BusinessServicesCommittee

1:30-3:00p.m., November7, 2014, FAC228D

I. 1:30 –1:45 BACS Update (Bob Harkins,William Green)

II. 1:45–2:00ITGovernanceAccountability Report (Brad Englert)

III. 2:00 -2:15 AdministrativeSystems MasterProject–Update(ReneeWallace)

*Impactof ASMPonnon-technicalresources(Discussion)

IV. 2:15-2:30Change ControlProcess–Update(KristiFisher)

V.2:30–2:45How toWork withABL(Discussion)

VI. 2:45-3:00 Priorities(Discussion)

On tapforournext BSCMeeting

I. LearningManagementSystemUpdate(Dave Moss, Mario Guerra) II. ITSApplicationsServicePlan (JulienneVanDerZiel)

Building(Access(Control(and(Security!!!Update"

!

Overview!

# The#university#determined#to#charge#for#BACS#services#beginning#FY#14F15:#

New#security#installation#was#to#be#Unit/project#funded#(historically#the#case)#

Exterior#door#recurring#was#to#be#Common#Good#funded#(new#ITS#Core#Charge#FY#15F16)#

Other#security#recurring#was#to#be#Unit#funded#

Removal#of#security#Units#no#longer#desire#was#to#be#centrally#funded#

#

Status!

1) Billing(Survey(

155#of#169#buildings#have#responded#to#the#survey;#some#are#still#working#on#responses#

#33%#of#expected#revenues#for#FY#14F15#has#been#collected#(buildings#converted#to#VoIP)#

Several#Units#are#appealing#and#did#not#provide#accounts:##BMA,#BME,#EAS,#ETC,#HRC,#NEL#

Requested#removals#are#higher#than#initial#task#force#projections:#

Security(Type(%(Removed(
Card(Readers(42%#
Electrified(Doors(31%#
Alarm(Points(60%#
Panic(Buttons(45%#

#

2) Survey/Removal(of(Unwanted(Security(

#New#survey#and#removal#estimate#is#$3M#

oIncrease#due#to#more#removals#and#addition#of#abatement#

oIt#would#take#3#years#of#Unit#payments#to#cover#the#survey/removal#cost#

RFP#process#for#contractor#expected#to#take#6#months#once#funds#are#identified#

Survey/Removal#projected#to#take#12#months,#sans#contractor#feedback,#for#completion#

#

3) Security(System(Replacement(Strategy(

IT#Governance#V#1.2#October#3,#2014#

#

BACS!Funding!Timeline!

$0.6M!

Declining!Voice!Subsidy!

$2.2M!

$1.6M!

1)!

Funding!Gap!

$0.6M!

09/2014

Charges!

New!CG!Funding!:!$0.4M/FY!

Unit!Funding!:!$1M/FY!

2)!

Survey/Removal!Funding!

$1.5M!=$2.5M!

!!!!!!!Survey/Removal!

!!!!!$3M!

Central!Funding!

3)!

Security!System!Upgrade!

$.5M!=!$5M!

December!

2013!

June!

2014!

September!

2014!

December!

2014!

March!

2015!

June!

2015!

September!

2015!

December!

2015!

March!

2016!

June!

2016!

ITS!–!20141003!

VoIP%and%BACS%Eight%Year1%Cost%Change%Example

(20140929'v1.11'wcg)

Eight%Year%VoIP%Cost%Changes2 / Eight%Year%BACS%Cost%Changes4 / Eight%Year%Overall
Unit'VOIP' Conversion'Cost / University'Copper'
Relocation'
Avoidance3 / ITS'Charges'to' Unit'Δ / Estimated'Unit' OE&M / ITS'Charges'to' Unit'at'Current' Size / Charges'After' Estimated' Removals / Common'Good' Funded / Unit'Δ / University''Δ
BAT/MEZ/BEN / $'''''''''''''''''20,538 / $''''''''''''''''(33,283) / $'''''''''''''('272,352) / $'''''''''''''''''48,824 / $'''''''''''''''656,064 / $'''''''''''''''''23,808 / $'''''''''''''''''45,408 / $'''''''''''''('179,182) / $'''''''''''''('167,057)
NHB / $'''''''''''''''''''3',790 / $''''''''''''''''(23,583) / $'''''''''''''('176,448) / $'''''''''''''''''30,156 / $'''''''''''''''325,152 / $'''''''''''''''118,176 / $'''''''''''''''185,760 / $''''''''''''''''(24,326) / $'''''''''''''''137,851
NUR / $'''''''''''''''''32,659 / $''''''''''''''''(39,178) / $'''''''''''''('302,880) / $'''''''''''''''''55,212 / $'''''''''''''''102,432 / $'''''''''''''''''51,552 / $'''''''''''''''''37,152 / $'''''''''''''('163,457) / $'''''''''''''('165,483)
NOA / $'''''''''''''''''37,598 / $''''''''''''''''(36,135) / $'''''''''''''('339,648) / $'''''''''''''''''52,900 / $'''''''''''''''265,728 / $'''''''''''''''''88,800 / $'''''''''''''''''''8',256 / $'''''''''''''('160,350) / $'''''''''''''('188,229)
SEA / $'''''''''''''''''33,757 / $''''''''''''''''(38,418) / $'''''''''''''('305,856) / $'''''''''''''''''54,969 / $'''''''''''''''350,784 / $'''''''''''''''''66,816 / $'''''''''''''''''61,920 / $'''''''''''''('150,314) / $'''''''''''''('126,812)
POB / $'''''''''''''''''47,175 / $''''''''''''''''(54,013) / $'''''''''''''('304,944) / $'''''''''''''''''74,544 / $'''''''''''''''184,800 / $'''''''''''''''126,240 / $'''''''''''''''''''8',256 / $''''''''''''''''(56,985) / $'''''''''''''('102,742)
CBA/GSB / $'''''''''''''''133,546 / $'''''''''''''('133,701) / $'''''''''''''('524,736) / $'''''''''''''''189,278 / $'''''''''''''''407,328 / $'''''''''''''''128,256 / $'''''''''''''''''99,072 / $''''''''''''''''(73,656) / $'''''''''''''('108,285)
$'''''''''''''''309,063 / $'''''''''''''('358,311) / $''''''''''(2,226,864) / $'''''''''''''''505,883 / $'''''''''''2' ,292,288 / $'''''''''''''''603,648 / $'''''''''''''''445,824 / $'''''''''''''('808,270) / $'''''''''''''('720,757)

1)'Eight'years'was'the'original'horizon'for'the'VoIP'system'in'planning.

2)'Costs'at'time'Unit's'approval'to'convert,'changes'may'have'occurred'since.

3)'$3.2M'cost'to'relocate'all'copper'from'SER'to'EERC'if'VoIP'conversion'had'not'occurred'(orginally'$9M'with'indeterminate'NOC'location,'reduced'assuming'EERC'NOC).

4)'BACS'rates'still'undergoing'review.''Cost'to'remove'undesired'BACS'points,'~$3M,'not'included.

TEXASWHAT STARTSHERECHANGESTHE WORLD

-AfAUSTIN-

ASMP2.0DraftTimeline

, • ,:,.•:• 1\ 'ClJrv1 :.• r::, • J.'.N ' c

, .rrvr'

:'11 •

,: ,

'. ·•)r·c

Enter riseReadiness

TestSupport

Phaaa2

Configure

ArchitectPTestoep1o

rototype

TAlPhase3

Requlfements ValidationStudentVendor

Select•on

Integrator

Selection

StudentSystem

Implementation

PortalVendor

Seect10n

Portallmplementat•on

CoordinateandSUPF!Ort

applicationmodernization

Provided ta

accessandtransparency

11

ReadinessCoordinators

Financial Data Model

Approach to Campus Engagement

HumanCapital

Mgmt/Payroll

Technology

Architecture

FDM

Operational

Sponsors

FDM

HCM/Payroll

Operational

Sponsors

HCMAdvisory

Make policy decisions& provideguidance

Provideinputon

AIC

AITL

TechArch

UBOC

Advisory

Group

Group

projects,policy,

andkey decisions

CustomerSteering

Committee

ProjectTeam

SMEGroups

ProjectTeam

SMEGroups

Define

requirements &

workondetailed

configuration

ProjectTeam

SMEGroups

10/21/2014Universityof Texas-Austin2

ReadinessCoordinators

Approach to Campus Engagement

EnterpriseData

Management

Application

Modernization

DataManagement

Committee

Make policy

decisions

provideguidance

AIC

AITL

Data

Stewards

ProjectTeam

SMEGroups

Provideinputon

projects,policy,

andkey decisions

Define requirements & workondetailed configuration

BusinessIT

Contactsfrom

CampusUnits

ProjectTeam

SMEGroups

10/21/2014Universityof Texas-Austin3