Construction Controls Group

Los Angeles Southwest College Proposition ‘A/AA’ Bond Fund Projects

Six Pack Meeting Agenda November 6, 2008

8:00 a.m.

1.0 Major Outstanding Issues (Problem Areas)
1.1 / Tech Ed Mod / TE Room 250: Electrical Power & Data Drops Required
·  A/E, GC & CPM Team Met and reviewed College request for power/data drops
TE Rooms 110, 130, 190 & 230: Power/Data Required
TE Rooms 270 & Office 310: Power/Data Required
Summary & Status:
·  Revised Plans prepared and submitted to Icon West for re-pricing not to exceed 10% Contingency for the Additional College scope
·  FCD to DSA required, but will proceed with GC after Proposal is within the 10% Contingency and negotiated
1.2 / Upcoming Phase 2 Move for TE / Refer to Plancorp Move Plan & Schedule
·  Nov. 14th & 15th
1.3 / Code Blue Phone Access at Parking Structure / Parking Garage
·  Parking Spaces still to be stripped to resolve College’s comments on cars parking to close to Blue Phones
1.4 / NEQ-Package 3 Punchlist / A/E Punchlist is completed by Woodcliff. College punchlist pending.
2.0 Project Updates
2.1 / Child Development Center / Project in Closeout
Prepare Smart Classroom Documents (ISDG), move forward after Measure J
2.2 / NEQ – Student Quad & Palm Court / Work Status:
·  Closeout the Project and obtain DSA Certification
2.3 / Cox Building Modernization / Gkkworks/LHA Architects Work Status:
·  Elevator Package in Preparation
2.4 / New Central Plant
(By Chevron Energy Solutions) / Progress:
·  Weekly Construction Meetings on Mondays at 2:00 pm in CPM Trailer Conference Rm
·  Construction in progress 22% complete
·  Equipment received by Chevron
2.5 / Design-Build Update / Status of Projects:
Park’g Structure: Construction Complete
M&O Facility: DSA Certification in Process
Athletic Field House: Construction 92% complete
Stadium: Construction 97% Complete; Elevators inspected on 11/03/08
SSAC: 90% Complete; Elevators approved
Campus Corner Sign: 100% Complete
Campus Security Facility: 99% Complete
2.6 / Campus-Wide Technology / Target Time Schedule to complete:
Phase 1A: 100% Complete
Phase 1B: VOIP Phones for Cox Building delivery pending
Phase 2: Wireless for PE Gym Bldg on hold
Phase 3: Wireless for Tech Ed – 100% complete
2.7 / Technical Education Center Building Modernization / Icon West construction Progress at 99%
·  McQuay Maintenance Service Contract for Chiller in place
·  Post Occupancy issues being addressed by A/E Team, GC and CPM per College request.
2.8 / Campus Perimeter Fence / Design Phase - LHA updating design plans for 100% CDs
2.9 / LACCD-LAUSD
Middle College High School / CPM waiting on update.
2.10 / Site Improvements – Campus East Pump House & Fire Water Upgrade / NTD A/E Team design work in progress
MACTEC Soil Report completed issue to A/E Team.
Design plans at 30% Completion
2.11 / Chevron’s Renewable Energy/Solar Panel Project / Progress:
·  Owner’s weekly meetings being held with Chevron & Pacifica for Solarvoltaic Systems, Parking Lots #1 & #3
·  Chevron in-progress with construction
·  Chevron to maintain south fence for College 11/15/08 Event
·  Chevron to continue after 11/15/08 Event with Construction activities; Completed forecast between February 1 to 15, 2009
2.12 / SMP Projects / College to discuss status
3.0 Finish – Additional College Coordination and Concerns

Handouts:

1.  Campus Project List and Status

2.  Campus Projects Project Status & Schedule

3.  Campus Projects Financial Updates

4.  Construction Update

G:\Ed Bilezikjian\SixPackMeetings\Meeting Agendas 2008\Meeting Agenda 11-06-08.doc