Pipeline to the Sea

Feasibility Study — Phase 1

Prepared October 2008 by Tonkin Science Engineering

Published May 2011

Pipeline to the Sea: Feasibility Study - Phase 1

Prepared for the former Murray-Darling Basin Commission by Tonkin Science Engineering
Published by Murray-Darling Basin Authority
Postal Address GPO Box 1801, Canberra ACT 2601
Office location Level 4, 51 Allara Street, Canberra City
Australian Capital Territory

Telephone (02) 6279 0100 international + 61 2 6279 0100
Facsimile (02) 6248 8053 international + 61 2 6248 8053
E-Mail
Internet

For further information contact the Murray-Darling Basin Authority office on
(02) 6279 0100

This report may be cited as:Pipeline to the Sea: Feasibility Study – Phase 1

MDBA Publication No. 148/11
ISBN (on-line) 978-1-921914-11-9
© Copyright Murray-Darling Basin Authority (MDBA), on behalf of the Commonwealth of Australia 2011.

This work is copyright. With the exception of photographs, any logo or emblem, and any trademarks, the work may be stored, retrieved and reproduced in whole or in part, provided that it is not sold or used in any way for commercial benefit, and that the source and author of any material used is acknowledged.

Apart from any use permitted under the Copyright Act 1968 or above, no part of this work may be reproduced by any process without prior written permission from the Commonwealth. Requests and inquiries concerning reproduction and rights should be addressed to the Commonwealth Copyright Administration, Attorney General’s Department,National Circuit, Barton, ACT, 2600 or posted at

The views, opinions and conclusions expressed by the authors in this publication are not necessarily those of the MDBA or the Commonwealth. To the extent permitted by law, the MDBA and the Commonwealth excludes all liability to any person for any consequences, including but not limited to all losses,damages, costs, expenses and any other compensation, arising directly or indirectly from usingthis report (in part or in whole) and any information or material contained within it.

Australian Government Departments and Agencies are required by the Disability Discrimination Act 1992 (Cth) to ensure that information and services can be accessed by people with disabilities. If you encounter accessibility difficulties or the information you require is in a format that you cannot access, please contact us.

Cover image: “Salinity Interception infastructure at Bookpurnong SA. Main line for salinity water to evaporation ponds” Arthur Mostead
Preface

The Basin Salinity Management Strategy 2001–2015 is the Murray-Darling Basin Ministerial Council’s response to the threat of salinity to water quality, the riverine environment, regional infrastructure and productive agricultural land.

A key element of this Strategy was the implementation of a joint program to construct new salt interception schemes to offset a predicted 61EC future increase in average salinity at Morgan. With an increase in the number of operating salt interception schemes came the need to assess options for disposal of saline groundwater generated by these schemes.

Due to the controversial nature of disposal basins from a social and environmental perspective, more detailed assessments of a number of alternate disposal options have been carried out or are under way. One alternative for the Riverland is a pipeline to transfer saline water to the sea.

The Murray-Darling Basin Commission first assessed a pipeline to the sea to transfer saline water generated by salt interception schemes in the Murray-Darling Basin in 1990 (GHD et al, 1990). That assessment considered a combined pipeline to transfer water from the Sunraysia and Riverland areas (‘the Mallee Zone’) as well as a separate pipeline to transfer saline water east/upstream of Swan Hill (‘the Riverine Plains Zone’).

The objective of this latest feasibility report was to establish the feasibility of a pipeline/channel delivery system that would efficiently and effectively dispose of saline groundwater from the Stockyard Plain Disposal Basin in the Riverland Region of South Australia to the sea.

The key conclusion of this feasibility study is that a pipeline to the sea may have some promise in the longer term when or if the capacity of the existing basins is exceeded. This report has only been prepared to inform discussion around possible disposal alternatives. Any decision to build such a pipeline at some point in the future would require more detailed engineering and ecological assessments followed by an extensive consultation and approval process.

Table of Contents

Pipeline to the SeaFeasibility Study – Phase 1

Executive Summary

1.Introduction

1.1Project Objective

1.2Stockyard Plain Disposal Basin

2.Outline of Scheme

2.1Outline of Infrastructure

2.2Range of options considered

3.Other Options

3.1General

3.2Disposal to Existing Salt Fields

3.3Disposal of Salt

3.4Discharge to Morella Basin or Southern Lagoon of the Coorong

4.Pipeline Routes

4.1Alternative Routes

4.2Alternative Disposal Locations

4.3Options Assessed

5.Pipeline and Pumping Infrastructure

5.1System Description and Operating Philosophy

5.2Pipeline

5.2.1Pipe Size

5.2.2Pipe Material

5.2.3Pipeline Cost

5.3Pump Stations

5.3.1Number of Pump Stations

5.3.2Pump Station Cost

5.4Discussion

5.5Off Peak Pumping

5.6Energy Recovery

5.7Open Channels

5.8ETSA Upgrade

6.Marine Outfalls

6.1General

6.2Ecosystems at Outfall Locations

6.2.1Port Wakefield

6.2.2Port Gawler

6.2.3Middleton

6.2.4Murray Mouth

6.2.5Coorong Crossings (Hells Gate, Tea Tree Crossing, 42 Mile Crossing & South of Coorong)

6.3Impact of Discharge on Receiving Environments

6.3.1General

6.3.2Water Quality Policy

6.3.3Discharge Water Quality

6.3.4Required Dilution for Compliance

6.3.5Modelling of Discharge Mixing

6.3.6Risk Assessment

6.3.7Summary

7.Outfall Infrastructure

7.1Description of outfalls

7.2Outfall construction

7.3Pipeline to the Sea Outfalls

7.3.1Length of Outfalls

7.3.2Cost of Outfalls

8.Concentration Techniques

8.1Introduction

8.2Concentration via solar evaporation

8.3Climate Change

8.4Opportunistic production of other products

8.5Evaporation Basin Model

8.5.1General

8.5.2Model Methodology

8.5.3Model Inputs and Assumptions

8.6Area of Evaporation Basins Required

8.7Cost of Evaporation Basins

8.7.1Capital Cost

8.7.2Operation and Maintenance Cost

8.8Issues Associated with Evaporation Basins

8.9Concentration by Desalination

9.Ecological Issues

9.1Desktop Study

9.2Stockyard Plain Basin

9.3Pipeline Alignments

9.3.1Methodology

9.3.2Vegetation Types and Significance

9.3.3Summary of Vegetation Assessment

9.3.4Other Vegetation Issues

10.Aboriginal Heritage

10.1Desktop Study

10.2Aboriginal Heritage Sites

10.3Native Title

10.4Consultation with Aboriginal Groups

10.5Summary

11.Social Impacts

12.Comparison of Options

12.1General

12.2Total Cost

12.3Present Value Cost

12.4Cost per Tonne of Salt Removed

12.5Cost of Removing Salt by Truck

12.6Overall Comparison of Alternative Pipeline Alignments

12.7Comparison of Pipeline and Trucking

13.Technical Review Workshop

13.1Workshop Purpose, Attendees and Outcomes

13.2Phase 2

14.Conclusions

14.1Individual Conclusions

14.2Overall Conclusions

15.References

Tables

Table 4.1 – Alternative Pipeline Routes

Table 5.1 - Pipe Sizes Assessed for Different Velocities

Table 5.2 – Optimum Pipe Sizes

Table 5.3 – Pipe Details

Table 5.4 - Optimisation of Pipeline Size

Table 5.5 – Pipeline Capital Costs

Table 5.6 – Pipeline Friction (m/km) for Different Pipeline Capacities and Velocities

Table 5.7 – Number of Pump Stations for Each Pipeline Option (50 L/s)

Table 5.8 – Number of Pump Stations for Each Pipeline Option (100 L/s)

Table 5.9 – Number of Pump Stations for Each Pipeline Option (250 L/s)

Table 5.10 – Number of Pump Stations for Each Pipeline Option (375 L/s)

Table 5.11 – Number of Pump Stations for Each Pipeline Option (500 L/s)

Table 5.12 – Unit Cost for each Different Pump Station

Table 5.13 – Pump Station Capital Costs

Table 5.14 – Density of Pumped Water

Table 5.15 – Annual Pump Station Operational Cost ($ million)

Table 5.16 - Power Upgrade Costs

Table 5.17 - Costs to Upgrade Electricity Network

Table 6.1 – Water Quality Data for Stockyard Plain Basin

Table 6.2 – CORMIX Model Input Data for Receiving Waters

Table 6.3 – CORMIX Model Input Data for Outfall Discharge

Table 6.4 – Results of Initial CORMIX Model Runs

Table 6.5 – Results of CORMIX Model Runs for Different Outfall Pipe Sizes

Table 6.6 – Impact Assessment Matrix

Table 6.7 – Summary Risk Matrix

Table 6.8 – Summary Risk Assessment for Habitat and Species

Table 6.9 – Summary of Marine Outfalls

Table 7.1 – Outfall Lengths for Port Gawler Pipeline Options

Table 7.2 – Cost of Outfall Structures

Table 8.1 – Weather Data Used in Evaporation Basin Model

Table 8.2 – Area of Evaporation Basins for Salt Harvesting

Table 8.3 – Areas of Evaporation Basins for 300 L/s Inflow

Table 8.4 – Area (Ha) of Evaporation Basins Required to Concentrate Groundwater at Stockyard Plain

Table 8.5 - Estimated Cost of Reverse Osmosis Desalination Plants

Table 9.1 – Overall Significance Score

Table 9.2 – Roadside Vegetation Categories

Table 9.3 – Vegetation Scoring for Bow Hill to Tailem Bend

Table 9.4 – Roadside Vegetation Categories for Bow Hill to Tailem Bend

Table 9.5 – Summary of Roadside Vegetation Assessment

Table 10.1 – Consolidated List of Known Aboriginal Heritage Sites

Note:NNTT ID = National Native Title Tribunal Identification number

Table 10.2 – Native Title Claims

Table 10.3 – Aboriginal Stakeholder Groups

Table 12.2 – Overall Comparison of Pipeline Alignments

Figures

Figure 2.1 – Schematic Diagram of Project Infrastructure

Figure 4.1 – Alternative Pipeline Routes

Figure 4.2 – Longitudinal Sections of Pipeline Routes

Figure 5.1 – Pipeline Capital Costs

Figure 12.1 – Present Value Costs

Figure 12.2 – Cost per Tonne of Salt Removed

Appendices

Appendix A Fisheries Habitats

Appendix B Risk Assessment for Marine Habitats

Appendix C Risk Assessment for Marine Species

Appendix D Pipeline System Schematics

Pipeline to the Sea: Feasibility Study - Phase 1

Document History and Status

Rev / Description / Author / Rev’d / App’d / Date
A / Draft for comment / RME / JPW / 7/11/07
B / Revised draft for workshop / RME / JPW / 21/4/08
C / Revised draft following workshop / RME / JPW / 30/6/08
D / Final / RME / PDC / PDC / 9/10/08

Pipeline to the Sea: Feasibility Study - Phase 1

Executive Summary

Key Conclusions

A pipeline to the sea is a promising option to remove salt from the Riverland region of South Australia some time in the future when additional volumes of saline groundwater are generated by new salt interception schemes and the capacity of existing disposal options is exceeded.

For the likely groundwater flows and salt loads to be disposed of in the short term, piping salt is not as cost effective as harvesting salt at Stockyard Plain Basin and removing by trucking. A drawback of this option however is that additional evaporation basins would have to be constructed to allow salt to be harvested

It is more cost effective to concentrate the groundwater at the StockyardPlainBasin before pumping to the sea. This indicates that the additional costs to concentrate the groundwater are more than offset by the reduction in pipeline cost by using a smaller pipe to transfer the same volume of salt.

The enhanced concentration of the groundwater generated by the salt interception schemes, possibly by desalination at the Stockyard Plain Basin, would reduce theinflow to the basin and extend its sustainable life beyond the currently estimated 100 years.

The most cost effective pipeline option is to concentrate brine at Stockyard Plain Basin and transport to Cheetham Salt at Dry Creek north of Adelaide. Although preliminary figures indicate that this option is not as cost effective as the trucking option it is considered that it warrants more detailed assessment as it re-uses a waste product and there is opportunity to offset costs against the reduced pumping which would be required by Cheetham Salt. If coupled with a desalination plant at Stockyard Plain Basin to concentrate the brine and produce fresh water as aby-product, the total project would be seen as turning a problem into a number of benefits.

If a pipeline to the sea was to be adopted in the future a detailed investigation would be required to more accurately determine costs for the preferred alignment and to determine the optimum time to cease disposal to Stockyard Plain Basin to ensure the long term ecological sustainability of salt interception schemes in the Riverland.

Objective

The objective of this study is to establish the feasibility of a pipeline/channel delivery system that will efficiently and effectively dispose of saline groundwater from the Stockyard Plain Disposal Basin in the Riverland Region of South Australia to the sea.

A pipeline to the sea would be expected to extend the sustainability of existing salt management basins in the region as well as delaying or negating the need for the development of additional salt management basins.

Methodology

The project was considered as consisting of three main components;

  • Works required at Stockyard Plain to concentrate the salt load.
  • Works required to transport the salt load from the Stockyard Plain Basin to the disposal site.
  • Works required to dispose the salt load at the disposal site.

The efficiency of a salt disposal scheme can be measured by estimating the unit cost of salt removed from the Stockyard Plain Basin i.e. $/tonne. A number of alternative schemes were assessed by considering a range of pipeline capacities and salinities of pumped groundwater.

For this project a range of flows from 50L/s to 500L/s was considered for the disposal of groundwater from the Stockyard Plain Basin.

To cover the possible range of salinities to be pumped, the following salinities were considered when assessing the alternative schemes;

  • 20000mg/L (lower limit).
  • 60000mg/L (mid range).
  • 100000mg/L (upper limit).

Alternative Options

Alternative pipeline routes were selected by consideration of potential disposal locations and proximity to the sea. The geography of the South Australian coastline highlights four principal disposal locations;

  • Top of Gulf St Vincent.
  • North of the city of Adelaide.
  • The Coorong.
  • Encounter Bay (Middleton).

The top of Gulf St Vincent is due west of the StockyardPlainBasin and a pipeline alignment would avoid any major townships. The nearest point on the coastline to the StockyardPlainBasin is north of the city of Adelaide. The Southern Ocean adjacent the Coorong is a logical destination because of its direct route and high energy coastline. The EncounterBay alternative was selected as it provides a shorter pipeline route than the Coorong option.

In addition to disposal of the saline water to the sea, disposal at the existing Cheetham saltfields at Dry Creek was considered.

For each of the locations a pipeline alignment was selected by following existing road reserves and existing or disused railway corridors. The alignments also cross the River Murray and other rivers and creeks at existing or disused bridges.

A total of four principal pipeline routes (A to D) and 11 alternative disposal locations were considered and are summarised in the following table.

Pipeline Route / Disposal Location / Length
(km) / Maximum
Elevation
(m AHD) / Distance Pumped (km)
A1 / Port Wakefield / 210 / 460 / 120
A2 / Lochiel Salt Works / 220 / 460 / 120
A3 / Price Salt Works / 240 / 460 / 120
B1 / Dry Creek Salt Works / 160 / 380 / 85
B2 / Port Gawler / 155 / 380 / 85
C1 / Middleton / 255 / 150 / 150
C2 / Murray Mouth / 265 / 150 / 150
D1 / Hells Gate / 240 / 76 / 210
D2 / Tea Tree Crossing / 280 / 76 / 245
D3 / 42 Mile Crossing / 295 / 76 / 265
D4 / South of CoorongNational Park / 330 / 76 / 290

Pipeline Costs

For the range of options considered, capital and on-going costs were estimated for a pipeline and pumping system. Pipeline capital costs varied from $44million to $93million for the 50L/s capacity options and from $130million to $278million for the 500L/s capacity options.

For all pipeline options the capital cost of the pipeline is much greater than the capital cost of the pump stations. For the Port Gawler (B2) and Dry Creek(B1) options the cost of the pump stations is 10% to 25% of the pipeline cost, while for the options which discharge to the Southern Ocean the cost of the pump stations is 10% to 15% of the pipeline cost.

The capital cost of the pipeline for any particular option is much greater than the capital cost of the pump stations and the outfall structures. For the options which pump raw groundwater from the Stockyard Plain Basin the pipeline represents 65% to 75% of the capital cost for the Port Gawler options and 75% to 90% of the capital cost for the options discharging to the Southern Ocean.

It was also found that the pump station operating costs were small compared to the pipeline capital cost. Using a 30year period and 4% discount rate the present value of the operating cost for the Port Gawler options is 20% to 50% of the pipeline cost. For the pipeline options which outfall to the Southern Ocean the operating cost is between 10% and 15% of the pipeline cost, depending upon the pipeline capacity.

The existing ETSA Utilities electricity distribution network would require a significant upgrade south of Meningie and west of Blanchetown to cater for the proposed pump stations along the Coorong and Port Gawler pipeline options.

Concentration at Stockyard Plain

For the options pumping concentrated groundwater the area of evaporation basins required to achieve the desired concentration was estimated. To achieve the desired salinities it is necessary to line the basins to reduce the seepage rate. The cost of the basins was estimated using a rate of $35000 to $40000/ha. The capital cost of the basins becomes significant for these options and the pipeline cost becomes 40% to 50% of the total capital cost for Port Gawler options and 50% to 70% for other options.

Marine Outfalls

The composition of the groundwater being pumped into the StockyardPlainBasin is similar to that of seawater. The principal differences between the Stockyard Plain Basin water and seawater are elevated concentrations of oxidised nitrogen, ammonia, iron and manganese.

Based on the number of species and habitats the Southern Ocean marine outfall locations have a lower environmental risk than the Gulf St. Vincent marine outfall locations. However, results of the CORMIX modelling indicate that discharge from a single open pipe marine outfall without a diffuser structure should adequately mix to achieve acceptable concentrations of critical elements at the edge of the mixing zone as defined in the Environmental Protection (Water Quality) Policy, 2003.

Marine outfalls discharging to the Southern Ocean are likely to be shorter in length than those discharging to Gulf St Vincent because of higher energy waters and deeper water closer to shore.

The location of the outfall will be governed by specific site conditions and further detailed modelling using site specific data would be required before any definite decisions on outfall locations were made. In particular, site specific bathymetry and time series wind and current data to define the worst conditions scenario are required to allow more accurate modelling of the outfalls.

For each option discharging to the sea, capital and on-going costs were estimated for a marine outfall. The cost of all outfalls was much smaller than the pipeline cost.

Ecological Issues

To assess the nature and scale of matters of conservation significance likely to be encountered along the alternative pipeline routes the database of roadside vegetation mapping was used. From the database, the extent of high value vegetation was quantified as this was considered a good indicator of the potential for impacting on conservation values.

It was concluded that the risk of impacting on conservation values along the Port Gawler alignment is low while the risk of impacting on conservation values along the Coorong alignments is high.