City of Barstow, CA

State of California Department of Water Resources

2014 Water-Energy Grant Program

Wastewater Treatment Plant Electrical Energy Offset and Water Waste Reduction Project

●Applicant Information/ Organization Name:

City of Barstow

220 E. Mountain View Street

Barstow, CA 92311

(760) 256-3531

●Tax ID: 95-6000675

●Point of Contact: Kody Tompkins

●Point of Contact Position Title: Chief Wastewater Treatment Plant Operator

●Proposal Name: Wastewater Treatment Plant Electrical Energy Offset and Water Waste Reduction Project

●Proposal Objective(s):

Project 1 (see Work Plan,) submitted under the water savings aspect of the 2014 Water-Energy Grant Program, includes replacement of water lines and appurtenances at the Wastewater Treatment Plant (WWTP).

Project 2 (see Work Plan,) submitted under the energy savings portion of the Program, proposes to reduce high electrical energy costs by providing an alternative renewable energy source at the WWTP.

Each project reduces waste of vital resources by lowering/offsetting energy costs, reducing GHGs (Project 2), creating public awareness of renewable energy, and reducing water waste throughout the treatment plant.

Proposal Budget:

Other Contribution: 0

Local Contribution (Cost Share): 0

Federal Contribution: 0

In-kind Contribution: 0

Amount Requested (Grant Funds Requested): $3,046,395.00

Total Proposal Cost: $ 3,046,395.00

●Proposal Geographic Information:

Latitude: 34° 53’ 24” N

Longitude: 116° 59’ 46” W

Longitude/Latitude Clarification: N/A

Location: 2200 Riverside Drive, Barstow, CA 92311

County(ies): San Bernardino County

Groundwater Basins: Lower Mojave River Valley

Hydrologic Region(s): South Lahontan

Watershed(s): 161 9628 Mojave

●Legislative Information:

State Assembly District No. 33

State Senate District No. 183

U.S. Congressional District No. 8

●Disadvantaged Community Proposal: Yes

●Regional Proposal: No

●System Water Savings: See Attachment 2

●System Energy Savings: See Attachment 2

●Grant Total GHG Savings: See Attachment 2

●What is the statutory or other legal authority under which the applicant was formed and is authorized to operate? Municipality

●Does the applicant have legal authority to enter into a grant agreement with the State of California? Yes

PROJECT INFORMATION -- PROJECT #

Project Name: Water Waste Vital Resource Reduction Project

Implementing Organization: City of Barstow

Secondary Implementing Organization: Wastewater Treatment Plant

Proposed Start Date:June 1, 2016

Proposed End Date:October 7, 2016

Project Representative: Charles C. Mitchell, City Manager, or designee

Project Manager: Kody Tompkins, Chief Plant Operator

PROJECT INFORMATION -- PROJECT #

Project Name: Wastewater Treatment Plant Electrical Energy Offset

Implementing Organization: City of Barstow

Secondary Implementing Organization: Wastewater Treatment Plant

Proposed Start Date:June 1 , 2016

Proposed End Date:May 17, 2017

Project Representative: Charles C. Mitchell, City Manager, or designee

Project Manager: Kody Tompkins, Chief Plant Operator

1