Schneider T200E Control Unit and RTU Test Form / Document Number: ECP 11-0532a
Version: 3.0
Date: 12/12/2016

Schneider T200E Control Unit and RTU Test Form

Substation Name
Substation Number
Control Unit Serial No
Switchgear Type(s)
Switchgear Serial No(s)
Switches and FPIs Fitted ()
SW1 / SW2 / SW3 / SW4
FPI1 / FPI2 / FPI3 / FPI4
ENMAC
System Code / RTU Address
Main Telephone No / Standby Telephone No
Paknet Comms
Paknet ESN / Paknet NUA1
RSSI / FSSI / Base Station
Preliminary Checks / ()
Inspection satisfactory (no visible signs of damage etc)
Check control unit is correctly earthed
Check the security of all umbilical cable plugs
Check that a data acquisition module is installed for each FPI
Check battery is installed and correctly connected
Check mains supply is correctly installed and fused
Check actuator polarity (positive for rotary actuator or negative for linear actuator)
Check FPI phase CTs have been tested and shorting-link removed
Connect battery
Turn on mains supply
Functional Checks / ()
Select Local
Check that each remotely controlled switch/circuit-breaker can be operated from the front panel and that the local indications are correct
Select Remote
Check that each remotely controlled switch/circuit-breaker cannot be operated from the front panel
Paknet Pad Installation and Configuration / ()
Install Paknet pad
Connect aerial lead, power supply and data lead (do not connect the data cable to the RTU at this stage)
Register Paknet pad
Check pad registration using Vodafone automated health check (08700 700600 option 1) – enter ESN and record RSSI (>60), FSSI (>14), NUA and base station
Check pad configuration using Vodafone Customer Services (08700 700600 option 2)
Port / Port Parameters
NUA1 / Schneider RTU / 0:0, 1:0, 2:0, 3:0, 4:1, 5:0, 6:5, 11:13 12:0, 13:0, 15:0, 21:0
NUA2
Contact Commissioning Operator and provide ESN, NUA, RSSI, FSSI and base station. Request system code, RTU address and telephone numbers
T200 Control Module Configuration / ()
Connect laptop PC to Control module and configure using the parameters below
Name / Site Number eg 123456
Delayed AC supply OFF / 4h
Setup Time / Stop Clock (Do not correct date and time)
Configure FPI module and configure using the parameters below
Phase level / 600A
Earth level / 90A
Minimum fault duration / 50ms
After AC supply ON / Yes (mains derived on-site) / No (mains derived remote to site)
After delay / 2h
T200 Comms (Wisp+) Module Configuration / ()
Connect laptop PC to Wisp+ module and configure using the parameters below
RTU protocol / ExtWisp+
System code / As specified by Commissioning Operator
RTU address / As specified by Commissioning Operator
Modem type / Paknet
Comms Parameters
Host baud rate / 4800
Host paknet number (main) / As specified by Commissioning Operator
Host paknet number (standby) / As specified by Commissioning Operator
Alarm Parameters
Set all alarms for the switches and FPIs fitted to immediate
Set alarms for Local, Immediate AC Supply Off, Delayed AC Supply Off, FPI Module Fault, Charger Fault, Battery Fault and SW Supply OFF to immediate
Primary Injection Earth Fault Tests (ensure mains supply is off)
FPI1 / FPI2
Conductors / Ind () / Current / Conductors / Ind () / Current
L1-E / A / L1-E / A
L2-E / A / L2-E / A
L3-E / A / L3-E / A
FPI3 / FPI4
Conductors / Ind () / Current / Conductors / Ind () / Current
L1-E / A / L1-E / A
L2-E / A / L2-E / A
L3-E / A / L3-E / A
The earth fault should operate at approx 90A
Secondary Injection Overcurrent Tests (ensure mains supply is off)
FPI1 / FPI2
Terminals* / Ind () / Current / Terminals* / Ind () / Current
A / A
A / A
A / A
FPI3 / FPI4
Terminals* / Ind () / Current / Terminals* / Ind () / Current
A / A
A / A
A / A
The overcurrent should operate at approx 1.2A for a 600A primary setting (500/1 CT)
*FPI Secondary Injection Terminal Designations
Switch / Terminals / Switch / Terminals / Switch / Terminals
RSW1 / D111-D131 / RSW2 / D111/2- D131/2 / SE6 / D111-D131
D131-D151 / D131/2- D151/2 / D131-D151
D151-D111 / D151/2- D111/2 / D151-D111
ENMAC Commissioning / ()
Connect Paknet pad
Contact Commissioning Operator and confirm unit dials in
Once call has dropped operate dummy circuit-breaker from ENMAC
Commission telecontrol (see ENMAC telecontrol form 5.32b)
Disconnect laptop
On-load Tests
FPI1 / FPI2 / FPI3 / FPI4
Terminals* / Voltage / Terminals* / Voltage / Terminals* / Voltage / Terminals* / Voltage
mV / mV / mV / mV
mV / mV / mV / mV
mV / mV / mV / mV
Laptop / A / Laptop / A / Laptop / A / Laptop / A
ENMAC / A / ENMAC / A / ENMAC / A / ENMAC / A
Final Checks / ()
Check all circuits are clearly labelled
Check all connections secure
Check Remote Control selected
Check All outstanding ENMAC alarms cleared
Complete asset data form and submit to ART
Test Equipment
Purpose / Make/Type / Serial Number
Certification / ()
All tests have been completed satisfactorily
Comments
Commissioning Engineer / Signature / Date

This test form should be left on-site, in a plastic wallet, in the RTU cabinet.