Exercise 3: “Rework”_Is No Work at All

We have been appointed as a Six Sigma breakthrough improvement team to look into rework costs and inefficiencies in the company’s invoicing process. Our breakthrough improvement team consists of representatives from the groups that provide the billing information and the groups that process the invoices. At our first meeting, we listed the major steps involved in the process and began constructing a flow diagram. Next, we looked at each step and began detailing the kinds of problems that are detected there. Finally, we listed specific activities that take place to resolve the individual problems that arise. On our completed flow diagram, we identified nine rework loops in the invoicing process.

To estimate the cost associated with rework, each team member took responsibility for one of the rework loops. The assignment was twofold: (1) conduct a two-week study to tally the number of invoices that go through that rework loop, and (2) take the detailed rework activities, identify who is involved, and determine how much time is spent in that activity.

We decided against performing a detailed “time-and-motion” study. Instead, we agreed that reasonable estimates could be generated by the “jury method”—simply ask the people involved to come up with a consensus estimate of the time it takes to complete the activity.

To convert these time estimates into dollars, one of the team members volunteered to meet with someone from the personnel department to determine the average salaries of the various clerks, supervisors, and managers who get involved in the rework loops. (We have a number of clerical salary levels in our company, and we designate them as “Grade 1,” “Grade 2,” etc., with the higher salaries going to the higher grades.)

We have conducted our studies and are meeting again. Today, we will be analyzing our problem tallies and time estimates. (See the accompanying table of data. The first line has the number of invoices processed in the rework loop. The next lines are the number of minutes required per invoice for each person to do the rework. Note that some of the calculations have been completed for you.)

INVOICING PROCESS REWORK LOOPS

Total of All Invoices Processed During Two-Week Study = 327

Rework Loops

123456789

Number of Invoices Requiring Rework2414341172938513

Time Required (minutes)

Billing Department

Manager————30———30

Supervisor20——560—5—45

Grade 545—5.10—510560

Grade 3—10 10 15 20 10 15 10—

Other Departments

Manager10 — — — 15 —— —

Supervisor 10 ——5 15 ———20

Grade 7———5 10 —

Grade 5 10 10 — — 10 —10 —

Rework Cost Per Invoice

Total Rework Cost During Study

Assumptions

50 work-weeks per year

40 work-hours per week

2,000 work-hours per year

120,000 work-minutes per year

Average Salaries (non-loaded)

LEVEL$ANNUAL$/MIN
Manager142,000_____

Supervisor 34,000_____

Grade 7 29,000_____

Grade 6 25,000_____

Grade 5 22,000_____

Grade 4 18,000_____

1List the steps that the team took in approaching the problem. What do_you think of their approach?

2What rework loops should the team focus on?

3Would the results of the Pareto analysis have been different if you had based it on the number of invoices requiring rework, rather than on the cost of rework?

Use the space below to rank-order the rework loops and show the cumulative percents of total.

ReworkTotal Rework CostCumulative Percent
Loopduring Studyof Total

Construct a Pareto diagram of the rework loop data using the grid below.

©McGraw-Hill 2002. To customize this overhead for your audience, download it from ( The document can then be opened, edited, and printed using Microsoft Word or other popular word-processing software.