TOTAL FINA ELFTSP - PRODUCTION

TOTAL SOUTH PARS / TSP-P-PR-HSE-SAF- 139 SIMULTANEOUS OPERATIONS
TSP / PR–HSE–SAF–139 / Rev 0 / 04/08/01
SIMULTANEOUS OPERATIONS

Authorisation Record

ORIGINATOR / TECHNICAL AUTHORITY / ISSUING AUTHORITY
Signature / Signature / Signature
POSITION / head of hse / POSITION / TSP HSE MANAGER / POSITION / SITE REPRESENTATIVE
NAME / R. LEPOITEVIN
A. DESPREZ / NAME / b. cOTE / NAME / J. GALVES/A. MARCHAL
DATE / 04 AOUT 2001 / DATE / 04 AOUT 2001 / DATE / 04 AOUT 2001

TABLE OF CONTENTS

1PURPOSE OF THE SIMOPS......

1.1Main purpose......

1.2Detailed objectives......

1.3SUPPORT AND CONTRIBUTING ELEMENTS......

1.4REFERENCES......

TSP HSE MANUAL......

2DOCUMENT CONTROL......

2.1ISSUE......

2.2DISTRIBUTION......

2.3REVIEW AND UPDATE......

3OPERATIONS FORECAST & PLANNING......

3.1OPERATIONS PLANNING......

3.1.1Step 1 : First turbo-generator running on diesel (HDEC Milestone A)......

3.1.2Step 2. Take over by Production of Sea Water Intake and Plant Sea Water distribution.

-Activities under Production responsibility......

3.1.3Step 3 : Ready to receive fuel gas from Kangan and run generator/boiler on fuel gas . (HDEC Milestone D)

3.1.4Step 4 : 4 wells to be completed and ready for hook up on SPD3......

3.1.5Step 5 : Operation on behalf of HDEC by ODC. (Milestone E)......

3.1.6Step 6 : Final take over by Prod of SPD3 platform ready for gas production with 4 wells, Start sea line de watering

3.1.7Step 7. Take over by Production of partial onshore plant area: (HDEC Milestone F)

3.1.8Step 8 : End of sea line de watering, gas-in of receiving facilities......

3.1.9Step 9(a) : Take over by prod of Train 1 area (HDEC Milestone Process train 1)

3.1.10Step 10 : Start to export gas......

3.1.11Step 11 : Reach first production stage......

3.2SIMULTANEOUS OPERATIONS FORECAST......

4RESPONSIBILITIES......

4.1T.S.P. SITE MANAGER......

4.2SIMULTANEOUS OPERATIONS LEADER......

4.3AREAS OF RESPONSIBILITIES......

CONSTRUCTION AREAS......

UTILITY AREAS......

PRODUCTION AREAS......

4.4INSTALLATION AUTHORITY......

CONSTRUCTION AREAS......

UTILITY AREAS ( OPERATION DURING COMMISSIONING )......

PRODUCTION AREAS......

4.5RESPONSIBILITIES OF THE INSTALLATION AUTHORITY......

5SUPERVISION......

6OPERATIONS MANAGEMENT AND ORGANISATION......

6.1OPERATIONS PLANNING......

6.2OPERATION PREPARATION......

6.3ORGANISATION FOR SIMOPS......

6.4MEETINGS......

6.5WORK PERMITS......

6.5.1SHARED AREAS......

6.5.2HAZARD IDENTICATION and IMPACTED ZONES......

6.6OPERATION CONTROL......

6.7PLANT AND EQUIPMENT......

7PERSONNEL CONTROL......

7.1AREAS WITH PERSONNEL ACCESS RESTRICTIONS......

7.2ALARMS AND COMMUNICATION......

7.3MUSTERS......

8AUTHORIZED SIMULTANEOUS OPERATIONS......

9SHARED FACILITIES......

9.1FIRE BRIGADE......

9.2CLINIC AND AMBULANCE......

9.3SEARCH AND RESCUE TEAM......

9.4SECURITY TEAM......

1PURPOSE OF THE SIMOPS

1.1Main purpose

The main purpose of the Simultaneous Operation Safety Rules and Procedures is to provide all personnel involved with simultaneous operations on TOTAL /South Pars phase 2 and 3 with a knowledge of the relevant safe practices and procedures.

Additionally, this Section is used to predetermine the compatibility, interference and limitations during the planning and operational stages of Simultaneous operations.

It takes into account the specific design of the South Pars Phases 2 & 3 Installations and the TSP Organization.

The present version addresses the specific situation of phased hand over to Production up to first gas export

The activities concerned by this document are:

-Construction activities (Lifting, Cold work /Hot works, etc.)

-Commissioning Activities.

-Operation of the utility system by ODC ( Operation during Commissioning ) Team conducted in geographical areas under construction authority and prior to hand over to Production.

-Production activities after partial hand over to production.

It is possible to forecast the equipment lay out , the number of personnel

Involved and the safety status of a given area for determining Construction or

Commissioning operations during routine production.

This will optimize safety clearance , prevent obstructions / interference and

minimize constraints. This is one of the objectives of the SIMOPS

procedures.

This document has addressed as many situations as possible. However,

should the need arise, specific operations will have to be reviewed on a

case by case basis.

1.2Detailed objectives

This Section called “ Simultaneous Operation Safety Rules and Procedures “ are referred to, in short, as SIMOPS.

The objectives of the SIMOPS are to:

-Highlight potential restrictions when forecasting and planning additional activities due to take place at the same time and location where long-term activities are performed.(for the purpose of this document, SIMOPS starts with the start-up of the first utilities i.e. electricity supply.)

-Ensure any activity or operation affecting an area, where another activity may be on going simultaneously, is reviewed and analyzed for potential interference or limitation.

-Establish a mechanism for review of proposed activities (e.g. meeting and identifying department participation).

-Establish matrix to authorize simultaneous activities.

-Ensure simultaneous activities are controlled and performed in a safe manner by :

  • Defining responsibilities of personnel involved
  • Requiring the appointment of a SOL (Simultaneous Operation Leader) to coordinate activities within different organizations.
  • Stating preventive measures to be implemented prior to starting simultaneous activities
  • Limiting the number of simultaneous activities and / or the area affected
  • Avoiding interference during operations
  • Providing communication channels and procedures.
  • Training of all personnel including communication of step

changes.

-Minimize the potential for personnel injury and equipment damage by

  • Controlling and restricting personnel access to areas of simultaneous activities
  • Providing specific instruction for securing operations and mustering personnel in case of emergency
  • Ensuring all personnel involved are aware of the specifics of simultaneous operations and of the procedures.
  • Identifying hazards and evaluating the consequences of failures, to update matrix of allowed simultaneous activities.

1.3SUPPORT AND CONTRIBUTING ELEMENTS

- Construction forecast and planning

- Commissioning activities forecast and planning

- Operation of utility system by ODC forecast and planning

- Production activities forecast and planning

- Review and analysis of potential simultaneous activities up to the end of construction / commissioning activities (after train 4 hand over)

- Risk evaluation procedures

- Permit to work system

- Plant Design and engineering studies

1.4REFERENCES

TSP HSE MANUAL.

Standard 601 , Work Permit System

Standard 300 series, risk evaluation

Site Emergency Procedures Manual

-Site / Head Office ( existing )

-Site / Tehran relative to construction period ( existing )

-New Site Scenarios

2DOCUMENT CONTROL

2.1ISSUE

This document is issued by the site HSE Authority under the control of the Site Manager in charge at the time of issue or update.

2.2DISTRIBUTION

This section is distributed as per list. These identified copies are controlled as per the general site control system.

Whether the Site Manager. / The Operation Assistant or the Safety Authority feels an extended distribution is necessary, it is their responsibility to dispatch the relevant document.

Minimum distribution List

-Construction Manager

-Commissionning Manager

-Operation Assistant

-HSE Manager

-Simultaneous Operations Leader

-Head of Construction

-Head of Production

-Head of Safety and FIFI

-Commissioning Site Leader

-HDEC Site Representative

-HDEC Commissioning Manager

2.3REVIEW AND UPDATE

The Simultaneous Operations Safety Rules and Procedures will be reviewed and amended as necessary under the responsibility of the Site Manager, then the document will be updated through revisions.

3OPERATIONS FORECAST & PLANNING

3.1OPERATIONS PLANNING

Two groups, Project (construction , commissioning & odc) and Production, will be performing operations on South Pars Phases 2 & 3 over the period 2001 – 2002

-Construction and Commissioning activities are planned until end of 2002

-Production is due to start in Dec 2001

Definition of start-up sequence:

3.1.1Step 1 : First turbo-generator running on diesel (HDEC Milestone A)

-Due date : 25-5-2001

-Area under SIMOPS procedure: Turbo-generator area and SS1

-Activities under Project responsibility

3.1.2Step 2. Take over by Production of Sea Water Intake and PlantSea Water distribution.

-Due date : 30-07-2001

-Area under SIMOPS procedure: SWI area

-Activities under Production responsibility

3.1.3Step 3 : Ready to receive fuel gas from Kangan and run generator/boiler on fuel gas . (HDEC Milestone D)

-Due date : 1-9-2001

-Area under SIMOPS procedure: All gas pressurized lines and systems, corresponding generators, boilers and electrical substations

-Activities under Project responsibility

3.1.4Step 4 : 4 wells to be completed and ready for hook up on SPD3

-Due date : 30-9-2001

-Area under SIMOPS procedure: SPD3.

Note : for information only.

3.1.5Step 5 : Operation on behalf of HDEC by ODC. (Milestone E)

-Due date:01-10-01

-Area under SIMOPS Procedure: MEG, tanks and distribution, part of utilities, propane tank, Reception facilities (pressurized water)

-Activities under Project responsibility

3.1.6Step 6 : Final take over by Prod of SPD3 platform ready for gas production with 4 wells, Start sea line de watering

-Due date : 7-11-2001

-Area under SIMOPS procedure: SPD3.

Note : for information only.

3.1.7Step 7. Take over by Production of partial onshore plant area: (HDEC Milestone F)

-Due date : 15-11-2001

-Area under SIMOPS procedure: MEG , reception facilities, part of utilities, condensate stabilization, condensate storage, export facilities, phase two flare , ESD ,F&G, DCS, Power distribution and systems which interface with equipment handed over to Production.

-Activities under Production responsibility

3.1.8Step 8 : End of sea line de watering, gas-in of receiving facilities

-Due date : 28-11-2001

-Area under SIMOPS procedure: as 3.1.7 and around sour water treatment and disposal.

-Activities under Production responsibility

3.1.9Step 9(a) : Take over by prod of Train 1 area (HDEC Milestone Process train 1)

-Due date : 20-12-2001

-Area under SIMOPS procedure: as 3.1.7, Train 1 and substation 2 excluding Sulphur Recovery Unit.

-Activities under Production responsibility

Step 9(b) : Take over by prod of Train 1 area.

-Due date :

-Area under SIMOPS procedure : as step 9(a) and Sulphur

Recovery Unit.

-Activities under Production responsibility

3.1.10Step 10 : Start to export gas

-Due date : 15-1-2002

-Area under SIMOPS procedure: No change

-Activities under Production responsibility

3.1.11Step 11 : Reach first production stage

-Due date : 1-3-2002

-Area under SIMOPS procedure: No change

-Activities under Production responsibility

Note: Next steps will be defined at later stage

3.2SIMULTANEOUS OPERATIONS FORECAST

Construction , Commissioning, Utility systems running and Production Operations with potential interference between them should be forecasted to minimize any interference.

Information relevant to simultaneous activities with a possible / potential impact to the other team should be given for every planned operation as well as for contingency and emergency situation.

Simultaneous operations which are not authorized within this procedure, or simultaneous operations for which special precautions may be required shall be subject to a ”what if” or risk evaluation.

Urgent decisions regarding SIMOPS are the responsibility of the Site Manager

4RESPONSIBILITIES

4.1T.S.P. SITE MANAGER

The Site Manager is responsible for the Safety, Health and Welfare of all personnel working on the site. All supervisors working on the project assist the Site Manager.

The TSP Site Manager’s responsibility for safety and coordination will be handed over to the Production Assistant at train one hand over (step 9).

Up to step 4 The Site Manager takes responsibility as Simultaneous Operations Leader.

4.2SIMULTANEOUS OPERATIONS LEADER

The Simultaneous Operations Leader (S.O.L) is responsible for proper coordination and safe simultaneous interfaces as well as identification and resolution of possible impact on other operations. He receives delegation for these responsibilities from the Site Manager.

He liaises with all supervisors (Production, Construction, Commissioning, Maintenance, Safety, etc) and area /installation authorities.

He ensures that the operational team duly enforce SIMOPS procedures. However both Construction and Production teams remain responsible for the safe management of their own operations.

.

The S.O.L. acts under guidance and control of the TSP Site Manager additionally he will report and liaise with Project and Production as required.

It is the responsibility of the SOL to follow up the completion of listed activities and to report to the Site Manager any trend or omission which could potentially jeopardize the planning forecast.

In the event of a disagreement regarding the safety of a proposed simultaneous operation or the continuation of an activity in progress, the matter should be decided by the SOL and referred to the Site Manager for approval ( if deemed necessary )

4.3AREAS OF RESPONSIBILITIES

Four types of operational zones are defined on South Pars Phase 2 and 3 installations.

CONSTRUCTION AREAS

Under the responsibility of the Site Manager

COMMISSIONING AREAS

Under the responsibility of the Site Manager

UTILITY AREAS

Operated by ODC ( Operation during Commissioning ) under the responsibility of the Site Manager

PRODUCTION AREAS

Under the responsibility of the Operations Assistant

4.4INSTALLATION AUTHORITY

One nominated person is in charge of each operational zone:

CONSTRUCTION AREAS

The HDEC Area Authority is the Installation Authority

COMMISSIONING AREAS

The Commissioning Manager is the Installation Authority

UTILITY AREAS ( OPERATION DURING COMMISSIONING )

Prior to hand over ‘The Operation during Commissioning’ team operate and maintain utilities.

The Commissioning Manager is the Installation Authority.

However during phases where production operations are in hand, clear definition of interfaces should be set up and responsibilities shared for any activity having a potential impact on production, i.e. PCS, ESD, F&G, power sources and distribution, etc.

PRODUCTION AREAS

The Process and Utility Superintendents are the Installation Authorities on the areas handed over to Production.

4.5RESPONSIBILITIES OF THE INSTALLATION AUTHORITY

In addition to the duties defined by the Permit to Work system (TSP PTW) the nominated Installation Authority is responsible for

Ensuring planned operations have:

  • Been properly evaluated as to their implications and potential consequences
  • Been forecasted correctly in terms of time and duration.

Ensuring Area Operators are fully aware of the SIMOPS as well as the implication and consequences of each of their operations in regard to the proximity of other teams personnel and equipment.

Ensuring operations are performed within forecast. In case of delays, the area Authority should evaluate consequences of the delay then notify the Site Rep., SOL, and other interested parties as required.

Ensuring that only essential personnel are authorized to enter areas affected by SIMOPS operations.

Ensuring that involved personnel are aware of alarms and evacuation procedures.

5SUPERVISION

Safety of SIMOPS operations is dependent to a great degree on the general communication, coordination and cooperation between the Supervisors and Authorities involved.

Accurate evaluation and control of the operational parameters are of prime importance for SIMOPS operations, safety and efficiency.

For this purpose commissioning will maintain two sets of permanently up-dated and marked-up copies of electrical online diagrams identifying energized circuits and P IDs identifying pressurized equipment ,location of isolations (spades, spools, valves, etc…) One copy for their own use theother copy for the SOL.

In this respect, and in addition to the usual job preparation, supervisors should:

  • Ascertain their operation has been duly planned and that the Site Manager. / SOL, Area Authority and other involved supervisors have been informed of the timing and about any potential constraint and interference.
  • Confirm evaluation of starting time and duration.
  • Confirm evaluation of potential constraints and interference.
  • Check that operation and emergency procedures comply with SIMOPS context and to the current running / planned activities.
  • Ensure both, equipment and personnel, are available and comply with SIMOPS.

During the operation, direct control should be maintained by:

  • Continuous supervision and monitoring
  • Clear instruction, constantly updated according to progress and events.
  • Enhanced checking and testing.
  • Good communication and detailed instructions eg Tool Box Talks

6OPERATIONS MANAGEMENT AND ORGANISATION

Planning highlights concurrent activities performed by different sections. A general agreement on work organization and schedule is reached to minimize disruption and promote communication between all parties.

6.1OPERATIONS PLANNING

Construction , Commissioning and Production Departments issue planning forecasts which are reviewed by respective management to identify Simultaneous Operations.

When SIMOPS are identified Managers will advise all affected parties and when required Construction / Commissioning planning will be updated to incorporate SIMOPS .

Acceptance of planned operations , additional requirements and constraints will be approved by management and supervision.

The operation program should give all relevant information relating to simultaneous operations including constraints, limitations, areas of conflict and include or refer to applicable emergency procedures.

The SOL will inform all parties involved, obtain acceptance for the operation plan and any identified constraints. When conflicting operations are identified he will liaise with Project and /or Production who will decide which takes priority.

6.2OPERATION PREPARATION

Prior to commencing SIMOPS the Site Manager / SOL will meet with all involved parties to verify all aspects of the operation , confirm emergency procedures, identify constraints, limitations and conflicting activities.

Once the planning of the operation is confirmed and the detailed program and/or procedures approved, equipment and personnel are mobilized.

6.3ORGANISATION FOR SIMOPS

Project Phaseup to Step 3

Acting as:
Site Manager / Construction
TSP Construction Manager / Commissioning
TSP Construction Manager
SOL / Not required / Not required
Installation Authorities / HDEC
Area Authorities / Commissioning Manager
Safety Authority / HSE
Area Authorities / HSE
Area Authorities

Project and Production Phases

(Starting step 5 and up to train 1 hand over)*

Acting as :
Site Manager / Up to step 8
TSP Construction
Manager / Starting step 9
Operations
Assistant
SOL / Required / Required
Installation Authorities / Construction
HDEC Area Authorities
Commissioning / ODC
Commissioning Manager
Production
Process / Utility Superintendents / Construction
HDEC Area Authorities
Commissioning / ODC
Commissioning Manager
Production
Process / Utility Superintendents
Safety Authority / Project
HSE
Area Authorities
Production
Head of FF & HSE / Project
HSE
Area Authorities
Production
Head of FF & HSE

*After train 1 hand over to be defined later

6.4MEETINGS

Meetings are required to :

  • Keep the highest standards of Safety awareness for all personnel.
  • Ensure proper Communication, Cooperation and Coordination between the different teams working on the installations .
  • Ensure proper planning and progress of simultaneous activities to minimize unproductive downtimes.
  • Ensure strict application of the Safety Rules & Procedures and of the risk evaluation and work Permit System.

Meetings will be held :

Prior to start-up of simultaneous activities :

All supervisors and Authorities to be convened to a kick-off meeting by the Site Manager, SOL, to ensure that all precautions have been implemented and equipment is available .