Portables for Head Start

  • Punch-list finalized 6/30/17.
  • Paving pending the install of shade structure, possible acceleration on the paving if performed in phases.
  • Electrical and alarms being worked on at this time.
  • Irrigation & sod to start after completion of shade shelter and paving.
  • Play Structure install to start after DSA approval.
  • Completion appears to be mid July.