New Home Construction Builder Building

Home Construction Estimation Form

Courtesy of Mortgage-Investments.com

GENERAL SUMMARY
ITEM I / DESCRIPTION
/ COST
1
Preliminary Expenses
2
/ Clearing, Layout, and Excavation
3
/ Foundation Wall and Backfill
4
/ Reinforcing Steel
5
/ Concrete
6
/ Lumber
7
/ Mason
8
/ ' Plumbing
9 Heating and Cooling System
10 Electrical
11 Special Equipment
12 Windows and Glazing
13 Insulation and Soundproofing
14 Dry-Wall and Plaster
15 Ceramic Tile and Marble
16 Flooring
17 Ceilings
18 Overhead Door
19 Structural Steel and Ornamental Iron
20 Roofing and Gutters
21 Trim and Hardware
22 ' Cabinets
23 Decoration
24 ; Cleanup and Landscape
25 Miscellaneous
TOTAL
1. PRELIMINARY EXPENSES
ITEM
/ DESCRIPTION
/ COST
Financing
/ Appraisal Fee
Origination Fee
Inspection Fee
Attorney's Fee
Recording Fee
Stamps (Documentary)
Stamps (Tax)
Surve
Title Examination
Plans
/
Permits
/
Insurance
/ Bond
/
/ Liability
Risk (Builder's)
Utilities
/ Water Connection
Water Service
Sewer Connection
Sewer Service
Electric Connection
Electric Service
Telephone Service
Other
TOTAL
/ PRELIMINARY EXPENSES
2. CLEARING, LAYOUT, AND EXCAVATION
Quantity,
/ Unit
/ MATERIAL LABOR
ITEM
/ DESCRIPTION
/ Unit / Total Unit
/ Total
Clearing
Debris
Removal
Land Fill
/
Lumber / Batter Boards
/
Stakes
Cord I /
/
Layout
I
Excavation
/
/
TOTAL '
/
TOTAL CLEARING, LAYOUT, AND EXCAVATION
3. FOUNDATION WALL AND BACKFILL
Block
/
Mortar Mix
Sand
Termite
Protection
Water
Proofing
Backfill
Moisture
Barrier
Expansion
Joint
/
Bolts
/ Anchor
Lumber / Forming
TOTAL
TOTAL
/ FOUNDATION WALL AND BACKFILL
/ -
4. REINFORCING STEEL
MATERIAL
/ LABOR
ITEM
/ DESCRIPTION
/ Quantity
/ Unit
/ Unit / Total I
/ Unit / Total
Rods
/ Footin
I
Columns
Beams
Mesh
/ I
Chairs
Tie Wire
/ I
Stirrups
TOTAL
TOTAL
/ REINFORCING STEEL
/ I I
5. CONCRETE
Footing / I _
/ I / I
Slab
Beams
Columns
Walls
Walks and
Patios
Drives /
Curbs
/
/
D eck
TOTAL
TOTAL
/ CONCRETE
6. LUMBER
Quantity / MATERIAL
/ LABOR
ITEM
/ DESCRIPTION
/ Unit
/ Unit / Total
/ Unit / Total
Flooring / Girders
Sills
Joists and Header
Bridging
Subfloor
Exterior
Walls
/ Btm. Plate
/
Top Plate
Headers
/ Beams
Studs
Furring Strip
Sheathing
Siding
Interior
Walls
/ Btm. Plate
To Plate
Headers
Studs
Roofing
/ Beams
Trusses
Rafters
Joists
Ridge
Backing
SUBTOTAL
/ LUMBER
6. LUMBER (PAGE TWO)
Quantity / MATERIAL
/ LABOR
ITEM
/ DESCRIPTION
/ Unit
/ Unit
/ Total
/ Unit
/ Total
SUBTOTAL '
/ (From page one- LUMBER)
Sheathing
Purlins
Eave
Detail
/ Fascia I
/
/
Drip nailer
Soffit
/ Vents
/
Frieze
/
/ Molding
Backing
/
/
Ceiling
/ I Exterior /
Drop
/
Soffit
/
Gable
Detail
/ Siding
/
Molding
-
Vents
/
/
Post
Beams
Stairway
/ Stringer
Treads and Landing
Decking
/ Beams and Joists
Flooring
/
/
Other
TOTAL
TOTAL
/ LUMBER
7. MASONRY
MATERIAL
/ LABOR
ITEM
/ DESCRIPTION
/ Quantity / Unit
/ Unit
/ Total
/ Unit
/ Total
Block
Lintels
Sills
/
Sill Paper
Steps
Brick
Stone
Mortar Mix
/
Sand
Wall Ties
Reinforcing
/
Fireplace
TOTAL
TOTAL
/ MASONRY
8. PLUMBING
ITEM
/ DESCRIPTION
/ COST
Contract
Septic Tank
Well
Pum
Other
TOTAL
/ PLUMBING
9. HEATING AND COOLING SYSTEM
Contract
Other
/
TOTAL
/ HEATING AND COOLING SYSTEM
10. ELECTRICAL
Contract
/
Fixtures
Intercom
Security
Chimes
TOTAL
/ ELECTRICAL
11. SPECIAL EQUIPMENT
Kitchen
/ Range ,
Dishwasher
Disposal
Refrigerator
Oven
Ventilating Hood
Central Cleaning
TOTAL
/ SPECIAL EQUIPMENT
12. WINDOWS AND GLAZING
ITEM
/ DESCRIPTION
/ COST
Windows
Doors
Glazing
Mirrors
Enclosures
Other
TOTAL
/ WINDOWS AND GLAZING
13. INSULATION AND SOUNDPROOFING
Walls
Ceiling
Other
TOTAL
/ INSULATION AND SOUNDPROOFING
14. DRY-WALL AND PLASTER
Exterior
Walls
Interior
Walls
TOTAL
/ DRY-WALL AND PLASTER
15. CERAMIC TILE AND MARBLE
ITEM
/ DESCRIPTION
/ COST
Floors
Walls
Sills
Other
TOTAL
/ CERAMIC TILE AND MARBLE
16. FLOORING
Vinyl
Carpet
Wood
Other
TOTAL
/ FLOORING
17. CEILINGS
Suspended
/ Acoustical
Luminous
Moldin
Tees (Main)
Tees (Cross)
Other
TOTAL
/ CEILINGS
18. OVERHEAD DOOR
Garage
Openers
Other
TOTAL
/ OVERHEAD DOOR
19. STRUCTURAL STEEL AND ORNAMENTAL IRON
MATERIAL
/ LABOR
ITEM
/ DESCRIPTION
/ Quantity
/ Unit
/ Unit / Total
/ Unit / Total
Steel
/ Beams
Columns
/ I
/ I
f / Joist
I / Plates
Angles
/ I
Stairway
/ I
Rails
Door Frames
Other
/ `
TOTAL
TOTAL ! / STRUCTURAL STEEL AND ORNAMENTAL IRON
20. ROOFING AND GUTTERS
Felt
/ Dry-in
Shingles / I
Built-up
Gravel
Stop
/
Eave Drip
Flashing
Vents
Flues
Skylight
/
Nails
Gutters
Downs out
Other
TOTAL
TOTAL
/ ROOFING AND GUTTERS
21. TRIM AND HARDWARE
Unit
/ MATERIAL
/ LABOR
ITEM
/ DESCRIPTION
/ Quantity
/ Unit / Total
/ Unit / Total
Door Units
Frames / Exterior
/
I nterior
/
Doors
/ Exterior
Interior
Bifold
Pocket
[ SUBTOTAL / TRIM AND HARDWARE
21. TRIM AND HARDWARE (PAGE TWO)
/ MATERIAL
/ LABOR
ITEM
/ DESCRIPTION
/ Quantity / Unit
/ Unit / Total
/ Unit
/ Total
SUBTOTAL
/ (From page one-TRIM AND HARDWARE)
Molding I
/ Casing
Crown
Corner
Stop
Base
/
Shoe
Paneling
Spindles
/
Stairway Risers
Ballusters
Hand Rail
Disappearing
Shelving
Lock Sets Exterior
Interior
i
Door
Accessories Threshold
Hin es
Weatherstripping
Bumpers
Closet
Rods
Other
TOTAL
/
TOTAL
/ TRIM AND HARDWARE
22. CABINETS
ITEM
/ DESCRIPTION
/ COST
Kitchen
/ Base
/
Wall
Trim
Countertops
Baths
/ Vanities
Countertops
Medicine
Other
TOTAL
/ CABINETS
23. DECORATION
Paint
Wallpaper
Drapes
Other
TOTAL
/ DECORATION
24. CLEANUP AND LANDSCAPE
ITEM
/ DESCRIPTION
/ COST
Mason
Windows and
Doors
Walls and
Floors
Cabinets
Debris
Removal
Grading and
Landfill
Sod
Plants
I
TOTAL
/ CLEANUP AND LANDSCAPE
25. MISCELLANEOUS
I
Supervision
I
Scaffolds
Crane
Service
/
Sanitation
Service
Asphalt
Paving
Roof
Anchors
/
Plywood
Clips
Hangers
Nails
TOTAL
/ MISCELLANEOUS

Courtesy of mortgage-investments.com. ©