Location Map of the Project in Gujarat

Location Map of the Project in Gujarat

DESIGN, ENGINEERING, FINANCEE, CONSTRUCTION, OPERATION AND MAINTENANCE OF SAMAKHIALI – GANDHIDHAM SECTION OF NH-8AFROM KM 306+000 TO KM 362+160IN THE STATE OF GUJARAT UNDER PHASE-V ON DESIGN, BUILD,FINANCE, OPERATE AND TRANSFER(DBFOT) BASIS

/ Employer:
NATIONAL HIGHWAYS AUTHORITY OF INDIA
/ Independent Engineer:
Louis Berger Group, Inc. in association withM/s Louis Berger Consulting Pvt. Ltd.
/ Concessionaire:
M/s Samakhiyali – Gandhidham Toll way Limited.

Location Map of the Project in Gujarat

(Length of Project Road in 56.16 Km.)

SALIENT FEATURES OF PROJECT

Sl. No. / Item / Description
1 / Employer / NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI)
2 / Number of Contract Package / NHDP- V/MC-II/BOT/DPR/21.
3 / Name of Contract Package / Six laning of Samakhiali to Gandhidham Section from Km. 306.000 to Km. 362.160 of NH - 8A
4 / Location / Kutch, Gujarat
5 / Length Km / 56.16
6 / Name of the Concessionaire / L & T Samakhiali-Gandhidham Toll way Private Limited
7 / Concession Period / 24 years from the Appointed Date
8 / Letter of Acceptance Date / 20th January 2010
9 / Agreement Date / 17th March 2010
10 / Appointed Date (COD) / 11th September 2010
11 / Total Project Cost (EPC Contract) / Rs. 805.39 Crore
12 / Grant Amount / Nil
13 / Premium / Rs. 58.41 Cr.
14 / Design and Construction Period / 912 days from the Appointed Date
15 / Construction Period / 912 days
Milestones-
Milestone- 1 [180 days] / 09th March’ 2011 - 10% of total capital cost
Milestone- 2 [365 days] / 10th September’ 2011 - 25% of total capital cost
Milestone- 3 [730 days] / 10th September’ 2012 - 75% of total capital cost
Completion- [912 days] / 10th March’ 2013 - 100% of total capital cost
16 / Independent Engineer (IE) / The Louis Berger Group, Inc. in association with Louis Berger Consulting Pvt. Ltd., Gurgaon(Haryana.)
17 / Commencement of IE Services / 22nd December 2010
18 / Safety Consultant / M/s Mott McDonald
19 / EPC Contractor / L&T Infra -OC
20 / Time Elapsed (days) / 1353days (Till 25th May 2014) 441 days delay

SCOPE OF THE PROJECT AS PER CA

Sr.No. / Description of Item / Length in Km / Nos.
1 / Highway
i)Samakhiali area / 17.000 Km
ii)Bhachau area / 21.000 Km
iii)Gandhidham area / 5.240 Km
iv)Adipur area / 12.920 Km
Total- / 56.160 Km
2 / Service Roads
i)Rural Section 7 m wide (LHS + RHS) / 28.001 + 22.984 = 50.985(Km)
ii)Urban Section 8 m wide (LHS + RHS) / 16.687 x 2 = 33.374(Km)
iii)Urban Area with overlay 10 m wide (LHS + RHS) / 5.027 x 2 = 10.054(Km)
3 / Structures:
i)Flyovers (3x30), (3x30), (3x30+3x30), (3x30) / 4 Nos.
ii)ROB (Integral part of II interchange) 1379 m. / 1 No.
iii)MajorBridge (For S/R at 355.587 both side) 4x15.25 / 1 No.
iv)Major & Minor bridges (Repairs only) (Cracks, Rusting & exposed steel) / 10 Nos.
4 / Cross Drainage structures
i)Box Culverts (Widening only) All single span of 3.0 to 5.75m. / 16 No.
ii)Pipe Culverts (Widening only) 1 to 5 Rows of 0.9 m & 1.2 m dia. Hume Pipe / 27 No.
5 / Under Passes (VUP) All 2x9.0m. + 1x35.0m.(as rotary) / 10 Nos.
6 / Major Intersections 6+3 Nos. of 3&4 Arms respectively / 9 Nos.
7 / Major Interchange (700 m. long with 90 m. viaduct), (1379m.long with 230 m.via.) / 2 Nos.
8 / Causeway /Minor Bridges on service Road (Total length 680 m.) / 23 Nos.
9 / Staircase on both side of ROB / 2 Nos.
10 / Retaining Structures
i)At ROB and Grade Junction/Interchange / 2.049 (Km)
ii)For Flyovers at 4 locations (Km) / 2.656 x2 = 5.312 (Km)
iii)For Underpasses at 10 locations / 5.647 x2 = 11.294 (Km)
iv)Kandla Port By pass / 760 mts.
11 / Longitudinal Drains (Both side) at 24 locations / 28.281x2= 56.562 (Km)
12 / Others/Amenities
i)Bus Bays with Shelter / 12 x 2 = 24 Nos.
ii)Truck Lay Byes with Shelter / 3x2= 6 No.
iii)TollPlaza / 1 No.

4