MPF Xtra® Servicing Released

from Prospect Mortgage to Redwood

ULDD & Additional File Testing Process

Master Commitment (MC) Setup (Redwood MC)

Before a Delivery Commitment (DC) can be transferred from Prospect Mortgage to Redwood, the PFI is required to a have new MPF Xtra MC, the MPF Xtra Consolidated addendum needs to have been delivered and the additional information file needs to have been successfully tested.

ULDD & MPF Additional Info File Testing Process

  1. The PFI logs in to the eMPF® Website
  2. *(one-time step) In order to build the MPF Additional Info CSV file required for MPF Xtra Servicing Released batch submissions, the PFI retrieves the MPF Additional Information file layout from eMPF.
  3. Under the eMPF “Start” tab, the PFI clicks on the “Forms & Exhibits” link.
  4. The PFI clicks on the “MPF Additional Information File – Layout” link.
  5. The PFI saves the file.
  6. The PFI creates the MPF Additional Information File using the layout and saves the file.
  7. The PFI clicks on the “Transactions” tab.
  8. The PFI clicks on the “Upload File” link.
  9. The PFI selects “Other Documents” from drop down menu.
  10. The PFI clicks on the “Browse” button.
  11. The PFI selects the ULDD file and clicks the “Open” button.
  12. The PFI clicks the “Submit” button.
  13. The PFI clicks on the “Browse” button.
  14. The PFI selects the MPF Additional Information File and clicks the “Open” button.
  15. The PFI clicks the “Submit” button.
  16. The PFI sends an email request to the MPF Service Center:
  17. To:
  18. Cc: Owning MPF Bank contact(s)
  19. Subject: [PFI Number] MPF Xtra Servicing Released Batch Testing Request
  20. Body of email: Indicate that files have been uploaded and contact information for PFI.
  21. The MPF Service Center processes the files & replies to the email to return the results to the PFI.
  22. If there are errors that need to be corrected, the process will be repeated with the MPF Service Center until testing is successfully completed.