CONTRACT No. AT.10/2009
INTEGRATED FIRE DETECTION, FIRE ALARM
AND FIRE EXTINGUISHING SYSTEM
VOLUME 2
PART VI:STATEMENT OF COMPLIANCE
AT.10/2009Vol.2, Part VI: Statements of CompliancePage 1
«Cyta PROPRIETARY AND CONFIDENTIAL»
CONTRACT No. AT.10/2009
INTEGRATED FIRE DETECTION, FIRE ALARM
AND FIRE EXTINGUISHING SYSTEM
Vol. 2, PART VI: STATEMENT OF COMPLIANCE
Paragraph / Title / ComplianceStatus / Comments
VOLUME 1 - CONTRACTUAL SPECIFICATION
Vol.1-Part I / INSTRUCTIONS TO PERSONS TENDERING
Vol.1-Part I- 1. / TENDER INVITATION
Vol.1-Part I- 2. / CLOSING DATE
Vol.1-Part I- 3. / EXTENT OF TENDERS
Vol.1-Part I- 4. / SUPPLY AGREEMENT
Vol.1-Part I- 5. / CONTRACT DESIGNATION
Vol.1-Part I- 6. / TENDER IDENTIFICATION
Vol.1-Part I- 7. / PHYSICAL SIZE OF TENDER PACKAGE
Vol.1-Part I- 8. / VALIDITY
Vol.1-Part I- 9. / PARTICIPATION GUARANTEE
Vol.1-Part I- 10. / TENDER PRESENTATION
Vol.1-Part I- 11. / CORRESPONDENCE LANGUAGE AND TENDER COPIES
Vol.1-Part I- 12. / STATEMENT OF COMPLIANCE AND SUPPORTING LITERATURE
Vol.1-Part I- 13. / INTERPRETATION OF TENDER
Vol.1-Part I- 14. / INFORMATION FOR TENDER PREPARATION
Vol.1-Part I- 15. / TENDER PREPARATION COSTS
Vol.1-Part I- 16. / AGENCIES
Vol.1-Part I- 17. / PRICES
Vol.1-Part I- 18. / PAYMENT TERMS
Vol.1-Part I- 19. / TAXES
Vol.1-Part I- 20. / SAMPLES
Vol.1-Part I- 21. / OPTIONS
Vol.1-Part I- 22. / ORIGIN OF MATERIALS AND EQUIPMENT
Vol.1-Part I- 23. / REFERENCES
Vol.1-Part I- 24. / MAINTENANCE AGREEMENT
Vol.1-Part I- 25. / TENDER EVALUATION
Vol.1-Part I- 26. / TENDER ACCEPTANCE
Vol.1-Part I- 27. / TENDER AWARD
Vol.1-Part I- 28. / STAMPING OF DOCUMENTS
Vol.1-Part I- 29. / PERFORMANCE GUARANTEE (BOND)
Vol.1-Part I- 30. / BANK CHARGES
Vol.1-Part I- 31. / WARRANTY
Vol.1-Part I- 32. / VARIATIONS IN TYPES AND QUANTITIES
Vol.1-Part I- 33. / DELIVERY
Vol.1-Part I- 34. / TRANSPORTATION
Vol.1-Part I- 35. / CLARIFICATION OF TENDERS
Vol.1-Part I- 36. / TECHNICAL INFORMATION
Vol.1-Part I- 37. / OWNERSHIP OF SPECIFICATION DOCUMENTS
Vol.1-Part I- 38. / PRICE OF TENDER DOCUMENTS
Vol.1-Part I- Appendix Ι / LETTER OF GUARANTEE
Vol.1-Part II / FORMAL TENDER
Vol.1-Part III / SCOPE
Vol.1-Part IV / SUPPLY AGREEMENT
Vol.1-Part IV-S.A.- 1. / DEFINITIONS
Vol.1-Part IV-S.A.- 2. / AGREEMENT INTERPRETATION
Vol.1-Part IV-S.A.- 3. / CONTRACTOR TO INFORM ITSELF FULLY
Vol.1-Part IV-S.A.- 4. / SCOPE OF THE AGREEMENT, CΥΤΑ’S RESPONSIBILITIES AND NOTICE TO PROCEED
Vol.1-Part IV-S.A.- 5. / PRICES
Vol.1-Part IV-S.A.- 6. / PAYMENT TERMS
Vol.1-Part IV-S.A.- 7. / TAXES AND DUTIES
Vol.1-Part IV-S.A.- 8. / PAYMENT DUE FROM THE CONTRACTOR
Vol.1-Part IV-S.A.- 9. / DURATION
Vol.1-Part IV-S.A.- 10. / PERFORMANCE BOND / BANK GUARANTEE OR ADVANCE PAYMENT GUARANTEE
Vol.1-Part IV-S.A.- 11. / BANK CHARGES
Vol.1-Part IV-S.A.- 12. / GENERAL OBLIGATIONS
Vol.1-Part IV-S.A.- 13. / CONTRACTOR’S OBLIGATIONS
Vol.1-Part IV-S.A.- 14. / ORDERING
Vol.1-Part IV-S.A.- 15. / ACCESS TO PREMISES, FACTORY TESTS AND INSPECTION
Vol.1-Part IV-S.A.- 16. / DELIVERY AND STORAGE
Vol.1-Part IV-S.A.- 17. / DELAY IN DELIVERY
Vol.1-Part IV-S.A.- 18. / INSTALLATION
Vol.1-Part IV-S.A.- 19. / ACCEPTANCE
Vol.1-Part IV-S.A.- 20. / REJECTION AND REPLACEMENT
Vol.1-Part IV-S.A.- 21. / TITLE AND RISK
Vol.1-Part IV-S.A.- 22. / DEFAULT
Vol.1-Part IV-S.A.- 23. / INSURANCE
Vol.1-Part IV-S.A.- 24. / WARRANTIES
Vol.1-Part IV-S.A.- 25. / CΥΤΑ’S RIGHTS
Vol.1-Part IV-S.A.- 26. / FORCE MAJEURE
Vol.1-Part IV-S.A.- 27. / LIMITATION OF LIABILITY
Vol.1-Part IV-S.A.- 28. / INDEMNIFICATION FOR DAMAGE TO PROPERTY AND INJURY TO PERSONS
Vol.1-Part IV-S.A.- 29. / CONFIDENTIALITY AND NON-DISCLOSURE OF PROPRIETARY INFORMATION
Vol.1-Part IV-S.A.- 30. / LICENCE RIGHTS
Vol.1-Part IV-S.A.- 31. / PATENTS, TRADEMARKS AND OTHER PROPRIETARY RIGHTS
Vol.1-Part IV-S.A.- 32. / ASSIGNMENT
Vol.1-Part IV-S.A.- 33. / ARBITRATION
Vol.1-Part IV-S.A.- 34. / AGREEMENT AMENDMENTS
Vol.1-Part IV-S.A.- 35. / GOVERNMENTAL APPROVALS
Vol.1-Part IV-S.A.- 36. / NOTICES AND DOCUMENTATION
Vol.1-Part IV-S.A.- 37. / AGREEMENT MANAGEMENT
Vol.1-Part IV-S.A.- 38. / SEVERABILITY AND WAIVER
Vol.1-Part IV-S.A.- 39. / COMPLIANCE WITH THE LAW
Vol.1-Part IV-S.A.- 40. / APPLICABLE LAW; INTERPRETATION AND LANGUAGE
Vol.1-Part IV-S.A.- 41. / SURVIVAL
Vol.1-Part IV-S.A.- 42. / COUNTERPARTS
Vol.1-Part IV-S.A.- 43. / LIST OF ANNEXES
Vol.1-Part IV-S.A.- 44. / MISCELLANEOUS
Vol.1-Part IV-S.A.- 45. / EXPENSES OF AGREEMENT
Vol.1-Part V / MAINTENANCE AGREEMENT
Vol.1-Part V-M.A.- 1. / INTERPRETATION
Vol.1-Part V-M.A.- 2. / SCOPE OF THE AGREEMENT
Vol.1-Part V-M.A.- 3. / CONTRACTOR’S OBLIGATIONS
Vol.1-Part V-M.A.- 4. / EXEMPTED SERVICES
Vol.1-Part V-M.A.- 5. / CHARGES AND PAYMENT
Vol.1-Part V-M.A.- 6. / DELAY IN THE PERFORMANCE OF THE SERVICES
Vol.1-Part V-M.A.- 7. / PERFORMANCE BOND
Vol.1-Part V-M.A.- 8. / WARRANTIES
Vol.1-Part V-M.A.- 9. / LIABILITY
Vol.1-Part V-M.A.- 10. / INTELLECTUAL PROPERTY RIGHTS
Vol.1-Part V-M.A.- 11. / INDEMNITY
Vol.1-Part V-M.A.- 12. / FORCE MAJEURE
Vol.1-Part V-M.A.- 13. / CYTA’S GENERAL OBLIGATIONS
Vol.1-Part V-M.A.- 14. / FALSE FIRE ALARMS
Vol.1-Part V-M.A.- 15. / INSURANCE
Vol.1-Part V-M.A.- 16. / TERM AND TERMINATION
Vol.1-Part V-M.A.- 17. / ALTERNATIVE REMEDY TO TERMINATION
Vol.1-Part V-M.A.- 18. / CONFIDENTIALITY
Vol.1-Part V-M.A.- 19. / SUB-CONTRACTING
Vol.1-Part V-M.A.- 20. / VARIATIONS
Vol.1-Part V-M.A.- 21. / ASSIGNMENT
Vol.1-Part V-M.A.- 22. / RELIANCE ON INSTRUCTIONS
Vol.1-Part V-M.A.- 23. / NOTICES
Vol.1-Part V-M.A.- 24. / ENTIRE AGREEMENT
Vol.1-Part V-M.A.- 25. / GOVERNING LAW AND JURISDICTION
Vol.1-Part V-M.A.- 26. / GENERAL
Vol.1-Part V-M.A.- 27. / COUNTERPARTS
Vol.1-Part VI / IMPLEMENTATION SCHEDULE
Vol.1-Part VII / BILL OF QUANTITIES AND PRICE BREAKDOWN
Vol.1-Part VII- 1. / GENERAL
Vol.1-Part VII- 2. / GUIDELINES FOR RESPONDING TO THE BILL OF QUANTITIES AND PRICE BREAKDOWN
Vol.1-Part VII- TABLE S1 / SYSTEM SOFTWARE AND EQUIPMENT - PHASE I
Vol.1-Part VII- TABLE S2 / SYSTEM EQUIPMENT - PHASE II
Vol.1-Part VII- TABLE S3 / SERVICES - PHASE II
Vol.1-Part VII- TABLE S4 / IMPLEMENTATION OF PHASE I
Vol.1-Part VII- TABLE S5 / HALON DISPOSAL
Vol.1-Part VII- TABLE S6 / MANPOWER TRAINING
Vol.1-Part VII- TABLE S7 / DOCUMENTATION
Vol.1-Part VII- TABLE S8 / TESTING EQUIPMENT AND TOOLS
Vol.1-Part VII- TABLE M1 / SPARE PARTS
Vol.1-Part VII- TABLE M2 / SYSTEM MAINTENANCE
Vol.1-Part VII- TABLE M3 / SWAP/REPAIR
Vol.1-Part VII- TABLE M4 / SYSTEM SUPPORT
Vol.1-Part VII- TABLE M5 / LABOUR RATES FOR INCIDENTAL WORKS
VOLUME 2 - TECHNICAL SPECIFICATION
Vol.2-Part I / GENERAL TECHNICAL SPECIFICATION
Vol.2-Part I- 1. / Scope
Vol.2-Part I- 2. / GENERAL
Vol.2-Part I- 3. / STANDARDS
Vol.2-Part I- 4. / DEVIATION FROM THE SPECIFICATION
Vol.2-Part I- 5. / TENDERER´S PROFILE AND RELEVANT EXPERIENCE
Vol.2-Part I- 6. / QUALITY ASSURANCE
Vol.2-Part I- 6.1. / Manufacturers
Vol.2-Part I- 6.2. / TENDERERS
Vol.2-Part I- 7. / DESIGN REQUIREMENTS
Vol.2-Part I- 7.1. / Design Life
Vol.2-Part I- 7.2. / Products of Proven Design - Uniformity
Vol.2-Part I- 7.3. / Labelling
Vol.2-Part I- 7.4. / Accessibility
Vol.2-Part I- 7.5. / Mechanical Structures - Finishing
Vol.2-Part I- 7.6. / Modern Techniques
Vol.2-Part I- 7.7. / Components
Vol.2-Part I- 7.8. / Controls
Vol.2-Part I- 7.9. / Arrangement of Terminations
Vol.2-Part I- 7.10. / Plug and Socket Connections
Vol.2-Part I- 7.11. / Layout of Equipment
Vol.2-Part I- 7.12. / Type Approval of Telecommunication Equipment
Vol.2-Part I- 8. / GENERAL HARDWARE REQUIREMENTS
Vol.2-Part I- 8.1. / COMPONENTS
Vol.2-Part I- 8.2. / PRINTED CIRCUIT BOARDS
Vol.2-Part I- 8.3. / INSTALLATION MATERIALS
Vol.2-Part I- 8.4. / WIRING AND CABLING
Vol.2-Part I- 8.5. / POWER SUPPLY
Vol.2-Part I- 8.6. / dimensioning
Vol.2-Part I- 9. / OPERATION AND MAINTENANCE
Vol.2-Part I- 9.1. / Reliability
Vol.2-Part I- 9.2. / Maintainability
Vol.2-Part I- 9.3. / Operational Aspects
Vol.2-Part I- 10. / SAFETY REQUIREMENTS
Vol.2-Part I- 10.1. / Safety of Personnel
Vol.2-Part I- 10.2. / Earthing
Vol.2-Part I- 10.3. / Noise Level
Vol.2-Part I- 11. / OPERATIONAL CONSIDERATION
Vol.2-Part I- 11.1. / Protection of Equipment
Vol.2-Part I- 11.2. / Lightning Protection and Transients
Vol.2-Part I- 11.3. / Radio Frequency Interference
Vol.2-Part I- 11.4. / Switching Transients
Vol.2-Part I- 11.5. / Electromagnetic Radiation
Vol.2-Part I- 12. / CLIMATIC AND ENVIRONMENTAL CONDITIONS
Vol.2-Part I- 12.1. / General
Vol.2-Part I- 12.2. / Conditions During Transport, Storage and Installation
Vol.2-Part I- 12.3. / Conditions During Normal Operation
Vol.2-Part I- 12.3.1. / Indoor Equipment
Vol.2-Part I- 12.3.2. / Outdoor Equipment
Vol.2-Part I- 12.4. / Conditions During Failure of Mains Power and Air Conditioning
Vol.2-Part I- 13. / TESTING EQUIPMENT AND TOOLS
Vol.2-Part I- 14. / SAMPLES
Vol.2-Part I- 15. / Software Licenses
Vol.2-Part I- 16. / Extensions And Upgrading
Vol.2-Part I- 17. / DISCONTINUED OR REPLACED EQUIPMENT
Vol.2-Part I- 18. / ABBREVIATIONS AND ACRONYMS
Vol.2-Part II / FUNCTIONAL AND TECHNICAL SPECIFICATION
Vol.2-Part II- 1. / SYSTEM GENERAL DESCRIPTION AND CONFIGURATION
Vol.2-Part II- 1.1. / INTRODUCTION
Vol.2-Part II- 1.2. / SYSTEM GENERAL REQUIREMENT
Vol.2-Part II- 1.3. / SYSTEM CONFIGURATION OVERVIEW
Vol.2-Part II- 1.3.1. / Central Control, Administration and Monitoring Station (CCAMS)
Vol.2-Part II- 1.3.2. / Backup Control, Administration and Monitoring Station (BCAMS)
Vol.2-Part II- 1.3.3. / Local Systems (LSs)
Vol.2-Part II- 1.3.4. / Network System
Vol.2-Part II- 1.3.5. / Building Network System Configuration
Vol.2-Part II- 1.4. / ACCESS TO THE SYSTEM
Vol.2-Part II- 1.4.1. / Dedicated Workstations (Multi-Workstation Operation)
Vol.2-Part II- 1.4.2. / Access from Office Computers.
Vol.2-Part II- 1.4.3. / Site Workstation Operation
Vol.2-Part II- 1.4.4. / Password Access
Vol.2-Part II- 1.5. / CCAMS AND BCAMS EQUIPMENT
Vol.2-Part II- 2. / SOFTWARE REQUIREMENTS
Vol.2-Part II- 2.1. / INTRODUCTION
Vol.2-Part II- 2.2. / SOFTWARE Functions & Facilities
Vol.2-Part II- 2.2.1. / Basic Characteristics
Vol.2-Part II- 2.2.2. / Minimum Requirements
Vol.2-Part II- 2.2.3. / Software for Fire Extinguishing System Calculations
Vol.2-Part II- 2.2.4. / Graphical Interface
Vol.2-Part II- 2.3. / STORAGE DEVICES
Vol.2-Part II- 2.3.1. / Storage Media
Vol.2-Part II- 2.3.2. / Main Memory
Vol.2-Part II- 2.4. / OPERATING SYSTEM
Vol.2-Part II- 2.5. / LANGUAGE and font SUPPORT
Vol.2-Part II- 3. / SYSTEM FUNCTIONAL OPERATION
Vol.2-Part II- 3.1. / INTRODUCTION
Vol.2-Part II- 3.2. / SYSTEM Functions & Facilities
Vol.2-Part II- 3.2.1. / System Administration
Vol.2-Part II- 3.2.2. / Operator Control Functions
Vol.2-Part II- 3.2.3. / Audit Trail
Vol.2-Part II- 3.2.4. / Human Machine Interface (HMI)
Vol.2-Part II- 3.2.5. / Backup and Restoration
Vol.2-Part II- 3.2.6. / System Fault Detection and Diagnostic Utility
Vol.2-Part II- 3.2.7. / Automated System Control
Vol.2-Part II- 3.3. / SYSTEM management and reporting
Vol.2-Part II- 3.3.1. / Graphical Programming Tool
Vol.2-Part II- 3.3.2. / Real Time Event Reporting
Vol.2-Part II- 3.3.3. / Loss of Communication Operation
Vol.2-Part II- 3.3.4. / Dialup Event Reporting
Vol.2-Part II- 3.3.5. / Event Grouping
Vol.2-Part II- 3.3.6. / Event Routing
Vol.2-Part II- 3.3.7. / Event Display
Vol.2-Part II- 3.3.8. / Alarms Management
Vol.2-Part II- 3.3.9. / History Manager
Vol.2-Part II- 3.4. / CCAMS functional concept - Response to Alarm/Fault
Vol.2-Part II- 4. / GENERAL HARDWARE REQUIREMENTS
Vol.2-Part II- 4.1. / GENERAL
Vol.2-Part II- 4.2. / CERTIFICATION AND ORIGIN OF MATERIALS
Vol.2-Part II- 4.3. / STANDARDS
Vol.2-Part II- 5. / FIRE ALARM SYSTEM
Vol.2-Part II- 5.1. / SCOPE
Vol.2-Part II- 5.2. / FIRE ALARM SYSTEM DESCRIPTION AND CAPABILITIES
Vol.2-Part II- 5.2.1. / General
Vol.2-Part II- 5.2.2. / Basic Performance
Vol.2-Part II- 5.2.3. / Programming
Vol.2-Part II- 5.2.4. / Field Programming
Vol.2-Part II- 5.2.5. / Devices Monitoring
Vol.2-Part II- 5.2.6. / Fault Warning
Vol.2-Part II- 5.2.7. / Fire Alarm System Response to Alarm Condition
Vol.2-Part II- 5.2.8. / Alarm Notification
Vol.2-Part II- 5.2.9. / Transmission to Remote Central Station
Vol.2-Part II- 5.2.10. / Non-Interfering
Vol.2-Part II- 5.2.11. / Priority of Signals
Vol.2-Part II- 5.2.12. / Evacuate
Vol.2-Part II- 5.2.13. / Silencing
Vol.2-Part II- 5.2.14. / Resetting
Vol.2-Part II- 5.3. / FIRE ALARM SYSTEM SPECIFIC OPERATIONS
Vol.2-Part II- 5.3.1. / Smoke Sensor Sensitivity Adjust
Vol.2-Part II- 5.3.2. / Alarm Delays
Vol.2-Part II- 5.3.3. / Disabling/Enabling
Vol.2-Part II- 5.3.4. / System Testing
Vol.2-Part II- 5.3.5. / Log/Display Reports
Vol.2-Part II- 5.3.6. / System History Recording and Reporting
Vol.2-Part II- 5.3.7. / Drift Compensation
Vol.2-Part II- 5.4. / Fire Alarm Control Panel (FACP)
Vol.2-Part II- 5.4.1. / General
Vol.2-Part II- 5.4.2. / Components and Circuit Design
Vol.2-Part II- 5.4.3. / FACP Capacity and Other Capabilities
Vol.2-Part II- 5.4.4. / Loop Interface Boards
Vol.2-Part II- 5.4.5. / FACP Power Supply Unit
Vol.2-Part II- 5.4.6. / Battery Set
Vol.2-Part II- 5.4.7. / Enclosures
Vol.2-Part II- 5.4.8. / Display
Vol.2-Part II- 5.4.9. / Keypad
Vol.2-Part II- 5.4.10. / Integral Printer
Vol.2-Part II- 5.4.11. / Operator Control Switches
Vol.2-Part II- 5.4.12. / Fire Alarm Control Panel (FACP) Internal Sounder
Vol.2-Part II- 5.5. / Repeater Panel
Vol.2-Part II- 5.6. / ANALOGUE ADDRESSABLE DEVICES
Vol.2-Part II- 5.6.1. / Common Requirements for Analogue Addressable Sensing Devices
Vol.2-Part II- 5.6.2. / Analogue Addressable Photoelectric Smoke Sensors
Vol.2-Part II- 5.6.3. / Analogue Addressable Heat Sensors
Vol.2-Part II- 5.6.4. / Addressable Manual Call Points
Vol.2-Part II- 5.6.5. / Addressable Monitor Module (Input Module)
Vol.2-Part II- 5.6.6. / Addressable Control Module (Output Module)
Vol.2-Part II- 5.6.7. / Addressable Fire Alarm Siren
Vol.2-Part II- 5.6.8. / Addressable Strobe Lights (Visual Alarm)
Vol.2-Part II- 5.6.9. / Remote Monitored Power Supply Unit
Vol.2-Part II- 5.7. / FIRE ALARM SYSTEM – OTHER AUXILIARY DEVICES
Vol.2-Part II- 5.7.1. / Isolator Module
Vol.2-Part II- 5.7.2. / Remote Indicator Module
Vol.2-Part II- 5.7.3. / Fire Alarm Bells
Vol.2-Part II- 5.7.4. / Beam Smoke Detectors
Vol.2-Part II- 5.7.5. / Fire Door Release Mechanism
Vol.2-Part II- 5.7.6. / Autodialing Unit
Vol.2-Part II- 5.8. / FIRE ALARM SYSTEM – additional capabilities
Vol.2-Part II- 6. / FIRE EXTINGUISHING SYSTEM
Vol.2-Part II- 6.1. / SCOPE
Vol.2-Part II- 6.2. / GENERAL SYSTEM REQUIREMENTS
Vol.2-Part II- 6.3. / SYSTEM SEQUENCE OF OPERATIONS
Vol.2-Part II- 6.3.1. / First Stage Alarm
Vol.2-Part II- 6.3.2. / Second Stage Alarm
Vol.2-Part II- 6.3.3. / Third Stage: Discharge
Vol.2-Part II- 6.4. / SYSTEM CAPABILITIES AND SPECIFIC OPERATIONS
Vol.2-Part II- 6.4.1. / FECP Capacity
Vol.2-Part II- 6.4.2. / Fault Monitoring
Vol.2-Part II- 6.4.3. / Fault Warning
Vol.2-Part II- 6.4.4. / Annunciating Alarm Circuits
Vol.2-Part II- 6.4.5. / Extinguishing Release Circuits
Vol.2-Part II- 6.4.6. / Alarm and Fault Warning Outputs
Vol.2-Part II- 6.4.7. / Selectable Operation Mode
Vol.2-Part II- 6.4.8. / Disabling
Vol.2-Part II- 6.4.9. / Discharge Cancellation
Vol.2-Part II- 6.4.10. / Silencing
Vol.2-Part II- 6.4.11. / Manual Starting of Sounders
Vol.2-Part II- 6.4.12. / System Reset from an Alarm Condition
Vol.2-Part II- 6.4.13. / Indicators Test
Vol.2-Part II- 6.5. / FIRE EXTINGUISHING CONTROL PANEL (FECP)
Vol.2-Part II- 6.5.1. / General
Vol.2-Part II- 6.5.2. / FECP Power Supply Unit
Vol.2-Part II- 6.5.3. / Battery Set
Vol.2-Part II- 6.5.4. / Enclosure
Vol.2-Part II- 6.5.5. / Visual Indicators on FECP
Vol.2-Part II- 6.5.6. / FECP Internal Sounder
Vol.2-Part II- 6.5.7. / Selector Switch
Vol.2-Part II- 6.5.8. / Extinguishant Release Control
Vol.2-Part II- 6.5.9. / FECP Operator Control Switches
Vol.2-Part II- 6.6. / FES (Fire Extinguishing System) DEVICES
Vol.2-Part II- 6.6.1. / FES (Fire Extinguishing System) Detectors
Vol.2-Part II- 6.6.2. / FES Manual Call Points
Vol.2-Part II- 6.6.3. / End of Line Resistors
Vol.2-Part II- 6.6.4. / FES Sirens
Vol.2-Part II- 6.6.5. / FES Bells
Vol.2-Part II- 6.6.6. / FES Strobe Lights
Vol.2-Part II- 6.6.7. / Entrance Warning Signs
Vol.2-Part II- 6.7. / MECHANICAL EQUIPMENT
Vol.2-Part II- 6.7.1. / Cylinders (Containers)
Vol.2-Part II- 6.7.2. / Discharge Valve
Vol.2-Part II- 6.7.3. / Pipe System
Vol.2-Part II- 6.7.4. / Nozzles
Vol.2-Part II- 6.7.5. / Pressure Relief Unit
Vol.2-Part II- 6.7.6. / Fire Dampers
Vol.2-Part II- 6.8. / Identification, Commissioning and acceptance
Vol.2-Part II- 6.9. / Refilling of FES cylinders
Vol.2-Part II- 7. / FIRE SUPPRESSANT AGENT
Vol.2-Part II- 7.1. / Suppressant Agent Type
Vol.2-Part II- 7.2. / Safety Precautions
Vol.2-Part II- 7.3. / Design Requirements
Vol.2-Part II- 7.4. / Quantities Required - Data Calculations
Vol.2-Part II- 7.5. / SPACE OCCUPANCY OF THE OFFERED EQUIPMENT
Vol.2-Part II- 7.6. / ENVIRONMENTAL IMPACT
Vol.2-Part III / IMPLEMENTATION SERVICES
Vol.2-Part III- 1. / SCOPE
Vol.2-Part III- 2. / GENERAL REQUIREMENTS
Vol.2-Part III- 2.1. / Note
Vol.2-Part III- 2.2. / GENERAL CONDITIONS
Vol.2-Part III- 2.3. / CONTRACT AND SITE ADMINISTRATION
Vol.2-Part III- 2.3.1. / Site Meeting and Reports
Vol.2-Part III- 2.3.2. / Supervision
Vol.2-Part III- 2.3.3. / Conduct on Site
Vol.2-Part III- 2.3.4. / Areas of Operations
Vol.2-Part III- 2.3.5. / CoOperation With Other Contractors
Vol.2-Part III- 2.3.6. / Responsibility for Contractors
Vol.2-Part III- 2.3.7. / Notice Boards
Vol.2-Part III- 2.3.8. / Workshop and Store
Vol.2-Part III- 2.3.9. / Cleanliness of Site
Vol.2-Part III- 2.4. / TECHNICAL ADMINISTRATION
Vol.2-Part III- 2.4.1. / Technical Administration
Vol.2-Part III- 2.4.2. / Check Sizes of Plant
Vol.2-Part III- 2.4.3. / Dimensions on Site
Vol.2-Part III- 2.4.4. / Setting out Works
Vol.2-Part III- 2.4.5. / Marking Cutting Away/Making Good
Vol.2-Part III- 2.4.6. / Temporary Electrically Supply Works
Vol.2-Part III- 2.4.7. / Protective Works
Vol.2-Part III- 2.4.8. / Damage to Equipment etc
Vol.2-Part III- 2.4.9. / Leave Work Perfect
Vol.2-Part III- 2.4.10. / Regulations, Compliance with Regulations
Vol.2-Part III- 2.4.11. / Notices and Fees
Vol.2-Part III- 2.4.12. / Safety Precautions
Vol.2-Part III- 2.4.13. / Labour and Materials etc.
Vol.2-Part III- 2.4.14. / Handling Materials
Vol.2-Part III- 2.4.15. / Acquaintances
Vol.2-Part III- 2.5. / DRAWINGS
Vol.2-Part III- 2.5.1. / Installation/Working Drawings
Vol.2-Part III- 2.5.2. / Drawings Approvals
Vol.2-Part III- 2.5.3. / “As Fitted’’ Drawings
Vol.2-Part III- 2.6. / HEALTH and SAFETY
Vol.2-Part III- 3. / PHASE I
Vol.2-Part III- 3.1. / Extent Of Work
Vol.2-Part III- 3.2. / Background and Nationality of Contractor’s Personnel
Vol.2-Part III- 3.3. / Detailed Design Study
Vol.2-Part III- 3.4. / Supply
Vol.2-Part III- 3.5. / Installation
Vol.2-Part III- 3.5.1. / General
Vol.2-Part III- 3.5.2. / Restrictions
Vol.2-Part III- 3.5.3. / Equipment Installation
Vol.2-Part III- 3.5.4. / Electrical Installation
Vol.2-Part III- 3.5.5. / Conduits & Trunking
Vol.2-Part III- 3.5.6. / Marking
Vol.2-Part III- 3.5.7. / Cabling
Vol.2-Part III- 3.5.8. / Fire Extinguishing System Pipework Installation
Vol.2-Part III- 3.5.9. / Building Diagram and Operating Instructions
Vol.2-Part III- 3.5.10. / Testing and Commissioning
Vol.2-Part III- 3.6. / System Customisation
Vol.2-Part III- 3.7. / Acceptance Testing
Vol.2-Part III- 3.7.1. / Factory Acceptance Tests
Vol.2-Part III- 3.7.2. / Provisional Acceptance Tests
Vol.2-Part III- 3.7.3. / Final Acceptance Tests
Vol.2-Part III- 3.8. / TEST PROGRAMMES
Vol.2-Part III- 3.8.1. / Preliminary Programmes
Vol.2-Part III- 3.8.2. / Final Programme
Vol.2-Part III- 3.9. / TEST REPORTS
Vol.2-Part III- 3.10. / HALON REMOVAL AND DISPOSAL
Vol.2-Part III- 4. / PHASE II
Vol.2-Part IV / TECHNICAL SUPPORT SERVICES
Vol.2-Part IV- 1. / DOCUMENTATION
Vol.2-Part IV- 1.1. / GENERAL REQUIREMENTS
Vol.2-Part IV- 1.1.1. / Number of Copies
Vol.2-Part IV- 1.1.2. / Language
Vol.2-Part IV- 1.1.3. / Units of Measure
Vol.2-Part IV- 1.1.4. / Terminology and Symbols
Vol.2-Part IV- 1.1.5. / Reproducible Documents
Vol.2-Part IV- 1.2. / TECHNICAL HANDBOOKS
Vol.2-Part IV- 1.2.1. / Station Technical Handbooks
Vol.2-Part IV- 1.2.2. / Product Handbooks
Vol.2-Part IV- 1.2.3. / Catalogue of Technical Handbooks
Vol.2-Part IV- 2. / SPARE PARTS
Vol.2-Part IV- 2.1. / GENERAL
Vol.2-Part IV- 2.2. / SPARES INCLUDED IN THE CONTRACT
Vol.2-Part IV- 2.3. / SPARE PARTS CONSUMED BEFORE PROVISIONAL ACCEPTANCE
Vol.2-Part IV- 2.4. / SPARE PARTS CONSUMED DURING THE PERIOD OF GUARANTEE
Vol.2-Part IV- 2.5. / FUTURE AVAILABILITY OF SPARE PARTS
Vol.2-Part IV- 3. / MANPOWER TRAINING
Vol.2-Part IV- 3.1. / GENERAL
Vol.2-Part IV- 3.2. / TRAINING COURSES
Vol.2-Part IV- 3.2.1. / Fire Risk Assessment Course
Vol.2-Part IV- 3.2.2. / Operation and Maintenance Course
Vol.2-Part IV- 3.2.3. / Fire Alarm System Design, Installation, Testing and Commissioning Course
Vol.2-Part IV- 3.2.4. / Fire Extinguishing System Design, Installation, Testing and Commissioning Course
Vol.2-Part IV- 3.3. / ALTERNATIVE PROPOSALS
Vol.2-Part IV- 3.3.1. / Information Requested from the Tenderer
Vol.2-Part IV- 4. / GUARANTEE
Vol.2-Part IV- 4.1. / PHASE I
Vol.2-Part IV- 4.2. / PHASE II
Vol.2-Part IV- 5. / SYSTEM MAINTENANCE
Vol.2-Part IV- 5.1. / Preventive Maintenance
Vol.2-Part IV- 5.2. / Corrective Maintenance
Vol.2-Part IV- 5.3. / Maintenance/Installation Team
Vol.2-Part IV- 5.4. / Spare Parts Stocks
Vol.2-Part IV- 6. / SWAP/REPAIR
Vol.2-Part IV- 6.1. / Introduction
Vol.2-Part IV- 6.2. / DEFINITION
Vol.2-Part IV- 6.3. / Handling Procedure
Vol.2-Part IV- 6.3.1. / Request for Swap/Repair
Vol.2-Part IV- 6.3.2. / Shipping Routines
Vol.2-Part IV- 6.3.3. / Delivery Time
Vol.2-Part IV- 6.3.4. / Emergency Swap
Vol.2-Part IV- 6.4. / Charges
Vol.2-Part IV- 6.5. / Terms of Delivery
Vol.2-Part IV- 6.6. / Warranty
Vol.2-Part IV- 6.7. / Terms of Payment
Vol.2-Part IV- 7. / SYSTEM SUPPORT
Vol.2-Part IV- 7.1. / Introduction
Vol.2-Part IV- 7.2. / Operation and Maintenance Support
Vol.2-Part IV- 7.3. / Emergency Support
Vol.2-Part IV- 7.4. / Information Service
Vol.2-Part IV- 7.5. / Operating System and Application Programs Upgrade and Corrections
Vol.2-Part IV- 7.6. / Routine fault reports
Vol.2-Part IV- 7.7. / Other Services
Vol.2-Part IV- 7.8. / Introduction of New Services, Facilities and Equipment
Vol.2-Part V / LIST OF BUILDINGS
Vol.2-Part VI / STATEMENT OF COMPLIANCE
AT.10/2009Vol.2, Part VI: Statements of CompliancePage 1