AVLO: TIMBER HARVEST ROAD PLANNING/COST ESTIMATION FORM

Landowner____________________________________ General location________________________________ County/State________________________________________Date_______________

Forester_____________________________________________

1. What is the current road situation?

An adequate road exists. Stop

No road exists. Go to part 2.

Road exists, but needs upgrade/repair. Go to 5.

2. Plan for a new road (or section of road). Locate the desired road on topomap and attach map.

Estimated length of road

Traffic (comment on weight, quantity, and configuration)

Width of road

Maximum desired grade of road

Permanent or temporary

Rock type & hardness expected (soil survey)

3. Are perennial stream crossings needed?___________ What is the stream width___________ Traffic wt? _________

How many of the following are needed?

Type Quantity Expected cost range/crossing Estimated cost

Ford $500-1000

Reinforced ford $500-2000

Culvert (steel or plastic) $400-1500

Portable skidder bridges $2000-7000

Stringer bridges $8000-50000

Other options

4. New Construction costs Length /quantity Expected cost range Estimated costs

Easement costs

Location and gradeline installation $500-1000/mile

Clearing and grubbing $4000-7000/mile

Cut & Fill slopes $1500-2500/mile

Ditch construction $1200-2000/mile

Shape final surface grade $1000-2500/mile

Water control

broad based dips $25-50/dip

water turnouts $10-50/turnout

culvert installation & cost $280 installation + pipe

Gravel ((LxWxD in ft)x 100)/ 2000 _________tons tons x $/ton

Seeding banks $300-500/mile

5. Upgrade-Repair-Maintenance needs for use of existing road

Length /quantity Expected cost range Estimated costs

Ditch improvement/repair $300-2000/mile

Grade road $300-2500/mile

Improve water control

broad based dips $25-50/dip

water turnouts $10-50/turnout

culvert installation & cost $280 installation + pipe

Add gravel (( LxWxD in ft)x 100)/ 2000 = _________tons tons x $/ton

Seeding $300-500/mile

6. Closure costs Length/quantity Expected cost range Estimated costs

water bars $15-30/bar

disc & seed $400-800/mile

gates $500-2000

other

7. Other?

TOTAL ESTIMATED COSTS