14-9.02A. Use for the demolition or rehabilitation of a bridge or building requiring notification to the US EPA, California Air Resources Board, APCD, or AQMD to comply with air quality regulations.

Do not use this SSP for naturally occurring asbestos, which is not part of a structure.

Add to the end of section 14-9.02A:

1

The US EPA has established the National Emission Standards for Hazardous Air Pollutants (NESHAP). Under the Health & Safety Code § 39658(b)(1), your demolition and rehabilitation activities must comply with 40 CFR 61, Subpart M (National Emission Standard for Asbestos).

2

The asbestos survey and sampling report for this project is included in the Information Handout.

Pars. 3–7. Use in a nondelegated APCD or AQMD for Asbestos NESHAP enforcement identified on the California Air Resources Board's website, http://www.arb.ca.gov/enf/asbestos/asbestos.htm.

3

Notify the US EPA and the California Air Resources Board of your demolition activities even if the activities will not disturb asbestos-containing material.

4

You may obtain an Asbestos NESHAP Notification of Demolition and Renovation Form at the California Air Resources Board's website:

http://www.arb.ca.gov/enf/asbestos/asbestos.htm

5

Instead of the 10 working days specified at the website, mail or deliver the form with the necessary attachments at least 15 days before starting demolition or rehabilitation activities to:

US EPA - REGION IX
ASBESTOS NESHAP NOTIFICATION (AIR-5)
75 HAWTHORNE ST
SAN FRANCISCO, CA 94105

6

Mail or fax a copy of the notification form to:

CALIFORNIA AIR RESOURCES BOARD
ENFORCEMENT DIVISION
ASBESTOS NESHAP NOTIFICATION
P.O. BOX 2815
SACRAMENTO, CA 95812
FAX: (916) 229-0645

7

Submit a copy of the notification form and attachments as informational submittals before starting demolition or rehabilitation activities.

Pars. 8–11. Use in a delegated APCD or AQMD for Asbestos NESHAP enforcement identified on the California Air Resources Board's website, http://www.arb.ca.gov/enf/asbestos/asbestos.htm.

8. Insert the name of the APCD or AQMD in which the project is located.

You must notify the ______of your demolition activities even if the activities will not disturb asbestos-containing material.

9. Insert the name, address, and website of the APCD or AQMD in which the project is located. The local air district directory is available at http://www.arb.ca.gov/capcoa/roster.htm.

You may obtain the notification form, submittal instructions, and other information from:

______
______
______
______

10. Edit 10 working days as needed to match the APCD or AQMD website. Insert the name of the APCD or AQMD.

Instead of the 10 working days specified at the website, submit a notification form to the ______at least 15 days before starting demolition or rehabilitation activities.

11

Submit a copy of the notification form and the necessary attachments as informational submittals before starting demolition or rehabilitation activities.

Pars. 12–13. Use in District 4.

12

Submit a copy of the acknowledgement letter from the Bay Area Air Quality Management District (BAAQMD) as an informational submittal.

13

Do not start demolition or rehabilitation activities before the date specified in BAAQMD's acknowledgement letter.

14. Use if the asbestos survey report states that no asbestos-containing material was found in the bridge or building to be rehabilitated or demolished.

If you discover unanticipated asbestos-containing material during the demolition or rehabilitation activities, immediately stop work in that area and notify the Engineer. The Department will use other forces to remove and dispose of the material. Do not resume work in the area until authorized.

15. Insert the name of the regulatory agency for Asbestos NESHAP enforcement (e.g., the US EPA Region IX and the California Air Resources Board or the delegated APCD or AQMD in which the project is located).

Notify the ______of a change to your demolition or rehabilitation activities, including a revised work plan or the discovery of unanticipated asbestos-containing materials, within 2 days of the change or discovery.