High Value Contracts (More Than One Crore)

S.N. / NIT No. / Name of work / Actual Value(Rs. In Crs) / Name of Contractor / Date of Acceptance / Original date of complition / Progress
(10-11)
(10-11)/147 / ADEN/SIKR Sub Div-Elimination of level crossing No 254 (Dundlodmukandgarh-NUA),LC No 282(Ratanshahar-Chirawa),LC No 309(Surajgarh-LHU),LC No 37(Laxmangarh-FatehpurShekhawati),LC No 49(FatehpurShekhawati-Kayamsar),LC No 50 (Kayamsar-RamgarhShekhawati) and LC No 56 (RamgarhShekhawati-Bissau) by Construction of RCC box for limited use Subway(By cut and cover method) / 3.89 / Jagdish Prasad Aggarwal, Alwar / 15.02.11 / 14.01.12 / 65%
(10-11)/148 / DEN(N) Sub division:- Elimination of level crossing No 123 (GND-RGS),LC No 31(LNH-FPS),LC No 10(SIKR-LNH),LC No 17(SIKR-LNH),LC No 93(NDH-COM)LC No 97(NDH-COM)by Construction of RCC box for limited use Subway & LC No 120 (COM-GND) by construction of RCC Box for normal height Sub Way (By cut and cover method) / 4.06 / Jagdish Prasad Aggarwal, Alwar / 03.01.11 / 02.12.11 / 30%
(10-11)/16 / RE-FL Sec :- Elimination of level crossing No 14 (KORI-KUND),LC No 80(NMK-BAGA),LC No 96(KACA-SMPR)LC No 129(BDHL-RNW)by Construction of RCC box for limited use Subway / 1.79 / SatishMalpaniJaipur / 23.06.10 / 24.09.10 / 54%
10-11/(149) / ADEN/AlwarBandikui Sub Divn.- Providing Limited height subway in lieu of L-xing No. 71, 72,73,75,83,122,&154 in Rewari-Jaipur & LC no. 114 in Alwar-Mathura section by cut & cover technique. (Total Nos. 8 RUB) / 4.85 / Jagdish Prasad Aggarwal, Alwar / 16.12.10 / 15.11.11 / 70%
(10-11)/141 / JP Providing Vacuum dewatered concrete suface in circulating Area of JP Station with glossary pavar block & drainage system / 1.6 / Dhanshree Construction Jaipur / 22.12.10 / 21.06.11 / 70%
(10-11)/118 / ADEN-LINE-JP / FL sub division-Construction of 20 Nos Type II Quarters and 10 Nos hand pump at various unmanned level crossings as per list attached in connection with manning of 10 Nos LC (39Nos) / 1.20 / M/s YadavFabricatersContractor,Jaipur / 03.11.10 / 02.10.11 / 94%
10-11/(188) / Supplying and loading in to ballast hoppers 65mm size machine crushed railway track ballast at Bandikui ballast depot in Jaipur Division of North Western Railway(Quantity 100000 Cum) / 4.94 / Meenesh Contractors & Developers Pvt Ltd, Jaipur / 31.5.11 / 31.5.12 / 60%
(11-12)
11-12/(26) / ADEN-BKI subdivision-BANDIKUI- Up gradation / Development of RPF training centre. / 1.63 / New Everest Stone Crushing,Company, Gurgaon / 22.10.11 / 22.8.12 / 60%
11-12/(150) / JP division -Providing RUB/Limited height subway in lieu of LC no. 131, 138 , 139 ,148 ,152 & 155 in between RE-JP. / 4.33 / Jagdish Prasad Aggarwal, Alwar / 13.8.12 / 12.4.13 / 10%
11-12/(97) / DEN (East)Jaipur section- Day to Day maintenance of new doubling track & Existing track between BKI –KUT(excl.) Section between Km. 150 to 214. ( 64Kms) / 1.64 / Darshan Singh, Ramgarh, Alwar / 8.11.11 / 7.11.12 / 60%
(11-12)/113 / JAIPUR division -Supplying and loading into ballast hoppers 65mm size machine crushed railway track ballast at Nizampur ballast depot in RPC Section of DEN(N) JP sub division of North Western Railway.(Quantity 100385Cum) / 5.34 / M/s. Sura Construction Compoany, Sector-13, Hissar (Haryana) / 20.04.12 / 19.04.13 / 04%
(11-12)/152 / JP Composite work of house keeping and maintenance and operation of civil & electrical installation including horticulture work & development of nursery in HQ office building of NWR Jaipur(24 Months) / 1.67 / B.M.UtilityservicesesPvt Ltd Bajwa(Gujarat) / 13.03.12 / 12.03.14 / 35%
(11-12)/130 / Suppling & Loading into Ballast hoppers 65mm size machine crushed railway track ballast at FL ballast depot in JP Div of NWR(Qty 33034 Cum) / 1.65 / ShriVinayak Stone Cresher,Jaipur / 23.04.12 / 22.10.12 / 46%
(11-12)/69 / ADEN Line/JP Sub - Division -Providing & fixing of railway boundary post, missing hectometer post, kilometer, gradient post & trolley refuses between BAI - FL & JP - SWM sections and cleaning of side drainage / cutting along the track & providing of trolley refuses between km 56/4 - 58/4 & 125/0-1 in JP - SWM section & 234/0 - 235/2 between BAI JP Section and Providing and fixing of LWR board, Curve board, gang beat board, Bridge board of SSE/P.way & JE/ P.way jurisdictions. / 1.33 / M/s RamsawaroopJat,Tonk Road Jaipur / 04.10.11 / 03.04.12 / 40%
(11-12)/112 / JP Division- Sr. DEN(S) JP sub division- The various works in relation to PQRS/TRT & base depot at FL & at sites during relaying with PQRS linking of A.T., Rail Renewal, leading rails, unloading, loading from/on BFR/BRH/KCM’s, spreading of PRC sleepers, fabrication of panels & other misc. works in Connection with CTR 30 Kms. / 2.59 / ShriShishupalKumawat,Badhal,Jaipur / 19.03.12 / 18.02.13 / 58%
12-13
12-13/(23) / DEN ¼East½Jaipur section Day to Day maintenance of new doubling track & Existing track between Alwar –Rewari stations from Km 0 to 74.2 / 1.96 / Darshan Singh, Ramgarh, Alwar / 3.7.12 / 2.7.13 / 25%
(12-13)/9 / JP division- RE-FL Sec.- Elimination of level crossing No.116, 117, 118 (KNMP-BDHL), 127 & 128 (PCMK-RNW) & LC No.122 & 123 (BDHL-PCMK) by construction of RCC box for limited use subway & Provision of additional water way at Km 67/0-1 (1.50m x 1.50m) RCC box for breaches over JP division near LC No. 54 (Cut & Cover Method). / 4.85 / M/s Akrati Engineers,
28/B,Sarla
Bagh
Extension,
DayalBagh,Agra (UP) / 13.08.12 / 12.02.13 / WIP
(12-13)/10 / RE-FL Sec.- Elimination of level crossing No.47(NNL-APJ), 52 (NIP-APJ), 54(NIP-DBLA), 63 (DBLA-JILO) & 73 (MADA-NMK) by construction of RCC box for limited use subway (Cut & Cover Method). / 3.22 / M/s Hari
Singh & Company, 101,Model
Town , Narwana,
DisttJind
(Haryana) / 01.10.12 / 31.03.13 / WIP
(12-13)/68 / RE-FL Sec. - Elimination of level crossing No.58, 59 (NIP-DBLA), .78 (NMK-BAGA), 89 (BAGA-KAWT), LC No.92 (KAWT-KACA), 101(KACA-SMPR), 105 (SMPR- RGS) & 110 (RGS-KMNP) by construction of RCC box for limited use subway (Cut & Cover Method). / 5.19 / Satish Malpani,2/108,Royal Green Apartment,SirsiRoad,Jaipur- / 07.09.12 / 06.03.13 / WIP