McMILLAN PAZDAN SMITH WCI GROUP LLC

FIELD REPORT

PROJECT: / North Augusta High School
Phase II / FIELD REPORT NO.: / Nine (9)
CONTRACT: / Single Prime Construction / ARCHITECTS PROJECT NO.:
DISTRIBUTION: / Owner: / Dr. Shawn Foster, Aiken County Schools
Mr. Kevin Chipman, Aiken County Schools
Mr. John Murphy, Aiken County Schools
Ms. Beth Clark, Aiken County Schools
Mr. Kip Gunter, Aiken County Schools
Ms. Sandra Waddell, Aiken County Schools
Mr. Larry Callaway, Aiken County Schools
Architect: / Mr. Donnie Love, McMillan Pazdan Smith
Mr. Bill Williams, WCI
Mr. Robert Wayne, WCI
Consultant: / Mr. Mayhar Angooraj, BGA
Mr. William Wafer, BGA
Mr. Dan Reider, BGA
Mr. Tilden Hilderbrand, Hass & Hilderbrand
Contractor: / Mr. Jeffrey Reynolds, HG Reynolds
Mr. Tim Perkins, HG Reynolds
Mr. Graham Reynolds, HG Reynolds
DATE: / July 20, 2016 / WEATHER: / Sunshine/100/Humid
TIME: / 1:00 p.m. / SCHEDULE COMMENTS: / Good / Aggressive

PRESENT AT SITE:

HJR Contractor, Earthmovers, Plumbing, Electrical, Mechanical

OBSERVATION:

1)  Service storm drains contractor is (100%) complete as new footing and foundation work continues.

2)  Current inspections are coordinated by WCI Group and completed by CSRA as footing and foundation construction is placed and consistent as specified.

3)  Concrete cylinder reports documented and maintained by CRSA.

4)  All underground conduits and infrastructure are installed thru courtyard to transformer.

5)  The Contractor foundation walls have formed rebar wired, bridge and spacing as specified of Phase II.

6)  The Contractor has soil wall is complete as areas to be tied in remain.

7)  Rebar are coordinated and sleeved as concrete slab foundations are being prepped, is ongoing

8)  Site grading is continuous, consistent as required and erosion control implements are maintained and inspections by WCI Group and SWPPS documents are maintained.

9)  Contractor retaining wall near roadway is nearing completion as backfill to wall is ongoing.

10)  CMU Masonry walls are now in construction as required as block cells have received grout requirements.

11)  Vertical rebar placement is capped as CMU walls construction is consistent.

SUBMITTALS

1)  Mechanical HVAC package is in review/ongoing.

2)  Mechanical Plumbing package is in review/ongoing.

3)  Insulation Submittal are required for review/ongoing.

COORDINATION:

1)  Project and coordination meetings are scheduled 7/26/2016 @ 10 am.

INSPECTIONS:

1)  CCI on site as inspections log is updated

DEFICEINT WORK:

1)  None

PHOTOS:

1)  Attached

Soil Wall construction has progressed near completion

Foundation wall are near top out as formwork remains consistent with plans and specifications

New CMU construction is ongoing as wall grout will be placed in required stages

New wall construction where wire ties and horizontal rebar placement is consistent, ready concrete grout

New CMU wall construction with vertical # 5

New Footing and Foundation inspected and ready for concrete placement

CMU walls consistent with plans and specification WCI Group has witnessed the required cell grout fill

Erosion Control MEASURMENTS all documented by WCI Group BWilliams as required

Report by: R. Wayne Jr / WCI Group

Page 2 of 6