D&C MMH:ack
SECTION 013510
ENERGY EFFICIENCY PROGRAMS
PART 1 GENERAL
1.01DESCRIPTION
A.This project was designed to comply with the New York State Energy Code.
B.This project was designed to qualify for incentives under New York State Utility Companies Energy Rebate Programs.
C.Provide project components listed in paragraph 1.03 A. in accordance with requirements of the Energy Rebate Program.
1.All motor efficiencies shall meet or exceed minimum listed EER or SEER.
2.All lighting fixtures listed i.e. lamps and ballast shall meet or exceed program requirements.
1.02JURISDICTION
FOR A., B., AND C. CHECK WITH ELECTRICAL DESIGN.
A.The New York State Utility Company serving the location area of this project is:
B.Rebate Program:
C.Rebate Program Responsibility:
1.03APPLICABILITY
A.The following project components qualify under the rebate programs:
EDIT OR ADD TO EQUIPMENT AND ASSOCIATED SPECIFICATIONS SECTIONS AS APPROPRIATE. NOTE: GENERALLY THIS APPLIES TO ALL MOTORS ABOVE 1HP, ALL FLUORESCENT FIXTURES AND HIGH INTENSITY DISCHARGE FIXTURES.
EQUIPMENT / SPECIFICATIONS SECTION / CONTRACTReciprocating Water Chiller / 236419 / HVAC
A/C motors / 206221 / HVAC, Plumbing
Adjustable speed variable frequency drives (Primary chilled water and hot water pumps variable air volume fans) / 206221 / HVAC
EQUIPMENT / SPECIFICATIONS SECTION / CONTRACT
High Efficiency Lighting:
a.Fluorescent fixtures, 1 & 2 lamp T8, Hard-wired Compact Fluorescent
b.High Intensity Discharge Lighting CL-18 Metal Halide.
c.High pressure sodium / 265110
265140
265150 / Electrical
Occupancy Sensors / 260925 / Electrical
1.04PROCEDURAL RESPONSIBILITY
A.Notify Utility Company having jurisdiction of this project.
1.Utility Company may require pre-approval for rebate application.
2.It is the Contractor’s responsibility to contact Utility Co. as soon as possible after contract award and determine if pre-approval is required.
3.It is the Contractor’s responsibility to comply with all Utility Co. requirements to insure maximum rebate.
B.Obtain from Utility Company a minimum of 2 copies of the latest edition of their Energy Rebate Program. Deliver one copy to the Director’s Representative.
C.Immediately notify the Director’s Representative of any additional project components that qualify under the Energy Rebate Program.
D.Complete the application form for the Energy Rebate Program and submit to the Utility Company.
1.Also send 2 copies of the application form to the Director’s Representative.
2.Proof of this submission to the Utility Company is required before Contract 50 percent payment will be made.
1.05SUBMITTALS
A.Waiver of Submittals: The “Waiver of Certain Submittal Requirements” in Section 013300 does not apply to project components listed in this Section.
B.In addition to submittals required by a specific Section, submit with the product data sheets the applicable section of the Utility Company’s Energy Rebate Program for that component.
1.06PAYMENT
CHECK A. WITH ELECTRICAL DESIGN, METHOD OF PAYMENT MAY CHANGE PERIODICALLY.
A.The Utility Company Rebate will be paid to the State of New York in manner designated by the Director’s Representative.
PART 2 PRODUCTS (Not Used)
PART 3 INSTALLATION (Not Used)
END OF SECTION
Updated 07/07/2009
Printed 10/15/2018013510 - 1Project No.