6 years in the planning, survey, design and application of engineering practices relating to soil and water conservation with M&E, NRCS Programs, Standards and Specifications, Retaining Walls, Grade Control Structures, Embankment and Spillways, Channels, Roller Compacted Concrete, HEC-RAS, SITES, Breach Maps.

Experience and Qualifications:

Civil Engineering Technician, M&E Consultants

Big Slough Watershed Developed figures used in the interdisciplinary team field review of Natural Resources to re-evaluate sites 1, 2, 3, 6, 7, 10, & 11. Imported topographic surveys taken of the different sites into Land Desktop to develop terrain models.

Sallisaw Creek Watershed – Rehab of FWRS No. 32 Developed construction drawings, bid schedule, construction specifications, and computed quantities for the rehabilitation of this site.

Caney Coon Watershed – Rehab of MPD No. 2 Developed construction drawings, bid schedule, construction specifications, and computed quantities for the rehabilitation of this site.

Big Creek Watershed – Rehabilitation of FWRS No. 6 Developed figures used in the Supplemental Watershed Plan and Environmental Assessment (EA) for the rehabilitation of the dam. Imported topographic surveys taken into Land Desktop to compute quantities, cross sections, profiles, and to develop alternatives for the EA.

Poteau River Watershed – Rehabilitation of MPD No. 5 and FWRS No. 8 Developed figures used in the EA for the rehabilitation of the sites. Imported topographic surveys taken into Land Desktop to compute quantities, cross sections, profiles, and to develop alternatives for the EA.

West Fork Point Remove Watershed, FWRS No. 7 Developed figures used in the EA for the rehabilitation of the site. Imported topographic surveys taken into Land Desktop to compute quantities, cross sections, profiles, and to develop alternatives for the EA.

Muddy Fork of the Illinois River – Rehabilitation of MPD Nos. 3 & 4 Developed construction drawings, bid schedule, and specifications for the rehabilitation of the site which met NRCS criteria. Imported topographical surveys taken into Land Desktop, generated terrain models, computed quantities, cross sections, and profiles.

Upper Brushy Creek No. 13A Developed the construction drawings, bid schedule, and specifications for the rehabilitation of the referenced sites for Texas NRCS which met NRCS criteria. Imported topographical surveys taken into Land Desktop, generated terrain models, computed quantities, cross sections, and profiles.

East Fork Above Lavon Site No’s. 3D, 3E, 3D, & 2B Prepared the construction drawings, bid schedule, and specifications for the rehabilitation of the referenced sites for Texas NRCS which met NRCS criteria. Imported topographical surveys taken into Land Desktop, generated terrain models, computed quantities, cross sections, and profiles. Was a member of the surveying crew that collected field data.

Montgomery County EWP Prepared construction drawings to repair stream channel erosion, erosion to an emergency spillway and erosion caused by water overtopping county and city roads.

Choctaw GSS Nos. 103 & 105 Prepared the construction drawings to repair stream channel erosion and flooding due to out of bank flow. These sites included the design of waterways, diversions, gabion chutes, HEC-RAS model, and computation of all quantities.

Elm Fork MPD No. 19 Prepared construction drawings, developed quantities, specifications and bid schedule for Phase II of a federally funded multipurpose dam. The dam provides flood control, municipal water supply, and recreation for the city of Munster. Structural drawings include a 50 ft. tall municipal inlet, a 50 ft. tall flood control inlet, catwalk, impact basin, and outlet box for the municipal water supply.

Muddy Fork of the Illinois River – Rehabilitation of Multiple Purpose Dam Nos. 3 & 4 Developed figures used in the EA for the rehabilitation of the site. Imported topographic surveys taken into Land Desktop to compute quantities, cross sections, profiles, and to develop alternatives for the EA.

Sallisaw Creek Watershed Rehabilitation of FWRS Nos. 32, 33, & 34 Developed figures used in the EA for the rehabilitation of these sites. Imported topographic surveys taken into Land Desktop to compute quantities, cross sections, profiles, and to develop alternatives for the EA.

Poinsett Watershed – Supplemental Watershed Plan 4 & Environmental Assessment Developed figures used in the EA for the rehabilitation of this site. Imported topographic surveys taken into Land Desktop to compute quantities, cross sections, profiles, and to develop alternatives for the EA.

Cottonwood Creek Watershed – Rehabilitation of FWRS No. 17 Developed construction drawings, developed quantities, bid schedule, and construction specifications for the rehabilitation of this site. Imported topographic surveys taken into Land Desktop to compute quantities, cross sections, and profiles.

Sallisaw Creek Watershed – Rehabilitation of FWRS No. 18M & 26 Developed construction drawings, developed quantities, bid schedule, and construction specifications for the rehabilitation of these sites. Imported topographic surveys taken into Land Desktop to compute quantities, cross sections, and profiles.

TX CO-01 Contract Collected topography information using a Topcon GPS Total Station. Imported topographical surveys taken into Land Desktop, generated terrain models, computed quantities, cross sections, and profiles. Developed final drawings for engineering practices of terraces, waterways, grade stabilization structures, land leveling, irrigation pipelines, farm ponds, and diversion terraces. Served as a member of the survey crew on many of these practices.