Appendix 6(a)
BLACKPOOL COUNCILHousing and Social Services
Inspection of Social Care Services for Older People
Action Plan
Page 1 of 8
Appendix 6(a)
Standard 1: National Priorities and Strategic Objectives
Action / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 20071(a) The Council should ensure continued support to the Senior Voice Forum so that it can contribute to improved services and better outcomes for older people. /
- A Corporate Older Person’s Strategy is established through a series of joint workshops
- The Corporate Strategy, ‘Celebrating Age, Experience and Aspiration’ is in place
- Senior Voice Forum members are actively involved in their 5 priority areas of: Health and Social Care, Transport, Crime and Community Safety, Disability and Access, Social Inclusion/Discrimination and actively influence Council priorities
- Difficulty in securing the full engagement of older people.
- Engaging older people who are not members of the Senior Voice Forum.
- Ability of Senior Voice Forum to become ‘self-funding’ in agreed timescales.
- Senior Voice Forum are represented on:
- Corporate Equalities Forum
- Advice Link Network
- Senior Voice Forum involved in consultation on:
- Corporate Strategic Plan
- Tender for new day services contract
- Senior Voice Forum being consulted by Lancashire Police and Age Concern.
- Workshops underway with Senior Voice Forum to develop the Corporate Older Person’s Strategy (draft 30.6.07)
Time Frame: / 31 March 2007 /
Lead Officer
/ Chair of Corporate Social Inclusion GroupStandard 2: Cost and Efficiency
Action / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 20072 (a) The Council and partners should ensure effective linkages between the Older People’s Partnership Board and other strategic fora and processes. /
- Accountabilities and governance arrangements for the Older Person’s Partnership Board are reviewed and amended to reflect ‘a whole system approach’ to the needs of older people.
- Blackpool Coastal Housing Limited now represented on the Older Person’s Partnership Board
- Representative from Older Person’s Partnership Board attends Sport, Nutrition and Physical Activity Alliance
Time Frame / 31 December 2006 /
Lead Officer
/ Assistant Director, Older Adults and Physical Disability ServicesAction / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement
2 (b) Social Services should monitor the recent
developments to ensure that the anticipated improvements to commissioning processes are delivered /
- Changes to commissioning processes are monitored and recorded through the Commission Advisory Group and any necessary remedial action taken
- Regular reports to DMT and Overview and Scrutiny Committee.
- Delays in development of new IT system
- A Risk Monitoring process and supporting documentation has been produced as is available to all staff. Regular monitoring reports are reviewed and actions taken by the Commissioning Advisory Group.
- A six month report will be reviewed by DMT and sent to Scrutiny committee for the March 2007 meeting.
Time Frame / 31 March 2007 /
Lead Officer
/ Assistant Director Strategy and PerformanceStandard 3: Effectiveness of Service Delivery and Outcomes for Service Users
Action / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 20073 (a) The Council should, with health partners, ensure that all hospital discharges of older people are effectively planned and coordinated. /
- Hospital Discharge processes are reviewed and gaps, which currently lead to poor discharge planning, are closed.
- Develop a system to identify ongoing breakdowns in hospital discharge
- Capacity within the Hospital Discharge Team
- Achieving engagement of Acute Trust colleagues at time of significant change
- PCT monitoring of unsafe discharge widened to include Social Services data. Joint regular review.
- Further joint PCT/Social Services audit of discharge in planning stage
- Issue raised at Health Economy Strategic Development Group
Time Frame / 31 December 2006 /
Lead Officer
/ Assistant Director, Older Adults and Physical Disability ServicesAction / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 2007
3 (b) The Council should effect the appointment of the adults safeguarding post, resume training in this area, and re-consider if the training should be required of certain post holders. /
- Workplan of newly appointed Safeguarding Adults Co-ordinator incorporates these targets, against which progress is reported to the Safeguarding Adults Committee
- Delays in new appointee taking up post
- The implementation of Mental Capacity Act absorbs resources
- Full training plan produced
- Awareness training commenced
- Work plan established
Time Frame / 31 March 2007 /
Lead Officer
/ Assistant Director, Mental Health and Learning DisabilitiesAction / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 2007
3 (c) The Council should clarify responsibilities between Social Services Direct and mental health services for older people to ensure that service users benefit from the most appropriate service for their needs. /
- Existing protocols and lines of responsibility are reviewed and fully implemented
- Waiting times for older adult mental health referrals via Social Services Direct, indicate no unnecessary delays
- Review of arrangements for older adult mental health across the whole of Lancashire may result in changes to service configuration
- Work agreed to establish Social Services Direct as the first point of access for older adults with mental health problems.
- Current protocols being updated prior to re-launch
Time Frame / 31 December 2006 /
Lead Officer
/ Assistant Director, Older Adults and Physical Disability ServicesAssistant Director, Mental Health and Learning Disabilities
Standard 4: Quality of Service for Service Users and carers
Action / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 20074 (a) The Council and partners should examine why there was little recorded evidence of multi-professional activity in assessments and should ensure the implementation of the Single Assessment Process. /
- Single Assessment Process is fully operational in all joint teams
- All Health partners are signed up to a fresh implementation plan for Single Assessment
- All health partners re-engaged through Health Economy Strategy Development Group
- Project Lead agreed and Project Plan in place
- High level Project Board established with implementation group below
- Person Held Record Pilot funded by PCT
Time Frame / 31 March 2007 /
Lead Officer
/ Assistant Director, Older Adults and Physical Disability ServicesAction / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 2007
4 (b) The Council should ensure the consistent good quality of case recording. /
- A single agreed system of case recording is in place in Social Services Direct
- A system for case file audit is operating and identifying areas for improvement
- Standards for process of assessments reviewed and updated
- Working group revising recording requirements to be embedded as consistent practice
Time Frame / 31 March 2007 /
Lead Officer
/ Assistant Director, Older Adults and Physical Disability ServicesStandard 5: Fair Access
Action / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 20075 (a) The Council should maintain their renewed focus on equalities and diversity and undertake the proposed equality impact Assessments into adult social care functions /
- A programme of Equality Impact Assessments is in place and being adhered to
- The Department is fully engaged with the Corporate Equality and Diversity initiatives
- Programme of Equality Impact Assessments in place
- Council focus groups in place
- Involvement with North West regional equality and diversity workshops
- Joint PCT and Council policy and delivery plan approved
Time Frame / 31 December 2006 /
Lead Officer
/ Assistant Director, Strategy and PerformancePage 1 of 8
Appendix 6(a)
Standard 6: Capacity for Improvement
Action / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 20076 (a) The Council should bring together individual supervision, a case-record audit system and performance management information into an overall approach to quality management. /
- The existing quarterly performance monitoring review captures information from supervision and case file audit.
- Performance Management Meetings take place quarterly
- Covering business, team plans, performance indicators, high/low lights
- Next cycle to include IPA, team meeting, supervision and case record audit activity
Time Frame / September 2007 /
Lead Officer
/ Assistant Director, Strategy and PerformanceAction / Objective / Measurable Planned Outcome / Risks & Barriers to Achievement / Update as of 5 February 2007
6 (b) The Council should explore with key partners the opportunities to develop joint workforce strategies that are clearly tied into service development strategies. /
- Areas for joint workforce development with partners are identified and plans agreed
- Joint Cadet Scheme
- Generic Care Workers Scheme
- Integrated Mental Health Team Plans
- Partner in Fylde Coast WFD Plan Project
Time Frame / April 2007 /
Lead Officer