60% PS&E Checklist
______
CORRIDOR: CONTRACT:
CONSULTANT: LETTING DATE:
NTTA Use Only
DATE: REVIEWED BY:
Comments: ______
PMO/GEC Use OnlyGrade ABCDF
AcceptRejectDate: By:
Comments:
______
DATE: REVIEWED BY:
Verify all design is in compliance with the NTTA Design Guidelines
Check all elements that apply to the project. If not applicable, explain why.
Color & FinishesLightingSign StructuresSignageWallsBridge Structures
Mainlane ElementsToll Gantry StructuresLandscape/IrrigationPublic Art
Comments:
NOTE: If any of the above boxes are not checked, an explanation must be provided as why Guidelines cannot be met.
Verify all design is in compliance with the following NTTA manuals and/or guidelines:
Roadway Electrical SystemMaintenance DesignPS&E Procedures Manual
Crash AttenuatorSign & Traffic Control Devices
Comments:
NOTE: If any of the above boxes are not checked, an explanation must be provided as why Guidelines cannot be met.
______
Design coordinated with adjacent project.
Verify all design in compliance with the established design criteria for this project.
Submittal being tracked in EPDS.
Comments:
Previous Plan Submittal
Revised PlansComments incorporated from previous review
Comments:
Consistent with NTTA CAD Guidelines
Title Sheet Updates
Project DescriptionContract No.Section No.Project Limits
Project LengthBridge LengthBegin/End Sta.Design Speed & ADT
Location MapTDLR InspectionSignature Block
Exceptions, Equations and Railroad CrossingsAdoption Date of Governing Specifications
Comments:
Index Sheet(s) Updates
Volumes ListedTxDOT Standards NTTA Standard DrawingsMunicipal Standards
Comments:
Project Layout Updates
Major Intersections LabeledLegible Project Stationing
Comments:
Typical Sections Updates (Include labels, legends and dimensions where appropriate)
------Existing------
ROWShouldersBorder WidthLane Width
BarrierType of CurbMedian
------Existing Pavement Structure------
LTSHMAC BaseCRCPJRCP
Comments:
------Proposed------
Existing/Proposed ROWShouldersCross SlopesLane Width
Type of CurbSide SlopesStation LimitsLane Direction
Border WidthWallsFlumesMow Strips
Median
------Proposed Pavement Structure------
LTSEmbankment TypeHMAC TypeCRCPJRCPPrime Coat
Comments:
General Notes Updates
IncludedSpecification DataSpecial Specification (Project Specific)
Comments:
Summary Sheet(s) - Preliminary
Estimate & Quantity SummaryTCPRemovalEarthwork
RoadwayDrainageRetaining WallsBridge
Pavement Marking/DelineationITSSW3PMiscellaneous
Comments:
Traffic Control Plan Updates
Sequence of Work NarrativeAdvance Warning SignsConstruction Sequence Typicals
Temporary Pavement Temporary ShoringDetour/ Alignment
Phasing LayoutWork Zone Pavement MarkingWork Zone Signing
Channelization DevicesTemporary Traffic Signals/Illumination
Standards
Comments:
Removal Plan Updates
Existing Roadway Topography (pavement, curb, driveways, etc.)Known existing utilities (OH or UG)
Removal items identifiedLegend
Comments:
Geometric Layout Updates
Control Point CoordinatesBaseline and/or CenterlineGraphic Scale
North ArrowOverall view of project with primary control monumentation
Roadway NamesChain NamesLane Assignments
Comments:
Horizontal Control Alignment Data Updates
Curve DataPC, PI, PT Stations & CoordinatesRadius and DOC
Deflection AngleTangent Length and bearingsStations and Station Equations
Station/offset information (relative to other alignments)
Comments:
Superelevation Data Sheet Updates
Begin/End SuperelevationSuperelevation Rates
Comments:
Plan/Profile Sheet(s) Updates
------Plan View------
Existing/Proposed ROWExisting/Proposed UtilitiesExisting/Proposed Cross Drainage
Lane AssignmentsStationing/BearingsBench Mark
Control Points LabeledNorth ArrowHorizontal Scale
Type of CurbRiprapMow Strips
Retaining WallsCrash AttenuatorsMBGF/Barrier/Rail
SGT/TASConstruction EasementsHorizontal Curve Data
Existing Roadway Topography (Background)Proposed Roadway (Foreground)
Comments:
------Profile View ------
Existing Ground ProfileProposed Grade LineCross Drainage Structures
Station/ElevationGradesVertical Curve Data
Comments:
Paving & Bridge Deck Contours - Preliminary
Intersection(s)Bridge(s)
Comments:
Miscellaneous Roadway Details (ADA Items, Transition for Curb Ends, etc.) - Preliminary
IncludedIn progress
Comments:
Retaining Wall Details (Preliminary)
Plan & ProfileBegin/End StationsTypical Sections
Comments:
Drainage Updates
Drainage Area MapDischarge RelationshipStorm Drain Layouts
Drainage CalculationsStorm Drain ProfilesStorm Drain Master Plan
Comments:
Culvert Layout Updates
Existing Plan/ProfileProposed Plan/ProfileDesign Data (Size, Length, Type)
Draft Hydraulic Report(s) (Bridge Class only)
Comments:
Utility Plan Updates
Existing Utilities LayoutProposed Utilities LayoutConflict Resolution
Comments:
Bridge Layout(s) Updates
Plan and ElevationBegin/End StationingSpansRail
Riprap LimitsTypical SectionsTest Hole Data
Comments:
Bridge Detail(s) - Preliminary
Abutment DetailsBent DetailsSlab DetailsBeam Unit Details
Quanity TablesCompliance with Aesthetic Criteria
Comments:
Railroad Exhibit Updates (when required)
TxDOT ChecklistRailroad Checklist (UPRR, BNSF, DART, etc.)
Comments:
Signing Layout - Preliminary
Sign LayoutGuide Sign DetailsOH Sign Structure Elevations
Preliminary Sign Support Details
Comments:
Illumination & Signal Layout – Preliminary
Illumination Layout(s)Signal Layout(s)Signal Phase DiagramTemporary Signal
Comments:
Pavement Marking & Delineation Layout - Preliminary
Pavement Marking PlanDesign details
Comments:
ITS Layout Updates
DMS LocationsCCTV Camera LocationsITS LegendPower Source
AVI Speed Map AntennaeTraffic SensorsPavement Sensors
Fiber Conduit LayoutGround Box Locations (1000’ min. spacing)
Comments:
Landscape and Irrigation Updates
------Landscape------
Plant LayoutPlanting DetailsLegend
------Irrigation------
Irrigation LayoutHydraulic DataControl System
Fiber ConnectionPower Source
Comments:
Storm Water Pollution Prevention Plan – SW3P - Preliminary
EPICSW3P site plan for construction phasesSW3P Data Sheet
Comments:
Earthwork Cross Sections – Preliminary
50’ IntervalsPavement LimitsRetaining WallsROW
Side SlopesVertical & Horizontal ControlBarrier/Rail
Comments:
Estimate Updates
Cost
Comments:
Proposal – Preliminary
Proposal Data List provided to PMO Specification Team
Comments: