£ p

A10 PROJECT PARTICULARS

110THE PROJECT

Name: Car Park 14

Location: Founders Building, Royal Holloway University of London, Egham, Surrey, TW20 0EX

Length of contract: 14 Weeks or alternative period offered by Contractor

120EMPLOYER (CLIENT)

Name: Royal Holloway College and Bedford New College

Address: Egham, Surrey, TW20 0EX

130PRINCIPAL CONTRACTOR (CDM)

Name: To be appointed (TBA).

Address: TBA

Contact: TBA

Telephone: TBA

140CONTRACT ADMINISTRATOR

Name: Jason Anderson

Address: RHUL, Estates Dept, Arts Annexe, Egham Hill, Egham TW20 0EX

Telephone: 01784 276415

145ARCHITECT / DESIGNER

Name: N/A

Address: N/A

Telephone:

150CDM COORDINATOR

Name: Walrus Safety Ltd

Address: 41Church Road, Newton Abbot, Devon, TQ12 1AL

Contact: Mike Eaton.

Telephone: 07970 206223

160QUANTITY SURVEYOR

Name: TBC

Address:

Telephone:

170M&E CONSULTANT (RHUL)

Name: Barry Kett

Address: RHUL, Estates Dept, Arts Annexe, Egham Hill, Egham TW20 0EX

Telephone: 01753 276415

A11 TENDER AND CONTRACT DOCUMENTS

110TENDER DRAWINGS

The tender drawings are: As listed in Appendix A

120CONTRACT DRAWINGS

The Contract Drawings: The same as the tender drawings.

160PRECONSTRUCTION INFORMATION

Format: The Preconstruction information is described in these preliminaries in Section A34.

It refers to information given elsewhere in the preliminaries and other tender documents. Refer to Appendix H.

180OTHER DOCUMENTS

Inspection: Drawings and other documents relating to the Contract but not included in the tender documents may be seen by appointment during normal office hours at the office of RHUL Estates Department.

The documents include: Asbestos Survey. Note this is a Management Survey only. A provisional sum for further intrusive surveys is included in Part 6 of the Schedules of Work

A12 THE SITE/ EXISTING BUILDINGS

110THE SITE

Description: Refer to the tender drawings.

120EXISTING BUILDINGS ON/ ADJACENT TO THE SITE

Description: Refer to campus map if required.

140EXISTING UTILITIES AND SERVICES

Drawings: (Information shown is indicative only): Refer to the tender drawings.

160SOILS AND GROUND WATER

Information: Survey to be undertaken by Contractor

170SITE INVESTIGATION

Report: Site Investigation Report to be undertaken by Contractor

180HEALTH AND SAFETY FILE

Availability for inspection: The Health and Safety File for the site/ building may be seen by appointment during normal office hours at: RHUL Estates department.

Arrangements for inspection: Contact the CA.

200ACCESS TO THE SITE

Description: North of the A30, located off Highfield Close.

Limitations: RHUL PM & Security should be advised for any site visits.

210PARKING

Restrictions on parking of the Contractor's and employees' vehicles: All contractors are to report to the security office within Founders’ Building to obtain passes for vehicles to be parked on site.

220USE OF THE SITE

General: Do not use the site for any purpose other than carrying out the Works.

230SURROUNDING LAND/ BUILDING USES

General: Adjacent or nearby uses or activities are as follows:

- Academic use and Children’s Nursery in close proximity.

240HEALTH AND SAFETY HAZARDS

General: The nature and condition of the site/ building cannot be fully and certainly ascertained before it is opened up. However the following hazards are or may be present: Refer to Pre-Construction Information pack.

Information: The accuracy and sufficiency of this information is not guaranteed by the Employer or the Employer's representative. Ascertain if any additional information is required to ensure the safety of all persons and the Works.

Site staff: Draw to the attention of all personnel working on the site the nature of any possible contamination and the need to take appropriate precautionary measures.

250SITE VISIT

Assessment: Ascertain the nature of the site, access thereto and all local conditions and restrictions likely to affect the execution of the Works.

Arrangements for visit: Contact Jason Anderson (PM) – 01753 276415

A13 DESCRIPTION OF THE WORK

110PREPARATORY WORK BY OTHERS

Works: Carried out under a separate contract and completed before the start of work on site for this Contract.

Description: N/A

120THE WORKS

Description: Design and Build of Car Parking facility.

130WORK BY OTHERS CONCURRENT WITH THE CONTRACT

Description:N/A

A20 JCT INTERMEDIATE BUILDING CONTRACT WITH

CONTRACTOR'S DESIGN (ICD)

JCT INTERMEDIATE BUILDING CONTRACT WITH CONTRACTOR'S DESIGN (ICD)

The Contract: JCT Intermediate Building Contract with Contractor's Design 2011 Edition.

Requirement: Allow for the obligations, liabilities and services described as follows:

THE RECITALS

First - THE WORKS

Comprise: The construction of Car Park facility with a minimum of 180 parking bays, 5 DDA parking bays, 1 motorcycle parking area and a Nursery Drop-off area.

Location: Royal Holloway University, Egham, Surrey. TW20 0EX

Second - CONTRACTOR'S DESIGNED PORTION

The Works include the design and construction of:

Car Park design and layout, drainage design, lighting with associated electrical works, CCTV/IT design.

Third - CONTRACT DRAWINGS

The Contract Drawings: As listed in clause A11/120.

Fourth - OTHER DOCUMENTS SUPPLIED BY THE EMPLOYER

Comprise: Schedules of Work. Preliminaries and RHUL Specification ‘Standards’

Named person: The whole of the text referring to a named person as a subcontractor Select from list be deleted.

Fifth A - PRICING BY THE CONTRACTOR

Option A will apply: Option B will be deleted.

Priced document: Within Option A the following words will be deleted:

Bills of Quantities / Specification

Priced Activity Schedule: The words 'and has provided the Employer with a priced

schedule of activities annexed to this Contract (the Activity Schedule)' will be

deleted.

Ninth - INFORMATION RELEASE SCHEDULE

The Ninth Recital will be deleted.

Eleventh - DIVISION OF THE WORKS INTO SECTIONS

The Eleventh Recital will be deleted.

THE ARTICLES

3 - ARCHITECT/ CONTRACT ADMINISTRATOR

Architect/ Contract Administrator: See clause A10/140.

4 - QUANTITY SURVEYOR

Quantity Surveyor: See clause A10/160.

5 - CDM COORDINATOR

CDM Coordinator: See clause A10/150.

5 - CDM COORDINATOR

Article 5 will be deleted.

6 - PRINCIPAL CONTRACTOR (CDM AND SWMP)

Principal Contractor: See clause A10/130 and A10/132.

6 - PRINCIPAL CONTRACTOR (CDM AND SWMP)

Article 6 will be deleted.

9 - LEGAL PROCEEDINGS

Amendments: ______.

CONTRACT PARTICULARS

PART 1: GENERAL

Fourth Recital - EMPLOYER'S REQUIREMENTS

Comprise: Documents for work as listed in the Second Recital.

Sixth Recital - CONTRACTOR'S PROPOSALS/ CDP ANALYSIS

Comprise: To be completed by the Contractor.

Specific Requirements: Documents requiring approval must be submitted a minimum of

two weeks prior to the specific item of work being carried out.

Eighth Recital and Clause 4.5 - CONSTRUCTION INDUSTRY SCHEME

Employer at Base Date is a Contractor for the purposes of the CIS.

Tenth Recital - CDM REGULATIONS

The project is notifiable.

Thirteenth Recital and Schedule 5 - SUPPLEMENTAL PROVISIONS

Collaborative working: Paragraph 1 applies.

Health and safety: Paragraph 2 applies.

Cost savings and value improvements: Paragraph 3 applies.

Sustainable development and environmental considerations: Paragraph 4 applies.

Performance indicators and monitoring: Paragraph 5 does not apply.

Notification and negotiation of disputes: Paragraph 6 applies.

Where paragraph 6 applies, the respective nominees of the parties are:

Employer's nominee: To be advised.

Contractor's nominee: To be advised. Or such replacement as each party may notify to

the other from time to time.

Article 8 - ARBITRATION

Article 8 and clauses 9.3 to 9.8 (arbitration) apply.

Clause 1.1 - BASE DATE

Base Date: May 2014.

Clause 1.1 - CDM PLANNING PERIOD

Shall mean the period of two weeks ending on 11th July 2014.

Clause 1.1 - DATE FOR COMPLETION OF THE WORKS

Date for completion of the Works (where completion by sections does not

apply):1st February 2015.

Clause 1.7 - ADDRESSES FOR SERVICE OF NOTICES

Employer:

Address: Refer to A10/120.

Fax number

Contractor: TBA

Address: .

Fax Number

Clause 2.4 - DATE OF POSSESSION OF THE SITE

Date of Possession of the site: 28th June 2014.

Clause 2.5 - DEFERMENT OF POSSESSION OF THE SITE

Clause 2.5 applies.

Where clause 2.5 applies, maximum period of deferment (if less than six weeks) is six weeks.

Clause 2.23.2 - LIQUIDATED DAMAGES

Damages: At the rate of £300.00 per Calendar Day.

Clause 2.30 - RECTIFICATION PERIOD

Period: Twelve months from the date of practical completion of the Works.

Clause 2.34.3 - CONTRACTOR'S DESIGNED PORTION

Limit of Contractor's liability for loss of use: £2,000,000.00.

Clause 4.6 - ADVANCE PAYMENT AND ADVANCE PAYMENT BOND

Advance payment: Clause 4.6 does not apply.

Clause 4.7.1 - INTERIM PAYMENTS - DUE DATES

The first due date is: 26th Jul 2014, and thereafter the same date in each month or the nearest Business Day in that month.

Clause 4.8.1 - INTERIM PAYMENTS - PERCENTAGE OF VALUE

Not achieved practical completion: Where the Works, or those works in a section, have not achieved practical completion, the percentage of total value in respect of the works that have not achieved practical completion is 95 per cent.

Completed works: Where the Works, or those works in a section, have achieved practical

completion, the percentage in respect of the completed works is 97.5 per cent.

Clause 4.9.4 - LISTED ITEMS - UNIQUELY IDENTIFIED

Listed items: Clause 4.9.4 will be deleted.

Clause 4.9.5 - LISTED ITEMS - NOT UNIQUELY IDENTIFIED

Listed items: Clause 4.9.5 will be deleted.

Clause 4.15 and Schedule 4 - CONTRIBUTION, LEVY AND TAX FLUCTUATIONS

Schedule 4 (Fluctuations Option): Not applicable.

Percentage addition for Fluctuations Option: Nil.

Clause 6.4.1.2 - CONTRACTOR'S INSURANCE - INJURY TO PERSONS OR PROPERTY

Insurance cover (for any one occurrence or series of occurrences arising out of one

event): £5,000,000.00.

Clause 6.5.1 - INSURANCE - LIABILITY OF EMPLOYER

Insurance may be required.

Minimum amount of indemnity for any one occurrence or series of occurrences arising out of one event: £5,000,000.00.

Clause 6.7 and Schedule 1 - INSURANCE OF THE WORKS - INSURANCE OPTIONS

Schedule 1: Insurance option C applies.

Percentage to cover professional fees: 15 per cent.

If option A applies, annual renewal date (as supplied by the Contractor): ______.

Clause 6.10 and Schedule 1 - TERRORISM COVER

Details of cover: TBA.

Clause 6.12 - JOINT FIRE CODE

The Joint Fire Code: Does not apply.

Clause 6.12 - JOINT FIRE CODE

Joint Fire Code: Applies.

Application: State whether the insurer under Schedule 1, Insurance Option A, B or C (paragraph C.2) has specified that the Works are a 'Large Project': No.

Clause 6.15 - JOINT FIRE CODE - AMENDMENTS/ REVISIONS

Joint Fire Code - Amendments/ revisions: The cost, if any, of compliance with amendments or revisions to the Joint Fire Code shall be borne by the Main Contractor.

Clause 6.16 - CONTRACTOR'S DESIGN PORTION - PROFESSIONAL INDEMNITY

INSURANCE

Level of cover: Amount of indemnity required: £ 2,000,000.00.

Cover for pollution and contamination claims: Not required.

Expiry of required period of CDP Professional Indemnity Insurance: 12 years.

Clause 8.9.2 - PERIOD OF SUSPENSION (TERMINATION BY CONTRACTOR)

Period of suspension: Two months.

Clauses 8.11.1.1 to 8.11.1.5 - PERIOD OF SUSPENSION (TERMINATION BY EITHER

PARTY)

Period of suspension: Two months.

Clause 9.2.1 - ADJUDICATION

The Adjudicator is: the Nominating Body.

Nominating body - where no Adjudicator is named or where the named Adjudicator isunwilling or unable to act (whenever that is established): The Royal Institute of Chartered Surveyors.

Clause 9.4.1 - ARBITRATION

Appointor of Arbitrator (and of any replacement): President or a Vice President of the

Royal Institute of Chartered Surveyors.

PART 2: COLLATERAL WARRANTIES

Part 2(E) - COLLATERAL WARRANTIES FROM SUBCONTRACTORS

Part 2(E)

Conditions: Clauses 3.5 and 3.6 of the Contract.

Collateral warranties may be required from the following subcontractors or categories of

subcontractor.

Name or category: Mechanical and Electrical Installations

Types of warranty: SCWa/E2011.

Professional Indemnity Insurance: Amount: £2,000,000.00, Period: 12 years.

THE CONDITIONS

SECTION 1: DEFINITIONS AND INTERPRETATION

1.5 - RECKONING PERIODS OF DAYS

Amendments: ______.

1.11 - APPLICABLE LAW

Amendments: ______.

SECTION 2: CARRYING OUT THE WORKS

Clause 2.12.2

Omit Clause 2.12.2 in its entirety and insert “Where there are Schedules of Work, then, unless otherwise stated, those Schedules have not been prepared in accordance with the Standard Methods of Measurement. Quantities will have been provided for various works to act as a schedule of rates and the Contractor is required to allow in their rates for all necessary works to achieve the specified item.”

SECTION 3: CONTROL OF THE WORKS

CDM REGULATIONS – UNDERTAKINGS TO COMPLY

Add new clause 3.18.5

If the Contractor fails to supply the information required under JCT clause 3.18.4 as required by the CDM Co-ordinator within such time as reasonably required under JCT clause 2.21, the value of the information for the purposes of valuing the works shall be deemed to be £5,000 and this money be withheld from the valuation and certificate of payment until the information has been received and approved, the approval of which shall not be unreasonably withheld.

SECTION 4: PAYMENT

Clause 4.7.1.1 - Delete the words “14 days” and insert “33 days.”

Clause 4.11.1 - Delete the words “14 days” and insert “33 days.”

SECTION 5: VARIATIONS

SECTION 6: INJURY, DAMAGE AND INSURANCE

SECTION 7: ASSIGNMENT AND COLLATERAL WARRANTIES

SECTION 8: TERMINATION

SECTION 9: SETTLEMENT OF DISPUTES

EXECUTION

The Contract: Will be executed as a Deed.

CONTRACT GUARANTEE BOND

Contract Guarantee Bond: Not required.

A30 TENDERING/ SUBLETTING/ SUPPLY

MAIN CONTRACT TENDERING

110SCOPE

General: These conditions are supplementary to those stated in the Invitation to Tender and on the form of tender.

160EXCLUSIONS

Inability to tender: Immediately inform if any parts of the work as defined in the tender documents cannot be tendered.

Relevant parts of the work: Define those parts, stating reasons for the inability to tender.

170ACCEPTANCE OF TENDER

Acceptance: No guarantee is offered that any tender will be recommended for acceptance or be accepted, or that reasons for non acceptance will be given.

Costs: No liability is accepted for any cost incurred in the preparation of any tender.

190PERIOD OF VALIDITY

Period: After submission or lodgement, keep tender open for consideration (unless previously withdrawn) for not less than 3 months.

Date for possession/ commencement: See section A20.

PRICING/ SUBMISSION OF DOCUMENTS

210PRELIMINARIES IN THE SPECIFICATION

The Preliminaries/ General conditions sections (A10-A56 inclusive) must not be relied on as complying with SMM7.

250PRICED DOCUMENTS

Alterations: Do not alter or qualify the priced documents without written consent. Tenders containing unauthorised alterations or qualifications may be rejected.

Measurements: Where not stated, ascertain from the drawings.

Deemed included: Costs relating to items, which are not priced, will be deemed to have been included elsewhere in the tender.

Submit: with tender.

310TENDER

General: Tenders must include for all work shown or described in the tender documents as a whole or clearly apparent as being necessary for the complete and proper execution of the Works.

315ALTERNATIVE TIME TENDERS

General: In addition to and at the same time as tendering based upon the date or period specified in section A20, an alternative tender based upon a different date for completion or period may be submitted.

Date for completion: If any such tender is accepted the date for completion inserted in the Contract will be the date stated in the alternative tender or determined from the period stated in the alternative tender.

500TENDER STAGE METHOD STATEMENTS

Method statements: Prepare, describing how and when the following is to be carried out:

Refer to the pre-construction information pack.

510ALTERNATIVE METHOD TENDERS

General: In addition to and at the same time as tendering for the Works as defined in the tender documents, alternative methods of construction/ installation may be submitted for consideration. Alternatives, which would involve significant changes to other work, may not be considered.

Alternative tenders: Such alternatives will be deemed to be alternative tenders and each must include a complete and precise statement of the effects on cost andprogramme.

Safety method statement: Carry out a health and safety risk assessment for each alternative and where appropriate provide a safety method statement suitable for incorporation in the Health and Safety Plan.

Full technical data: Submit for each alternative together with details of any consequential amendments to the design and/ or construction of other parts of the Works.

Submit: with tender

520DESIGN DOCUMENTS

Scope: Include the following in the Contractor's Proposals:

Design drawings: Car Park Layout Proposal

Technical information: Mechanical and Electrical Installations.

Submit: With tender.

530SUBSTITUTE PRODUCTS

Details: If products of different manufacture to those specified are proposed, submit details with the tender giving reasons for each proposed substitution. Substitutions, which have not been notified at tender stage, may not be considered.

Compliance: Substitutions accepted will be subject to the verification requirements of clause A31/200.

550HEALTH AND SAFETY INFORMATION

Content: Describe the organisation and resources to safeguard the health and safety of operatives, including those of subcontractors, and of any person whom the Works may affect. Include:

A copy of the contractor's health and safety policy document, including risk assessmentprocedures.

Accident and sickness records for the past five years.

Records of previous Health and Safety Executive enforcement action.

Records of training and training policy.

The number and type of staff responsible for health and safety on this project with details of their qualifications and duties.

Submit: within 2 days of request

570OUTLINE CONSTRUCTION PHASE HEALTH AND SAFETY PLAN

Content: Submit the following information within one week of request:

Method statements on how risks from hazards identified in the pre-construction

information and other hazards identified by the contractor will be addressed.

Details of the management structure and responsibilities.

Arrangements for issuing health and safety directions.

Procedures for informing other contractors and employees of health and safety hazards.

Selection procedures for ensuring competency of other contractors, the self-employed and designers.

Procedures for communications between the project team, other contractors and siteoperatives.

Arrangements for cooperation and coordination between contractors.

Procedures for carrying out risk assessment and for managing and controlling risk.

Emergency procedures including those for fire prevention and escape.

Arrangements for ensuring that all accidents, illness and dangerous occurrences arerecorded.

Arrangements for welfare facilities.

Procedures for ensuring that all persons on site have received relevant health and safetyinformation and training.

Arrangements for consulting with and taking the views of people on site.

Arrangements for preparing site rules and drawing them to the attention of those affectedand ensuring their compliance.

Monitoring procedures to ensure compliance with site rules, selection and managementprocedures, health and safety standards and statutory requirements.