Item 601 Slope and Channel Protection

1/2

District: / Date: / Project No.: / Co/Rt/Sec:
Contractor: / Project/District Contacts:
Reviewed “√” / Specification Conformance Statement / CMS/ CIM / Measurements / Conformance Comments
Do the slope and/or channel protection conform to the material specification / 601.02
Was the proper curing compound and application rate used? (gutters, concrete slope protection and grouted riprap) / 601.03
Riprap:
Does the installation conform to one of the alternatives set forth in the spec? / 601.04
A,B,C or D
Grouted Riprap or Rock:
Was the grout proportion measured (1Portland:3 Sand)? / 601.05
Grouted Riprap or Rock:
Was the riprap or rock wetted prior to the installation of the grout? / 601.05
Crushed Aggregate:
Does the aggregate conform to 703.19? / 601.06
Grouted Riprap or Rock:
Is the thickness of the slope protection blanket correct? / 601.05
Concrete Slope Protection:
Is the slab the correct thickness? / 601.07
Concrete Slope Protection:
Is the slab in the proper location? / 601.07
Concrete Slope Protection:
Is the toe of the slab thickened to prevent sliding? / 601.07
Concrete Slope Protection:
Was the expansion joint properly installed around the Piers? / 601.07
Concrete Slope Protection:
Was the block grid pattern laid out and installed? / 601.08
Dumped Rock Fill:
Does the material conform to 703.19? / 601.08
Dumped Rock Fill:
Is the rock fill blanket uniform in size and void distribution? / 601.08
Rock Channel Protection:
Is the protected channel per the plan (x-section / profile)? / 601.09

Item 601 Slope and Channel Protection

2/2

Reviewed “√” / Specification Conformance Statement / CMS/ CIM / Measurements / Conformance Comments
Rock Channel Protection:
Does the Rock and Bedding or Fabric conform to 703.19? / 601.09
703.19
Rock Channel Protection:
Was the channel floor prepared prior to the installation of the fabric? / 601.09
Rock Channel Protection:
Was the fabric installed properly (loose, lapped, direction of lap, pin spacing)? / 601.09
Paved Gutter:
Is the dimension shape as shown on the plan? / 601.11
Paved Gutter:
Was the gutter tied into Pavement or other rigid structure? / 601.11
Paved Gutter:
Was the gutter sub-grade properly prepared? / 601.11
Paved Gutter:
Were the impressed joints properly installed? / 601.11
Tied Concrete Block Mat:
Was the filter Fabric installed correctly?(grout?) / 601.12
Was the construction correctly measured? / 601.13