Question 692 for written reply
MINISTRY FOR HUMAN SETTLEMENTS
REPUBLIC OF SOUTH AFRICA
NATIONAL ASSEMBLY
QUESTION FOR WRITTEN REPLY
QUESTION NO.: 692
DATE OF PUBLICATION: 11 MARCH 2016
Mr M Waters (DA) to ask the Minister of Human Settlements:
(1) With regard to the building of Breaking New Ground houses in uMncube zone in Umthambeka Section ward 11, Tembisa, Gauteng, (a) how many houses are to be built, (b) who are the beneficiaries, (c) on what date did the project start and (d) who is the project manager;
(2) (a) what is/are the name(s) of the contractor(s), (b) how many local residents are employed and (c) what are their names;
(3) (a) what are the reasons that (i) the project has been stopped and (ii) that the people working on the project have not been paid, (b) when is it anticipated that the project will start again and (c) when can the beneficiaries of the houses expect the completion of the project? NW807E
REPLY:
(1) (a) The project in uMncube zone in Umthambeka Section Ward 11, Tembisa, Gauteng entails the construction of 118 houses.
(b) The identified beneficiaries of the project are the residents of Umncube Section in Tembisa.
(c) The Provincial Department of Human Settlements appointed the contractor in November 2013, however construction could not commence due to a delay occasioned by the contractor not furnishing the required performance guarantee and agreement on the subsidy quantum of R63366.00, which the contractor requested to be increased. The subsidy increase was only approved in the 2015/16 financial year. The contract for construction was signed in August 2015 with a date of completion being the 28th February 2016. The site was handed over the 13th August 2015 to the contractor.
(d) The Honourable member would be aware of Parliament’s convention which prohibits any public representatives, be it Members of the Executive or Honourable Members, from publishing names of people/contractors or companies when asking or responding to parliamentary questions. Accordingly, I will not able to provide names of people on the housing list as requested. But, I can confirm that the project manager is an employee of the Gauteng Provincial Department of Human Settlements.
(2) (a) The Honourable member would be aware of Parliament’s convention which prohibits any public representatives, be it Members of the Executive or Honourable Members, from publishing names of people/contractors or companies when asking or responding to parliamentary questions. Accordingly, I will not able to provide the names of people/contractors or companies as requested.
(b) A total of 24 employees were employed from local residents.
(c) The names of the beneficiaries will be made available subject to the relevant rules of privacy and confidentiality being adhered as is required in such disclosure, which requires approval from the households concerned and reasons for such request.
(3) (a) (i) The appointed contractor was deemed not to, by the Provincial Department in terms of its evaluation, have the functional and financial capacity to complete the project. The contractor committed to a construction programme which was not adhered to. In January 2016, progress on site was 19 Foundations and 9 wall-plates. The contract expired on the 28th February 2016. The contract was not extended to continue into the new financial year.
(ii) The Contractor was paid on the 07th March 2016 for 19 foundations and 4 wall-plates. The Province still has an outstanding claim, which is in the process of being evaluated for payment for 5 wall-plates.
(b) The balance of the project will be funded for completion in the 2016/17 financial year.
(c) The projected completion date for the project 31 March 2017.