Diocese of Sheffield Quinquennial Inspection Report – Section B

Quinquennial Inspection Report

Date

Church Name

Address

Insert image of church exterior

Section A

1 Basic Particulars

1.1 / Name of Church:
1.2 / Address:
1.3 / Diocese:
1.4 / Archdeaconry:
1.5 / Deanery:
1.6 / Parish:
1.7 / Local Authority:
1.8 / Conservation Area:
1.9 / Listed Building:
1.10 / Type of Property:
1.11 / Name of Inspector:
1.12 / Address:
1.13 / Telephone No:
1.14 / Report No:
1.15 / Date of Report:
1.16
1.17 / Date(s) of Inspection
Weather conditions on the day(s) of inspection
1.18 / Date of Previous Report:
1.19 / Previous Inspection By:
1.20 / Date Next Inspection Due:
1.21 / Copies Issued to: / PCC 2 copies
DAC 1 hard copy, 1 electronic copy

The Diocese of Sheffield leaves the fee for a Quinquennial Inspection to be negotiated between the Inspector and the parish. This should be agreed in advance of the inspection.

2 Site Particulars

2.1 / Site Area
2.2 / Burial Ground/Churchyard
2.3 / Access to Site
2.4 / Parking Facilities Available
2.5 / Rights or Easements

3 Premises Particulars

3.1 / Age of the Building
3.2 / Brief Description of the Building
3.3 / Size of the Building
3.4 / Number of Storeys
3.5 / Accommodation
3.6 / Suitability for Persons with Disabilities

.

Section B

Limitation of the Survey and Report

4.1The report is based on the findings of an inspection made from ground level, floor levels, ladders, and other readily accessible positions. Unless otherwise stated the inspection has been purely visual and no enclosed spaces or inaccessible parts, such as boarded floors, roof spaces, or hidden timbers have been opened up for inspection.

4.2Particular items not inspected or covered by this report are as follows:

  1. Inaccessible roof voids or inaccessible lofts.
  2. Voids between or below suspended floors.
  3. The organ console and organ chamber interiors.
  4. Flues or ducts.
  5. Only sample timbers inspected
  6. Manhole covers not lifted
  7. Drains not tested.
  8. Panelling not removed.
  9. Fittings not removed.
  10. Furniture not removed.
  11. Floor coverings not lifted.
  12. Parts of the building hidden or obstructed by storage.
  13. Floorboards not lifted.
  14. Monuments plaques and statuary.
  15. Tombs and graves
  16. Bells and bell frames.
  17. Clocks.
  18. Heating installation not tested.
  19. Electrical installation not tested.
  20. Lightning conductor not tested.

It may be necessary to arrange for special further inspection in relation to these matters.

4.3This report indicates the condition of the building and identifies defects. It does not purport to be wholly comprehensive or to give definitive solutions for remedial work. It is a report only and is in no way a specification for the execution of work and must never be used for such purposes. It is not a document for the purpose of obtaining estimates from builders. Professional advice should be obtained in determining appropriate repair work. Insensitive repairs (even minor repairs) can easily destroy the architectural character and inappropriate technical solutions to defects may prove unsatisfactory in the long run or even aggravate a problem.

4.4It must be emphasized that nothing in this report is intended to convey criticism of any person.

5Work Since the Last Inspection

5.1 / Previous Report
5.2 / Work Outstanding from the Previous Report
5.3 / Damage Since Last Report
5.4 / Projects Carried Out Since Last Report
5.5 / Repairs Since Last Report
5.6 / Maintenance Work
5.7 / Routine Servicing
5.8 / Works By Others Within and Around the Property.
5.9 / Defects or Problems Reported For Examination

6General Report on the Condition of the Building

Section B - Page 1

Diocese of Sheffield Quinquennial Inspection Report – Section B

7Detailed Condition Survey

The inspector should provide the following information for items in the main section of the report.
  • Component
This needs to clearly identify what is being looked at and where it is on the building.
  • Description
Include materials and construction of all components. Bullet points may be sufficient; lengthy prose is not necessary, particularly if no repairs are needed and repetition should be avoided.
  • Condition
Give a general overview, then specifics, i.e. fair condition, 2-3 broken tiles. It may be appropriate to refer to indicators of hidden or more substantial problems than are immediately apparent.
  • Repair needs
State repair needed, or what further investigation is required. In particular identify any specialist advice which the parish should seek, e.g. structural or mechanical engineers, conservators, heating specialists, arboriculturalists, etc.
Photographs should be used to illustrate particular areas of concern and can either be inserted into text or included in an appendix at the end.
7 / External Fabric
7.3 / Roof Coverings
Pitched Roofs
Flat Roofs
Flashings
7.4 / Rainwater Disposal System
7.5 / External Wall Surfaces
7.6 / External Doors and Windows
External Doors
Windows
7.7 / Bell & Bell Frame
8 / Internal Fabric
8.1 / Roof Structures, Lofts and Ceiling Spaces
8.2 / Internal Wall Finishes and Decorations
8.3 / Internal Partitions, Ceilings, and Doors
Partitions
Ceilings
Doors
8.4 / Floors
9 / Furniture and Fittings
9.1 / Furniture, Fittings,
9.2 / The Organ
10. / Services
10.1 / Heating System
10.2 / Electrical Installation
10.3 / Lightning Conductor
10.4 / Sanitary Facilities
10.5 / Fire Precautions
10.6 / Security
11. / Exterior and Site
11.1 / External Areas.

Section B - Page 1

Diocese of Sheffield Quinquennial Inspection Report – Section C

Section C

C1Recommended Repairs and Maintenance

1 / Urgent works requiring immediate attention
2 / Essential works to be carriedout during the next 18 months
3 / Works recommended to be carried out during the Quinquennial Period
4 / Works needing consideration beyond the Quinquennial Period.
5 / Works required to improve the energy efficiency of the fabric or services
6 / Works required to improve disabled access.

C2Recommendations for Further Investigation

1 / Items requiring opening up or special access to allow inspection
2 / Items for examination by experts or specialists
3 / Matters to be kept under observation.

Section C - Page 1

Diocese of Sheffield Quinquennial Inspection Report – Photographs

Section D

D1Notes on Routine Inspections and Maintenance Work

It is recommended that the Inspector identifies in their summary of recommendations which of the works would fall under the Diocese of Sheffield’s ‘Minor Works’ list (i.e. will not require a faculty), with reference being made to the Minor Works list and how to obtain such approval.

1.1Electrical Installation

Any electrical installation should be tested at least every quinquennium by a registered NICIEC electrician, and a resistance and earth continuity test should be carried out on all circuits. The engineer’s test report should be kept in the church log book. This report is based upon a visual inspection of the main switchboard and of certain sections of the wiring selected at random, without the use of instruments.

1.2The Lightning Conductor

Any lightning conductor should be tested every quinquennium in accordance with the current British Standard by a competent engineer, and the record of test results and conditions should be kept in the church log book.

1.3Heating Installation

A proper examination and test should be made of the heating system by a qualified engineer annually before the heating season begins and the report kept with the Church Log Book.

1.4Fire Extinguishers

A minimum of two water type fire extinguishers (sited adjacent to each exit) should be provided plus additional special extinguishers for the organ and boiler house as detailed below. Large churches will require more extinguishers. As a general rule of thumb, one extinguisher should be provided for every 250 square meters of floor area.

General AreasWater Extinguishers

OrganCO2 Extinguisher

Boiler House (gas fired)Dry Powder Extinguisher

All extinguishers should be inspected annually by a competent engineer to ensure that they are in good working order.

The above is only indicative and the PCC should seek advice for the local fire prevention officer and the insurers to establish their requirements.

1.5Rainwater Gutters and Down pipes

The PCC are strongly advised to enter into a contract with a local builder for cleaning out the gutters and down pipes twice a year. Ideally this should be once in November when the leaves have all fallen, and again in May.

1.6Regular Inspection

Although the Measure requires the church to be inspected every five years, it should be realised that serious trouble may develop in between these surveys if minor defects are left unattended. Churchwardens are required by the Care of Churches and Ecclesiastical Jurisdiction Measure 1991 to make an annual inspection of the fabric and furnishings, and to prepare a report for consideration by the PCC before the Annual parochial Church Meeting. Further guidance on the inspection and statutory responsibilities are contained in ‘How To Look After Your Church‘. ‘The Churchwarden’s Year’ gives general guidance on routine inspection and housekeeping, and general guidance on cleaning is given in ‘Handle with Prayer’, both published for the CCC by Church House Publishing

1.7Asbestos

It is the responsibility of the PCC to ensure a suitable and sufficient assessment should be made as to whether asbestos is liable to be present in the premises. Further details on making an assessment are available on

1.8Equality Act

The PCC should ensure that they have understood their responsibilities under the Equality Act 2010. Further details and guidance are available at

building/detailed-advice/disabled-access

1.9Headstones

Should be checked by hand to ensure that they are secure. An advisory publication on managing the safety of burial grounds has been published by the Ministry of Justice. See to download the document.

1.10Bats and other protected species

The PCC should be aware of its responsibilities where protected species are present in a church. Guidance can be found at: footprint/ways-to-take-action/wildlife

1.11Insurance

The PCC is reminded that insurance cover should be index linked, so that adequate cover is maintained against inflation of building costs. Contact should be made with the insurance company to ensure that insurance is adequate.

1.12Approvals

The repairs recommended in the report will (with the exception of some minor maintenance items) be subject to the faculty jurisdiction. Also Listed Buildings Consent will be required for any internal alterations.

1.13Consult the Expert

Some maintenance work may be undertaken on a do - it - yourself basis: some may require a builder or specialist subcontractor. In either case before applying for a Faculty or Archdeacon’s Certificate it would be advisable to consult the Architect.

1.14Construction (Design and Management) Regulations 2007

Generally under these regulations the client, usually the PCC, is responsible for ensuring the health and safety of persons working on the building. They must appoint a CDM Coordinator for the works at the earliest planning stage, and the Health and Safety Executive must be notified. However, for certain minor works the HSE do not need to be notified. The criteria for identifying minor works are as follows:

  • The work will be completed in less than 30 working days or
  • The amount of work must not be more than 500 person days.

If you are not sure whether the work meets these criteria, or clearly does not meet the criteria, please consult the Architect before approaching any builders, who will advise you accordingly.

Even if you are sure that the works are minor, you will still require someone to fulfil the role of the CDM Coordinator, and before employing any builder you must be sure that he is competent to undertake the works and that he will do so safely and not put anyone’s health and safety at risk.

Photographs

GLOSSARY OF ARCHITECTURAL AND TECHNICAL TERMS

Aisle: Part of a church alongside the nave or choir divided from it by an arcade

Apse: A polygonal or semi-circular plan to the sanctuary

Arcade: A series of arches and supporting columns

Arris: Sharp edge produced from the meeting of two edges

Ashlar: Masonry of squared blocks with dressed faces and laid in horizontal courses

Aumbry: Wall cupboard for sacred vessels

Barge board: Timber boarding on the gable end of the roof

Barrel vault: Internal shape of a simple semicircular shaped roof

Batter: Deliberate inclination of a wall face

Battlement: A parapet with alternating raised portions (merlons) and spaces (embrasures). Also called crenellation

Belfry: The chamber or stage of a tower in which the bells are hung

Bellcote: Housing for bells on a roof or gable

Bell fleche: Slender spire usually of wood containing bell(s)

Bell louvres: Horizontal slats in the window type opening within a bell chamber

Bench: Open seat, sometimes with a carved bench end

Boss: An ornamental carving at the intersection of ribs in a ceiling or vault

Brace: A subsidiary timber providing stiffness to a frame

Broaches: Sloping half pyramids adapting an octagonal spire to a square tower

Buttress: Projecting masonry or brickwork built against a wall for additional strength

Capital: The head of a column

Cementitious: Made of or containing cement

Chamfer: The surface made when a square edge is cut away at an angle

Chancel: The part of the east end of the church containing the altar and reserved for the clergy and choir

Choir: The part of the church, usually within the chancel, where divine service is sung

Ciborium: (i) a receptacle used to hold the eucharist (ii) a canopy over the altar

Cinquefoil: A leaf shaped curve of 5 parts within an arch, window head etc.

Clerestory: Windows located above the arcade

Communion rail: Low rail around an altar

Coping: A capping or covering, usually of masonry, to the top of a wall

Corbel: A projecting block of stone or timber, usually supporting a beam

Cornice: A projecting moulding along the top of a wall

Credence: A shelf or table beside the piscina for the sacramental elements

Crenellation: See battlement

Crossing: Central space at the junction of nave, chancel and transepts

Cruciform: In the form of a cross

Cusps: Projecting points between foils in gothic tracery

Dado: The lower part of an interior wall, sometimes panelled

Dressings: Worked stones, with smooth or moulded finish, used round angles or openings in masonry

Drip: A projecting stone etc. from which water drips clear of the face of a building

Dripstone: See hoodmould

Easter sepulchre: A decorated recess in the north wall of a chancel used in celebration of the Easter liturgy.

Eaves: Overhanging edge of a roof

Elevation: Face of a building

Fascia: Horizontal section usually at the junction of a wall and the lower edge of the roof

Ferramenta: Metal framing to which window glazing is fixed

Finial: Ornament at the top of a gable, pinnacle etc.

Flashing: A strip of metal used to seal junctions of roofs with adjacent construction

Flaunching: Mortar shaped to shed water

Frontal: Covering for the front of an altar

Gable: Upper, usually triangular, part of a wall at the end of a pitched roof

Gargoyle: Projecting rainwater spout, sometimes decorated

Haunching: a sloping fillet of mortar

Hip: The external angle formed by the intersection of two roof slopes

Hoodmould: Projecting moulding above a door or window opening

Hopper: (i) A box collecting water at the top of a rainwater pipe (ii) An inward opening ventilator in a window

Jamb: The side of a doorway, window or arch

Joist: Horizontal timber supporting a floor, ceiling or flat roof

Kneeler: Block of stone at the foot of a gable slope supporting the coping stones

Lancet: A tall narrow single light window, usually with a pointed head

Leading: Strips of lead between individual pieces of glass in a leaded window

Ledger: Floor slab monument

Light: A single window opening or compartment of a window between mullions

Lintel: A beam over an opening

Louvres: Angled boards or slates in a belfry opening

Lychgate: Roofed gateway at a churchyard entrance, providing resting place for a coffin

Merlon: See battlement

Moulding: The shaping of a continuous strip of wood or masonry

Mullion: A vertical member, in wood or stone, dividing a window or other opening into individual lights

Nave: The body of a church, west of the chancel or crossing

Newel: Central post to a staircase

Nosing: Projecting edge of the tread of a stair

Obelisk: A free standing tapering stone pillar of square or rectangular cross section

Ogee: A double curve with convex and concave section, occurring in arches, window and door heads and rainwater gutters.

Parapet: A low wall, usually concealing a roof or gutter

Parclose: A screen enclosing a chapel

Pew: Enclosed, fixed wooden seat

Pier: A solid masonry support, pillar of square section or masonry between doors and windows.

Pilaster: A shallow pier or square section column projecting from the face of a wall

Pinnacle: A small pointed turret on a tower, buttress etc.

Piscina: A stone basin with a drain, in a niche near the altar for washing the sacred vessels

Pointing: Exposed mortar in joints in masonry and brickwork

Purlin: A Horizontal roof timber, usually supporting rafters and spanning between walls and/or trusses

Quarry: A small diamond shaped or rectangular piece of glass in a leaded window

Quatrefoil: A leaf shaped curve of 4 parts within an arch, window head etc.

Quoins: Dressed stones at the corners of a building

Rafter: Sloping roof timbers supporting laths or battens to the roof coverings

Relieving arch: A rough arch positioned in a wall above a door or window opening to relieve it of structural loading

Rendering: A coating of mortar on a wall face

Reredos: A decorated wall or screen behind an altar

Reveal: The side of a door or window opening or recess

Rib: A curved member or projecting moulding on the underside of a vault or ceiling

Ridge roll: Lead dressed capping to the top of a pitched roof

Ringing chamber: The chamber or stage of a tower where the bell ringers stand

Rood: A crucifix over the entrance to the chancel, usually supported on a rood screen

Rood stair: A staircase formerly providing access to the rood loft on top of the rood screen

Rubble: Rough unsquared stones used for walling

Saddle bar: Horizontal metal bar to which window glazing is attached

Sanctuary: Area around the main altar

Sarking: Boards or felt over which roof slating or tiling is laid

Sedilia: Stone seats for clergy in south wall of chancel

Shake: A natural cleft or fissure (in timber)

Soaker: A strip of metal interleaved with roofing slates or tiles at junctions with walls etc

Soffit: Underside of a building element

Spandrel: Triangular area in an arch window or doorway

Squint: An oblique opening through a wall giving a view of the altar

Stoup: Stone Basin for holy water

Swan neck: A curved section of rainwater pipe connecting to the gutter