CLRC Instrumentation Department Calice Project Management Plan version 0-1
Project Management Plan
Project Name: Calice
Version: 0.1
Approval:
name / signature / dateProject Manager / Rob Halsall / XXXXXXXXX / XXXXXXX
Group Leader / Rob Halsall / XXXXXXXXX / XXXXXXX
Distribution for all updates:
Project Manager: / Rob HalsallGroup Leader responsible for the project: / Rob Halsall
Division Head responsible for the project: / Steve Quinton
Project Managers of related projects: / John Coughlan
Programme Manager: / Steve Quinton
Quality Manager: / Steve Quinton
Management Aspects
1. Related Projects
CMS Tracker FED
2. Stakeholder Plan
See document calice-shp-v0-1.doc
3. Risk Management Plan
See document calice-rmp-v0-1.doc
4. Project Staff and Organization
Name / Institute / RoleRob Halsall / RAL / Project Manager
CMS Liaison
Adam Baird / RAL / Lead Engineer
Ed Freeman / RAL / VME & Back End FPGA consultant
Ivan Church / RAL / Test/Test Firmware
Richard Matson / RAL / Test (JTAG)
Chris Day / RAL / DO
Bob Thompson / RAL / OM
Name / Institute / Role
Paul Dauncey / IC / Customer/sponsor
Software
Osman Zorba / IC / Front End FPGA up to FE-BE Interface
Dave Mercer / MAN / Back End/VME FPGA
Front End FPGA FE-BE Interface
Martin Prostranecky / UCL / Trigger FPGA Firmware
Matt Warrren / UCL / Trigger FPGA Firmware
5. Training
Area / Name / MethodCadence / Adam Baird / On the job
DO assistance
Xilinx Virtex II / Ivan Church / CMS Tracker FED
CMS Tracker FED / Adam Baird
Ivan Church / Rob Halsall assistance
CMS Tracker FED Testing
6. Project Plan
See document calice-plan-v0-1.mpp
7. Costs and Finance
Total budget estimated at £111K hardware & 20 Staff Months effort.
Item / Unit Cost / Quantity / TotalADC Module / £8090 / 11 / £89K
NIM-LVDS Module / £1000 / 1 / £1K
Prototype Cables / £100 / 10 / £1000
Final Cables / £70.5 / 64 / £4.5K
Total / £95.5K
Project Codes are FD31710 CALICE REQUISITIONS and FD31720 CALICE TD STAFF
See document calice-stp-v0-1.xls for estimated Staff To Project profile
See document calice-req-v0-1.xls for estimated requisition costs
8. Project Reviews and Documentation
Review Stage / Date / DocumentationConceptual Design / 11-10-2002 / On Web site
Preliminary Project / 24-10-2003 / Project Spec
Project Management Plan
Microsoft Project Plan
Staff to Project Spreadsheet
Pre-Production
Prototype Module / 24-10-2003 / CDR & PPR Documents
Schematics & Layout
Pre- Production
Final Module / 31-04-2004 / CDR & PPR Documents
Schematics & Layout
Problem Reports
Route Cards
Test Results from Lab
Close Out Review / 31-07-2004 / All available documentation
Test Results from Lab
Test Results from Cosmics
Post Implementation Review / 01-09-2004 / All available documentation
Test Results from DESY
9. Project Monitoring and Control
Weekly Project Monitor Forms
10. Procurement Plan
RAL OM/DO will procure Readout Boards & Cables
11. Software and Equipment
For use at RAL;
Item / Responsibility / NotesSpace in R25 Lab / RAL / Exists
PC with CAE Tools / RAL / Exists
JTAG Test System / RAL / Exists
Parallel Cable IV / RAL / Exists
XDAQ Software / IC/UCL/MAN / CMS DAQ
Test Software / IC/UCL/MAN / Develop
VME 64X Crate / IC/UCL/MAN / Exists
VME-PCI / IC/UCL/MAN / Exists
12. Quality Plan
The project will be run under the Instrumentation Department Quality System.
Conceptual Design Review held by customer prior to PPRP proposal submission.
13. Safety
Standard VME based ADC instrumentation board
Not EMC tested by CCLRC RAL
Make sure system grounding set up correctly
Observe anti static precautions
14. Environmental Impact
Not EMC tested by CCLRC RAL
Customer will responsible for disposal at end of life
Last modified 22/05/03 13:32 page 5 of 7
CLRC Instrumentation Department Calice Project Management Plan version 0-1
Technical Aspects
1. Requirements
See customer documents;
Specification of the readout electronics for the CALICE beam test, Nov 19, 2002
Proposal 317 – CALICE Resubmission, November 12, 2003
2. Specification of Deliverables
Front End Module;
Back End Section;
See CMS Schematics, PC3025M rev A, 13-11-02
See CMS Firmware & System presentation 05-03-2003
3. Manufacturing
Use RAL DO/OM approved PCB manufacturer, Assembly Company and processes.
4. Testing and Product Control
The test plan will be a separate document. Product control will be by standard route card for each module with an overall spreadsheet summary.
See documents calice-tp-v0-0.doc, calice-rc-xx.doc, calice-rcs.xls
5. Shipping and Installation
Customer will install
Shipping destination TBD – chargeable to project cost center
Modules will be packed in individual anti-static bags and padded foam boxes.
6. Maintenance and further orders
This project is part of a technology demonstrator programme and is such is not likely to require long term maintenance.
Review maintenance requirements at the Post Implementation Review
Last modified 22/05/03 13:32 page 5 of 7