THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

PERMIT REVIEW SECTION

14741 Governor Oden Bowie Drive, Upper Marlboro MD 20772.


Permit Reviewer: Brooke Larman 15397-2017-CGU

Telephone Number: (301) 636-2017 May 8, 2017

Fax Number: (301) 952-4141 JSF Largo/Cubesmart/New Building

The following comments were generated from permit review. Any questions or concerns regarding the following should be directed to the reviewer at the phone number provided above. Further comments may be generated when the appropriate information has been submitted.

1.)  Per Environmental Planning. HOLD. Pending certification of the TCPII and any conditions from District Council, scheduled 5/15/2017. Need to contact Thomas Burke at 301-952-4534 for more information on this comment. 08-04-17 Continue Hold. Need to upload the certified TCPII-023-95-04. BEL. 09-11-17 Comment Satisfied. OK. Certified TCPII-023-95-04 submitted.

2.)  Per Subdivision. HOLD. Pending approval of DSP-16030. This site is subject to the Order of Approvals, thus recommendation of approval of grading permits cannot be made prior to approval and recordation of Final Plat of Subdivision. 08-04-17 Continue Hold. Need recorded Final Plat of Subdivision uploaded. BEL. 09-11-17 Comment Stands. BEL. 09-19-17 Continue Hold. I spoke with Matthew Jones at Bohler Engineering on 9/13/17 and he asked me to hold the permit until he could upload the certified detailed site plan. As far as I can see, the certified site plan has not been uploaded. BEL. 10-11-17 Comment Satisfied. Okay per Plat 150-83 & DSP-16030. BEL

3.)  Need to upload the approved and certified DSP-16030 once completed and any conditions that may need to be met. 08-04-17 Comment Stands. BEL. 09-11-17 Comment Stands. BEL. 09-19-17 Comment Stands. BEL. 10-11-17 Comment Satisfied. DSP plans uploaded. BEL

4.)  Further review will continue once the above has been completed. 08-04-17 Comment Stands. BEL. 09-11-17 Comment Stands. BEL. 09-19-17 Comment Stands. BEL. 10-11-17 Comment Satisfied. BEL

05-08-17-Comments emailed to Joseph Jarvis at BEL

08-04-17-Comments emailed to Joseph Jarvis at BEL

09-11-17-Comments emailed to Joseph Jarvis at BEL

09-19-17-Comments emailed to Joseph Jarvis at BEL

10-11-17-APPLICATION APPROVED. BEL