ChildSupportEnforcementSystemReplacement(CSESR)Project
PROJECTMANAGEMENTPLAN
(PMP)
ExecutiveSponsor–SeanPearson,DeputyCabinetSecretary
ExecutiveBusinessOwner-StevenG.Smith,J.D.,CSEDDirector
ExecutiveBusinessSponsor-BetinaMcCracken,CSEDDeputyDirector
ExecutiveTechnologyOwner–SusanPentecost,CIO
HSDITProjectManager--HelenYackel
OriginalPlanDate:May21,2014
Version2.0Date:June10,2015
CSESR Project Management Plan
RevisionHistory
VersionNo. / Date / Author / SummaryofChanges1.0 / 5/21/2014 / HSDITProjectManager / PlanningPMP
2.0 / 6/10/2015 / PMOTeam / Revisedtoincludeprojectsub-plansandplanningactivities
TableofContents
1.0Acronyms and Definitions
2.0Project Overview
2.1Executive Summary - Rationale for the Project
2.2Funding Sources
2.3Constraints
2.4Dependencies
2.5Assumptions
2.6Project Risks
3.0Project Authority and Organizational Structure
3.1Stakeholders
3.2Project Governance Structure
3.2.1Describe the organizational structure – Org Chart
3.2.2Describe the role and members of the project steering committee
3.2.3Organizational Boundaries, interfaces and responsibilities
3.3Executive Reporting
4.0Project Scope
4.1Project Objectives
4.1.1Business Objectives
4.1.2Technical Objectives
4.2Project Exclusions
4.3Critical Success Factors
5.0Project Deliverables and Methodology
5.1Project Management Life Cycle
5.1.1Project Management Deliverables
5.1.2Deliverable Approval Authority Designations
5.2Product Life Cycle
5.2.1Technical Strategy
5.2.2Product and Product Development Deliverables
6.0Project Work
6.1Work Breakdown Structure (WBS)
6.2Schedule allocation -Project Timeline
6.3Project Budget
6.4Project Team
6.4.1Project Team Organizational Structure
6.4.2Project Team Roles and Responsibilities
6.5Staff Planning and Resource Acquisition
6.6Project Logistics
6.6.1Project Team Training
7.0Project Management and Controls
7.1Risk Management Plan
7.2Issue Management Plan
7.3Independent Verification and Validation - IV&V
7.4Project Change Management Plan
7.5Project Budget Management
7.6Communications Plan
7.6.1Communication Matrix
7.6.2Status Meetings
7.6.3Project Status Reports
7.7Performance Measurement (Project Metrics)
7.7.1Baselines
7.7.2Metrics Library
7.8Security and Privacy Management Plan
7.9Quality Management Plan
7.9.1Quality Standards
7.9.2Project and Product Review and Assessments
7.9.3Agency/Customer Satisfaction
7.9.4Product Deliverable Acceptance Process
7.10Document Control and Maintenance Plan
7.10.1Version Control
7.10.2Project Repository
7.11Schedule Maintenance Plan
7.12Resource Management Plan
7.12.1Organizational Change Management Plan
7.13Requirements Management Plan
7.14Governance Plan
8.0Project Close
8.1Administrative Close
8.2Contract Close
9.0Appendices
9.1Appendix A - Budget Estimate
9.1.1Funding Source(s) Planning
9.1.2Budget by Major Deliverable or Type of Expense
9.1.3Budget by State Fiscal Year (SFY15-17)
9.2Appendix B - Project Planning Risks
9.3Appendix C - Independent Verification and Validation - IV&V
TableofTables
Table 1 - Acronyms and Definitions
Table 2 - Constraints
Table 3- Dependencies
Table 4- Assumptions
Table 5 - Critical Success Factors
Table 6 - Project Management Life Cycle
Table 7 - Deliverable Approval Authorities
Table 8 - Product Life Cycle
Table 9 - Funding Sources Planning
Table 10 - Budget by Major Deliverable or Type of Expense
Table 11 – PM Budget by SFY
Table 12 - Initial Project Risks Identified
Table 13 - Independent Verification and Validation
1.0AcronymsandDefinitions
AcronymsandDefinitionswhichareuniquetothisdocumentarelistedbelow
Term / DescriptionDED / DeliverableExpectationDocument
IEEE / InstituteofElectricalElectronicsEngineers
PMBOK / ProjectManagementBookofKnowledge
PMI / ProjectManagementInstitute
APD / AdvancedPlanningDocument
Table1-AcronymsandDefinitions
2.0ProjectOverview
AnautomatedchildsupportsystemisrequiredbytheFederalOfficeofChildSupportEnforcement(OCSE)tosupporttheNMChildSupportEnforcementDivision(CSED)businessandensurecompliancewithfederalandstatelawandregulationsinsupportofNewMexico’schildrenbyassistingparentswiththeirchildsupportresponsibilities.InMarch1998,thefederalgovernmentcertifiedNewMexico’sChildSupportEnforcementSystem(CSES).Today,CSESmaintainscaserecordsandaccountinformationonmorethan64,000activecases.Morethan$137.1MilliondistributedinchildsupportpaymentsviaCSES(including$14.6MillionforNavajoNation)Paymentsprovidedassistancewithchildrearingexpensesforover105,000NewMexicoandNavajoNationchildren.CSESallowstheStatetoconductautomatedmatcheswithnumerousdatasources,anditautomaticallygeneratesincomewithholdingnotices,driver’slicensessuspensionnotices,andnumerousothernoticestocustodialparents,non-custodialparents,andemployerswithoutrequiringcaseworkerintervention.
2.1ExecutiveSummary-RationalefortheProject
ThepurposeoftheChildSupportEnforcementSystemReplacement(CSESR)ProjectistofullyenhanceorreplacethecurrentChildSupportEnforcementSystem(CSES)inordertosupportCSEDandensurecompliancewithfederalandstatelawsandregulations.
Thecurrentchildsupportsystemhasbeeninoperationsince1998andisbasedontechnologyover20yearsold(itwasatransfersystem)andismaintainedinternallybyHSDITDstaff.CSESusesoldertechnologies(COBOL,VSAM,DB2andCICS)withseveralolderinterconnectedsubsystemsincludingbutnotlimitedtotheeCSES,eEmployerandeReportingWebPortals,formsprocessing(batchandusergenerated),andadocumentmanagementsystem.TheCSESapplicationcurrentlyoperatesonamainframeenvironmenthostedbytheDepartmentofInformationTechnology(DoIT).
TheDepartmentmanagestheprojectthroughaSharedProjectManagementOffice(PMO).ThisPMOwillmanagetwosystemintegratorstoreplacetheCSESandMMIS.Theprojectisexpectedtotakeuptosix(6)yearsduetothecomplexityoffederalrequirementsandtheextensivenatureoftheimplementationrequirements.
HSDexpectstoleveragethenewMasterClientIndexdevelopedforASPEN,thenewHSDEligibilitySystem,asanessentialfunctionforthenewChildSupportenforcementSystemReplacement(CSESR).AsingleWebPortalforbothclientsandprovidersmaybeincorporatedintotheASPENarchitectureratherthandevelopinganewportalforChildSupport.Wherepossible,businessandtechnologycomponentsmaybeleveragedfromASPENinsupportofthisreplacementproject.
ThepurposeofthisProjectManagementPlan(PMP)istodescribetheprocessesandactivitieswhichwillbeperformedthroughoutthelifeoftheCSESRProject. ThePMPtailorsindustry-standardprocessestotheCSESRcontexttosupportasuccessfulimplementation. ThePMPdefineshowtheprojectwillfunctionandservesastheprocessdisciplineadheredtobytheReplacementProjectsteams.
2.2FundingSources
RefertoAppendixAforfundinginformation.
2.3Constraints
ThefollowingconstraintslimittheCSESRProject:
Number / Description1 / FundingrequestsapprovedfromtheStateandFederalpartners
2 / Completionoftheprojectwithinthefundingappropriationperiods
3 / AvailabilityofGeneralfundtopayfortheStateshareofthecosts
4 / Availabilityofresourcestodevelopsharedfunctionality
5 / AvailabilityofSMEresourcestoensurethatthereisnodegradingofexistingoperationalactivities
6 / Federalapprovaloffundsforexpenditure
Table2-Constraints
2.4Dependencies
Typesincludethefollowingandshouldbeassociatedwitheachdependencylisted.
- Mandatorydependenciesaredependenciesthatareinherenttotheworkbeingdone.
- D-Discretionarydependenciesaredependenciesdefinedbytheprojectmanagementteam. Thismayalsoencompassparticularapproachesbecauseaspecificsequenceofactivitiesispreferred,butnotmandatoryintheprojectlifecycle.
- E-Externaldependenciesaredependenciesthatinvolvearelationshipbetweenprojectactivitiesandnon-projectactivitiessuchaspurchasing/procurement
Number / Description / Type(M,D,E)
1 / StateandFederalgateandfundingapprovalsthroughouttheproject / M
2 / Anappropriatesolutionwillbeevaluatedandrecommendedduringtheplanningphaseoftheproject. / M
3 / AqualifiedandexperiencedsystemsintegratorwillbeselectedthroughaRFPprocess(createanRFP,receiveproposals,evaluateproposals,selectPMOandcompletecontracting) / M
4 / AqualifiedandexperiencedIV&Vvendorwillbeselectedthroughanapprovedprocurement / M
5 / CSEDprogramandITstaffwillberequiredtoworkwithcontractPMOandintegratorstaffthroughouttheproject / M
6 / FederalcertificationoftheChildSupportEnforcementReplacementSystem / M
7 / TimelyreleaseandawardofallRFPsissuedtodevelopandimplementtheCSESR / M
8 / TimelynegotiationandexecutionofallcontractstodevelopandimplementtheCSESR / M
9 / TimelydevelopmentofinterfacesbetweeninternalHSDsystemsandexternalbusinesspartners’systems / M
Table3-Dependencies
2.5Assumptions
Thefollowingassumptionsapply:
Number / Description1 / StateandFederalfundingwillbeavailabletosupporttheproject
2 / Decisionswillbemadeinatimelymannertosupporttheprojectschedule
3 / IndividualswithdifferentperspectiveswillworktogethertodefinerequirementsforbusinessandtechnicalsolutionsthatsupportandimprovetheChildSupportSystemandSubsystemsrequiredbyourstateandfederalpartners.
4 / Projectteammemberswillpossesstheappropriateandnecessarysubjectmatterexpertise.
5 / Contractorswillhavetherequiredknowledgeandskillsetsnecessarytosuccessfullymanage,design,build,test,andimplementthetechnicalsolution.
6 / Federal(OCSE)andState(DoIT)willapprovetheproject
7 / Anychangesinthecost,scopeorschedulesoftheReplacementProjectswillbecommunicatedtotheProjectStakeholdersinatimelymanner
8 / HSDwillreceiveresponsivebidsfromqualifiedcompaniestoallRFPsissuedonbehalfoftheCSESRProject
Table4-Assumptions
AdditionalprojectassumptionsaswellasapplicableStatedecisionsandanyconstraintswillbeincorporatedintothisplanaspartoftheongoingupdateprocess.
2.6ProjectRisks
InitialCSESRprojectrisksareidentifiedinAppendixB.
3.0ProjectAuthorityandOrganizationalStructure
TheProjectOrganizationdescribestherolesandresponsibilitiesoftheprojectteam.Italsoidentifiestheotherorganizationalgroupsthatarepartoftheprojectandgraphicallydepictsthehierarchicalconfigurationofthosegroups. Itexiststoclarifyinteractionwiththeprojectteam.
3.1Stakeholders
Stakeholdersareindividualsandorganizationsthatareactivelyinvolvedintheproject,orwhoseinterestsmaybepositivelyornegativelyaffectedasaresultofprojectexecutionorprojectcompletion. Theymayalsoexertinfluenceovertheprojectanditsresults.
CSESRindividualStakeholdersareidentifiedintheCSESRProjectCharterwhichcanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“CSESRSignedProjectCharter.”
3.2ProjectGovernanceStructure
3.2.1Describetheorganizationalstructure–OrgChart
Theproject’sgovernancestructureandrelatedorganizationalchartsaredescribedintheGovernancePlan.TheGovernancePlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“GovernanceManagementPlan.”
3.2.2Describetheroleandmembersoftheprojectsteeringcommittee
TheroleoftheExecutiveSteeringCommitteewillbetoassurethatHSDprioritiesaredefinedandthatstandardprocessesareinplaceforhigh-leveldecisionsandresolutionsforHSDpriorityprojects.TheExecutiveSteeringCommitteestructureandcompositionisincorporatedintheGovernancePlan.TheGovernancePlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“GovernanceManagementPlan.”
3.2.3OrganizationalBoundaries,interfacesandresponsibilities
TheCSESRProjectwillbeplannedandimplementedincoordinatedeffortwiththeMedicaidManagementInformationSystemReplacement(MMISR)Project. Thiscoordinatedeffortisplannedtoreducecostsandincreaseefficienciesbyleveragingtechnologiesandinfrastructures
3.3ExecutiveReporting
ExecutivereportingwillincludeMonthlyreportstotheExecutiveSteeringCommittee,toourFederalpartner(OCSE),andtotheDoITProjectOversightandComplianceBureauinadditiontootherreportsasrequired.
4.0ProjectScope
4.1ProjectObjectives
4.1.1BusinessObjectives
Number / DescriptionBusinessObjective1 / Establishatechnologicallycurrentchildsupportsystem:TheCSESsystemcurrentlyinuseisbasedon20+yearoldmainframetechnology. Asaresult,versatileandrobustdatabasesandapplicationsformanagingthecomplexitiesofcurrentinformationtechnologysystemsarenotflexible. TheCSESRprojectprovidestheNewMexicoChildSupportEnforcementDivisionanopportunitytoimplementasupportingsystemwithstandardarchitecture,alogically-structuredrelationaldatabase,up-to-datesecurityrequirements(includingIRSSafeguards),moreeasilymanagedformsprocessing,andanelectronicdocumentmanagementsystem.Inaddition,theFederalAdministrationforChildrenandFamilies(ACF)NationalHumanServicesInteroperabilityArchitecture(NHSIA)standardswillbeusedasaframeworktosupportintegratedeligibilitydeterminationandinformationsharingwillbeimplemented.
Number / Description
BusinessObjective2 / Improvecustomerservice:TheintentoftheChildSupportprogramistofacilitateandensurethetransferofincomeandsupportbetweenthenoncustodialparent(NCP)andcustodialparent(CP)tobenefittheirchildren. TheCSEDstaffandtheirstateandfederalpartnersareworkingtowardthismission,butwithautomatedsystemsupportthatisbothlimitedandoutdated,thesystemlackstheflexibilitytosupportclientsinthisageofweb-basedaccess,datastandardsandefficiencies.Thisinitiativewillexhaustthepossibilitiestoprovideaccesstoaccuratedataarchitecturestandards,andservicestobothinternalandexternalclients.
Number / Description
BusinessObjective3 / Maximizeintegrationwithotherstateandfederalsystems:TheNewMexicoChildSupportEnforcementDivisionistightlyboundtoprocessingbyotherHumanServicesDepartmentdivisionsandjudicialauthorities. OnekeytoincreasedchildsupportprogramefficiencywillbethepreparationforadditionalintegrationwiththeotherHSDDivisions(IV-A(TANF)andMedicaidPrograms)andnewintegrationswiththeChildren,YouthFamilyDepartmentFosterCareDivision(IV-E),theAdministrativeOfficeoftheCourts(AOC)systemandotherstateandfederalsystems.
Number / Description
BusinessObjective4 / Maximizeautomationofroutineprocessing:Inthepast25years,automatedsystemcapabilitieshaveexpandedtoprovidemorecomprehensivesupporttoautomateworkflowevents,generatedocuments,monitorchangingcasemanagementandfinancialmanagementconditions,handlecomplexlogicalprocesses,anticipatenextactions,andprovideclearinstructionstostaff. Incorporatingthesefeaturesintoanewsystemwillleadtosignificantproductivitygains.
4.1.2TechnicalObjectives
Number / DescriptionTechnicalObjective1 / ReplacetheagingCSESmainframewithamodernevent-drivenweb-basedsystemtoreducemanualinterventionandincreaseautomation.
Number / Description
TechnicalObjective2 / RepurposesharedHSDarchitecture,technologyandstandards.
Number / Description
TechnicalObjective3 / LeveragesupportresourcesacrossHSDtoeffectivelymaintainthesystemandsupportingarchitecture.
Number / Description
TechnicalObjective4 / Increaseintegrationandinterfaceeaseandefficiencieswithotherpartnersystems.
Number / Description
TechnicalObjective5 / EnhanceexistingservicesforHSDclientsthroughapplicationsandsecurewebportalsandthroughtheuseofacommonmasterclientindex(individualuniqueID).
Number / Description
TechnicalObjective6 / Complywithallprivacysecurityrequirementsandsafeguards(includingIRS).
4.2ProjectExclusions
None
4.3CriticalSuccessFactors
Number / DescriptionQualityMetric1 / ScheduleadherencetopreventimpactonProjectandStateandFederalrequirements
QualityMetric2 / DataconversionfromexistingCSESsystemandotherdatasourcessuccessfullyvalidated
QualityMetric3 / Interfaces(State,FederalandPrivatePartner)workasrequiredandelectronicdatatransmissionisaccurateanduninterrupted.
QualityMetric4 / PMO,IntegratorandHSDendusertestingcompletedpriortorolloutusingtestplans,testscriptsandvalidatedresults.
QualityMetric5 / Timelytransitionwithnocriticaltechnicalissuesoutstandingatendofproject.
Table5-CriticalSuccessFactors
5.0ProjectDeliverablesandMethodology
5.1ProjectManagementLifeCycle
Phase / SummaryofPhase / KeyDeliverablesInitiation / ObtainStateandFederalFundingApprovals;ProcureservicesforprojectPMO. /
- ProjectCharter,InitialRiskAssessment,High-levelschedule
- PMOContract
- Specialappropriationoffunds
Planning / Assessbusinessandtechnologyneedsaswellasstateandfederalrequirementstoanalyzealternativeoptions,costs,andbenefitstodeterminethemostadvantageoussolutionfortheCSESreplacement. /
- ProjectManagementPlan(PMP)andallotherrequiredprojectplans
- MasterProjectScheduleandWBS
- ApprovedTechnicalArchitecture
- Specialappropriationoffunds
Implementation / Develop,implement,deployandtrainonsystem(s)tosupportNewMexico’sChildSupportEnforcementDivision(CSED). Decommissionlegacysystems. /
- UpdatedPMPandSchedule
- IV&VReports
- TestingandTrainingDocumentation
- TransfertoOperationsDocumentation
Closeout / Ensurethatallactivitiesoftheprojecthavebeenaddressedandproperclosureisattained /
- ProjectClosureDocumentation
- LessonsLearned
Table6-ProjectManagementLifeCycle
5.1.1ProjectManagementDeliverables
ProjectDeliverablesareworkproductsorartifactsthataredrivenbytheprojectmanagementmethodologyrequirementsandstandardprojectmanagementpracticesregardlessoftheproductrequirementsoftheproject.
5.1.1.1ProjectCharter
Description–TheinitialProjectCharterwascompletedintheInitiationphasebutmaybeupdatedduringotherphases. / DeliverableAcceptanceCriteria-VerifyProjectCharterpreparedinaccordancewithrequiredDoITelements.
StandardsforContentandFormat–VerifydocumentincludesrequiredelementsasdefinedinDoITProjectCharterTemplate.
QualityReview–KeyprojectteammembersandDoITwillreviewandevaluate.
5.1.1.2PMOContractforCSESRandMMISR
Description–Toassureprojectsuccessandreducerisk,thePMOContractwillrequirethatanexperiencedandqualifiedvendorleadandsupportmanagementactivitiesoftheprojectthroughoutthelifecycle. / DeliverableAcceptanceCriteria-Verifycontractispreparedinaccordancewithrequiredcontractstandards.
StandardsforContentandFormat–Verifydocumentincludesrequiredlanguageasrequiredforaprojectofthisscope.
QualityReview–ExecutiveSponsors,ExecutiveBusinessOwners,keyprojectteammembers,HSDGeneralCounsel,andDoITwillreviewandevaluate.
5.1.1.3ProjectManagementPlan(PMP)
Description–TheProjectManagementPlanwillbetheguideusedthroughouttheProject. Thisplanwillcontainthefollowingplans:ScopeManagement,ScheduleManagement,Budget,RiskManagement,Communications,ChangeManagement,LessonsLearnedandRoles/Responsibilitiesofteammembers. Thisplanisanevolvingdocumentasnewinformationwillbeaddedandexistinginformationwillberevisedduringallprojectphases. / DeliverableAcceptanceCriteria-VerifyallPMPcomponentsarecapturedanddocumentsarepreparedinaccordancewithrequiredstandards.
StandardsforContentandFormat–VerifydocumentincludesrequiredelementsasdefinedinDoITProjectPMPTemplate.
QualityReview–ExecutiveSponsor,ExecutiveBusinessOwners,andkeyprojectteammembers.
5.1.1.4MasterProjectSchedule
Description–ThePMOwilldevelopaMasterProjectScheduleforbothCSESRandMMISRprojectstodefineandtrackallactivitiesandresources. TheMasterProjectSchedulewillbereviewedandupdatedthroughoutthelifecycleoftheproject. / DeliverableAcceptanceCriteria-Verifyallprojectschedulecomponentsarecapturedanddocumentsarepreparedinaccordancewithrequiredstandards.
StandardsforContentandFormat–VerifydocumentisdevelopedinMSProjectandisfullyresourceloadedwithallrequiredelementsasdefinedbyHSD.
QualityReview–ExecutiveSponsors,BusinessOwners,keyprojectteammembers,PMOstaffwillreview.
5.1.1.5CSESRTechnicalArchitecture
Description–ThePMOwilldeveloptheTARCdocumentstodefinethesystemdesignandtechnicalarchitectureforCSESR. TheTARCdocumentswillconsidercurrentHSDarchitectureaswellasplannedMMISRarchitectureandinfrastructuretobestsupportanenterpriseplan. / DeliverableAcceptanceCriteria-VerifyallTARCcomponentsarecapturedanddocumentsarepreparedinaccordancewithrequiredTARCelements.
StandardsforContentandFormat–VerifydocumentincludesrequiredelementsasdefinedinDoITtemplates.
QualityReview–ExecutiveSponsor,PMOtechnicalstaffandkeyprojectteammembersandwillreview.
5.1.2DeliverableApprovalAuthorityDesignations
Theprocessandauthoritiesforreviewingandapprovingcontractdeliverablesisdocumentedinthe“ReviewandApprovalProcessforDeliverableExpectationDocumentsandContractDeliverables”SupplementalDocumentwhichcanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“DED/Sub-TaskDeliverable/MilestoneForPaymentReviewProcess.”
DeliverableNumber / Deliverable / Approvers(Whocanapprove)CSESR-DEL-001 / ProjectCharter,InitialRiskAssessment,High–levelschedule / ExecutiveSponsor,BusinessOwners,andKeyProjectTeamMembers
CSESR-DEL-002 / PMOContract / HSDCIO,CFO,GeneralCounsel,HSDDoITCabinetSecretaries,NMTRDandHSDContractsBureau.
CSESR-DEL-003 / ProjectManagementPlan / ExecutiveSponsors,BusinessOwners,KeyProjectTeamMembersandProjectCertificationCommittee
CSESR-Del-004 / MasterProjectSchedule / ExecutiveSponsors,BusinessOwners,KeyProjectTeamMembers
CSESR-DEL-005 / CSESRTechnicalArchitecture(TARC) / ExecutiveSponsors,KeyProjectTeamMembersandTARCCommittee
Table7-DeliverableApprovalAuthorities
5.2ProductLifeCycle
“Duringtheprojectmanagementlifecycle,agenciesshallselectandimplementaphaseproductdevelopmentlifecyclemethodologyapprovedbytheDepartment.”PROJECTOVERSIGHTPROCESSMemorandum
Phase / SummaryofPhase / KeyDeliverablesPlanning / Assessbusinessandtechnologyneedsaswellasstateandfederalrequirementstoanalyzealternativeoptions,costs,andbenefitstodeterminethemostadvantageoussolutionfortheCSESreplacement. /
- BusinessRequirementsDocument(BRD)
- Federallyapprovedfeasibilitystudy,alternativesanalysis,costbenefitanalysis,andImplementationAdvancedPlanningDocument(IAPD)
- Integrator(s)StatementofWork(SOW)
- IntegratorRFP(s)
Implementation / Developandimplementinfrastructureandsystem(s)tosupportNewMexico’sChildSupportEnforcementDivision(CSED). /
- SystemRequirementsDocument
- DetailedSystemDesign(DSD)Document
- TestDeliverables
- DataConversion,ImplementationandTrainingExecutionDeliverables
- DecommissioningDeliverables
- FederalCertification
Closeout / Ensurethatallactivitiesoftheprojecthavebeenaddressedandproperclosureisattained. /
- ProjectClosureRequiredDocumentation
Table8-ProductLifeCycle
5.2.1TechnicalStrategy
ThecompletetechnicalstrategyforthisprojectwillbedefinedduringthePlanningPhaseoftheCSESRprojectafteralternativesolutionshavebeenanalyzedandatechnicalsolutionisrecommended.
5.2.2ProductandProductDevelopmentDeliverables
ProductDeliverablesareworkproductsorartifactsthataredrivenbytheproductmanagementmethodologyrequirementsandstandardprojectmanagementpracticesregardlessoftheproductrequirementsoftheproject.
5.2.2.1CSESRBusinessRequirementsDocument(BRD)
Description–BusinessRequirementDocument(BRD) / DeliverableAcceptanceCriteria-Verifyallbusiness,stateandfederalrequirementsarecaptured.
StandardsforContentandFormat-Defineandutilizestandardtoolstocreateandtrack.
QualityReview–ExecutiveSponsor,ExecutiveOwners,PMOexpertstaff,andprojectteammemberswillreviewtheBRD.
5.2.2.2CSESRIAPDandSupportingDocuments
Description–IAPDandSupportingDocuments(Feasibilitystudy,alternativesanalysis,costbenefitanalysis,andImplementationAdvancedPlanningDocument(IAPD)) / DeliverableAcceptanceCriteria-Verifyalternativesidentifiedaremostadvantageoustoevaluateforfeasibilityandcostbenefitanalysis.
StandardsforContentandFormat–ValidatethatstandardOCSErequirementsandformatarefollowed.
QualityReview–ExecutiveSponsor,BusinessOwners,PMOandkeyprojectteammemberswillreviewDRAFTdocumentspriortoOCSEreviewofDRAFT. KeyPMOandprojectteammemberswillreviewFINALversionpriortoOCSE’sreviewforapproval.
5.2.2.3CSESRIntegratorStatementofWork(SOW)
Description–CSESRIntegratorStatementofWork(SOW)tobeusedforRequestforProposal(RFP)andProcurement / DeliverableAcceptanceCriteria-Verifyallbusiness,stateandfederalrequirementsarecapturedfortheIntegratorSOW.
StandardsforContentandFormat-DefineandutilizestandardMSOfficetoolstocreatedocuments.
QualityReview–ExecutiveSponsor,ExecutiveOwner,PMOexpertstaff,keyprojectteammembers,DoIT,andOCSEwillreviewandevaluateIntegrator’sSOW.
6.0ProjectWork
6.1WorkBreakdownStructure(WBS)
TheWBS,includingaWBSDictionary,willbeamaintainedaspartoftheProjectMasterScheduleandcanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“WBSDictionary.”
6.2Scheduleallocation-ProjectTimeline
AProjectSchedulehasbeencompletedandcanbefoundintheProjectNotebookoftheDocumentLibrarywiththename “Master Project Schedule.” Below is a high-level estimated timeline.
6.3ProjectBudget
TheCSESRprojectbudgettables are inAppendixA.
6.4ProjectTeam
6.4.1ProjectTeamOrganizationalStructure
TheorganizationstructureoftheprojectteamincludingthePMOhasbeendefinedforthisProjectandisincludedintheGovernancePlanforthisProjectwhichcanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“GovernanceManagementPlan.”
6.4.2ProjectTeamRolesandResponsibilities
The Project Team members along with their roles and responsibilities are maintained in the “Resource Mgmt – Resource Roles Register” in the Document Library.AllpersonnelworkingontheplanningphaseareStateemployeesandareexperiencedintheirrespectivedisciplines. AdditionalsupportpersonnelwillbesuppliedbyCSED,ITD,andotherdepartmentsasnecessary.
6.5StaffPlanningandResourceAcquisition
StaffacquisitionandresourcemanagementisdocumentedintheResourceManagementPlanwhichcanbefoundintheDocumentLibraryinthe“01-ProjectNotebook”folder.
6.6ProjectLogistics
Logisticsdescribeshowtheprojectmanager,projectteam,thebusinessowner/customerandanyvendorresourceswillphysicallyworktogether.
6.6.1ProjectTeamTraining
ThePMOwillcreateandmaintainanOrganizationalChangeManagement(OCM)Plan. ThePlanwilldefinehowtheContractorwillleadtheorganizationalchangeactivitieswithHSD,tounderstandtheamountofsupportneededtoadequatelyaddressorganizationalchangemanagement.
TheOCMwillinclude:
- Theamountofchangethatwillbecausedbythereplacementsystemsandthereadinessbyuserstoacceptchange.
- Leadershiprolesandresponsibilitieswithinthechangemanagementteamandlocalmanagers.
- Trainingneedsforstaffmigratingtothenewbusinessmodel.
- TheimpactonHumanResourcessuchaschangesinjobdescriptionsandrequiredskillsets.
- Short-termchangevs.long-termchange:assessingthosechangesthatcanbeimplementedimmediatelyandthosethatmustwaitforautomatedsupportimplementation.
- Establishmentofacommunicationsnetworkforappropriatelycommunicatingthechangetothedifferentuseraudiencesatdifferentphasesoftheproject,aswellassharingthenewbusinessmodelandprocessestostaffandstakeholders.
InadditiontotheOCMPlantheCommunicationandTrainingPlanswillidentifyotherorientationandtrainingrequiredforprojectteams.
7.0ProjectManagementandControls
TheCSESRProjectandtheMMISRProjectshareasuiteofcommonprocessestomanagetheprojects.TheseprocessesaredocumentedinasetofplanscollectivelyreferredtoasthePMOSharedProjectManagementPlans.TheseplansarelocatedintheDocumentLibraryandinclude:
- RiskManagementPlan
- IssuesManagementPlan
- IndependentVerificationandValidation–IV&V
- ProjectChangeManagementPlan
- ProjectBudgetManagement
- CommunicationPlan
- SecurityPrivacyManagementPlan
- ScheduleManagementPlan
- RequirementsManagementPlan
- QualityManagementPlan
- DocumentControlandMaintenancePlan
- ResourceManagementPlan
- OrganizationalChangeManagementPlan
- GovernancePlan
7.1RiskManagementPlan
TheRiskManagementPlandescribestheprocessforidentifyingandmanagingrisksofalltypestotheCSESRProject. ThedetailedRiskManagementPlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“RiskManagementPlan.”Project planning risksarefoundinAppendixB.
7.2IssueManagementPlan
TheIssueManagementPlandescribestheprocessforidentifyingandmanagingissuesarisingduringtheplanningandexecutionoftheCSESRProject.ThedetailedIssueManagementPlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“IssueManagementPlan.”
7.3IndependentVerificationandValidation-IV&V
HSDwillidentifyandcontractaqualifiedIV&VcontractorfortheprojectduringtheplanningphaseoftheProject,priortoImplementationandtheSystemIntegratorbeingcontracted.SeeAppendixCforinformationregardinguseofIV&V.
7.4ProjectChangeManagementPlan
TheProjectChangeManagementPlandescribestheprocessforeffectivelymanagingchangestotheCSESRProject,includingscope,schedule,costandotherControlItemelements.Changeswillbemanagedbychangecontrolboards(CCBs)ateachofthethreelevelsofgovernance,consistentwiththechangeauthorityforthatgovernancelevelasdefinedintheGovernancePlan.ThedetailedProjectChangeManagementPlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“ProjectChangeManagementPlan.”
7.5ProjectBudgetManagement
TheCSESRprojectcostplansandfinancialtransactionsarecapturedinandreportedfromthefinancialmanagementsystemsuppliedandoperatedbythePMO,andthe MasterProjectBudgetPlanandFinancialSystemDocumentation.
7.6CommunicationsPlan
TheCommunicationsPlandescribesthecommunicationvehicles,media,andaudiencesfortheformalcommunicationpublishedtointernalandexternalstakeholdersduringthelifeoftheCSESRProject.ThisinformationissummarizedintheCommunicationsMatrixoftheCommunicationsPlan.ThedetailedCommunicationsPlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“CommunicationsPlan.”
7.6.1CommunicationMatrix
TheCommunicationMatrixisincludedintheCommunicationsPlan.
7.6.2StatusMeetings
Statusmeetingagendas,includingactionitems,decisionsmade,issuesraisedandresolved,arecoveredintheCommunicationsPlan.
7.6.3ProjectStatusReports
Thedefinitionoftheformatandcontentofweeklyandmonthlystatusreportshasbeencompletedandregularstatusreportinghasbegun.DistributionofweeklyandmonthlystatusreportsisdocumentedintheCommunicationsPlan.
7.7PerformanceMeasurement(ProjectMetrics)
AllperformancemeasureswillbeidentifiedintheQualityManagementPlanandtheassociatedQualityRegister.
7.7.1Baselines
AbaselinebudgetandschedulehavebeenconstructedfortheCSESRProjectandcanbefoundintheDocumentLibraryat:
- BaselineSchedule:canbefoundintheProjectNotebookoftheDocumentLibrarywiththename “BaselineSchedule.”
- BaselineBudget:canbefoundintheProjectNotebookoftheDocumentLibrarywiththename “BaselineBudget.”
7.7.2MetricsLibrary
Projectmetricswillbereportedmonthly. Allprojectdocuments,includingmetrics,willbelocatedintheDocumentLibrary.
7.8SecurityandPrivacyManagementPlan
TheSecurityandPrivacyManagementPlandescribestheapproachthePMOwilltaketomanageSystemsIntegrationactivitiestoassureappropriateandnecessaryprovisionsareincorporatedinthesolutionelementstoachievethenecessarylevelofprivacyasarticulatedinstateandfederalrequirementsandpolicies.ThedetailedSecurityandPrivacyManagementPlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“SecurityandPrivacyManagementPlan.”
7.9QualityManagementPlan
TheQualityManagementPlandescribestheprocessesandcontrolstoassurecompliancewithclientrequirementsandincludesQualityAssuranceandQualityControlstandards,methodsandpracticesthatwillbeemployedoverthelifeoftheCSESRProject.ThedetailedQualityManagementPlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“QualityManagementPlan.”
7.9.1QualityStandards
TheQualityManagementPlandefinesQualityManagementmetrics.ThePlanwilldefinequalitycontrolsandprocessestotrack,review,approveandprocesspaymentsforallprojectdeliverablesorworkproducts.
7.9.2ProjectandProductReviewandAssessments
TheProjectreviewswillfollowStatePCCandFederalOCSEgatereviewprocesses.
TheProduct(deliverables)reviewprocessesarefoundintheDEDandDeliverableReviewProcessSupplementalDocumentwhichcanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“DED/Sub-TaskDeliverable/MilestoneForPaymentReviewProcess”
7.9.3Agency/CustomerSatisfaction
TheChildSupportEnforcementDivision(CSED)isafullpartnerinthisprojectfromInitiationandcontinuestobeinvolvedthroughCloseout. Weeklymeetingsarebeingheldwithprojectteamtoreviewprogressandstatusofprojectactivities.CommunicationandOrganizationalChangeManagementPlanswilldefinecommunicationsandactivitiestoassurethatifanyconcernsorissuesarise,theyareimmediatelyaddressed.
7.9.4ProductDeliverableAcceptanceProcess
Theprocessandauthoritiesforreviewingandapprovingcontractdeliverablesisdocumentedinthe“DED/Sub-TaskDeliverable/MilestoneForPaymentReviewProcess“SupplementalDocumentwhichcanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“DED/Sub-TaskDeliverable/MilestoneForPaymentReviewProcess.”
7.10DocumentControlandMaintenancePlan
TheDocumentControlandMaintenancePlandescribestheauthorities,controls,standards,conventions,methodsandpracticesthatwillbeemployedtoassureintegrityofthedocuments,includingcontractualdeliverables,SupplementalDocuments,andotherdocument-typeworkproductsproducedduringthelifeoftheCSESRProject.ThedetailedDocumentControlandMaintenancePlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“DocumentControlandMaintenancePlan.”
7.10.1VersionControl
VersioningconventionsandaccessandupdatecontrolstodocumentsintheDocumentLibraryhavebeendefinedandcanbefoundintheDocumentControlandMaintenancePlanintheDocumentLibrary.
7.10.2ProjectRepository
AprojectrepositoryhasbeenimplementedusingSharePointtechnologyandisusedtostorealldocument-typeworkproducts.Accessanduseprocedures,permissions,andcontrolsaredocumentedintheDocumentControlandMaintenancePlan.
7.11ScheduleMaintenancePlan
ThedetailedprocessesformaintainingandpublishingtheprojectscheduleareprovidedintheScheduleMaintenancePlanwhichcanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“ScheduleMaintenancePlan”
7.12ResourceManagementPlan
Theprocess(es)formanagingavailabilityofresources,includingbusinessandprogramsubjectmatterexperts,ITsubjectmatterexperts,andotherstaffresourcesasrequiredduringthelifeoftheCSESRProjectisdocumentedintheResourceManagementPlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“Resource(Staff)ManagementPlan.”
7.12.1OrganizationalChangeManagementPlan
TheapproachformanagingtheorganizationalandbusinessprocesschangemanagementactivitiesisdescribedintheOrganizationalChangePlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“OrganizationalChangeManagementPlan.”
7.13RequirementsManagementPlan
AdetailedprocessformanagingbusinessandtechnicalrequirementsfromidentificationthroughdispositionisprovidedintheRequirementsManagementPlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“RequirementsManagementPlan.”
7.14GovernancePlan
Projectgovernanceistheprocessforassuringconformancewithprojectstandards,policies,andpracticesandfordecision-makinganddirection.AdetaileddescriptionoftheCSESRprojectgovernanceisprovidedintheGovernancePlancanbefoundintheProjectNotebookoftheDocumentLibrarywiththename“GovernanceManagementPlan.”
8.0ProjectClose
ClosingtheprojectswillbedetailedtowardtheendoftheCSESRProjectandwillbearticulatedinaProjectClosePlan. Activitiesintheplanwillincludebutnotbelimitedto:
- Executionoffinallessonslearnedactivities
- Identificationandstorageofdocumentstoberetainedpasttheendoftheprojects
- Transitioningofstafffromtheprojects
- CloseoutofprojectfinancialsincludingaFinalBudgetReport
- FinalOpenIssuesReport
- Operationalturnoverhasbeencompleted
- Ensuringalldeliverableshavebeencompletedandapproved
- Allcontractshavebeenclosedortransitionedtooperatingcontractstatus
8.1AdministrativeClose
AdministrativeCloseoccursatbothendofphaseandendofproject. Thisclosureconsistsofverificationthatobjectivesanddeliverablesweremet.Acceptanceisformalizedandphaseactivitiesareadministrativelyclosedout. Administrativeclosureoccursona“by-phase”basisinaccordancewiththeWBSandshouldnotbedelayedtoprojectend. Atthatpoint,theburdenofclosingistoogreatandauditsinaccurate.
Thespecificprojectcloseactivitiesforagivenprojectarecontingentontheproject’scomplexityandsize.PMOandHSDprojectmanagerswillworkwiththedesignatedrepresentativesofallthecontractsawardedandperformedinsupportoftheCSESRProjecttotailorProjectCloseprocedurestothespecificsoftheindividualcontract(s).
8.2ContractClose
Contractcloseissimilartoadministrativecloseinthatitinvolvesproductandprocessverificationforcontractclose.
9.0Appendices
9.1AppendixA-BudgetEstimate
ThecurrentFundingSourcefortheCSESRprojectisaPlanningAdvancedPlanning Document(PADP)TheProjectestimatesbelowincludeactualappropriationforSFY15andestimatesforSFY16.
9.1.1FundingSource(s)Planning Phase
PlanningCosts(non-recurring) / StateGeneralFunds(GF) / OtherStateFunds / FederalFunds(FF) / TotalsSFY15Appropriation / $527,300 / $1,023,700 / $1,551,000
SFY16(CurrentRequest) / $3,400,000 / $ 0 / $3,400,000
Totals / $527,300 / $3,400,000 / $1,023,700 / $4,951,000
Table9-FundingSourcesPlanning
9.1.2BudgetbyMajorDeliverableorTypeofExpense
Theestimated planningdeliverablesandexpensesarebelow.
Estimated Planning Deliverables and Expenses / Current Estimated Dates / BudgetState Fiscal Year 15
Deliverable Number 1: SFY15 Operational Readiness (PMO Setup) / 10/31/2014 / $223,153
Deliverable Number 2: SFY15 Complete Project Plans / 6/30/2015 / $223,153
Deliverable Number 3: SFY15 Ongoing Project Management (9 months - $30,107.91 per month) / Payments Monthly - Oct 2014 - June 2015 / $270,971
Deliverable Number 4: SFY15 NHSIA State Self-Assessment, Data Cleanup and Conversion Plan and Interface Plans / 6/30/2015 / $714,089
Total SFY15 / $1,431,366
Estimated Planning Budget continued.
State Fiscal Years 16-17Deliverable Number 3: Ongoing Project Management / Payments Monthly - July 2015-September 2016) / $451,619
Deliverable Number 6: CSESR Project Planning and IAPD Activities / 1/31/2016 / $1,071,133
Deliverable Number 8: CSESR RFP Development and Procurement Support / 8/31/2016 / $1,071,133
Deliverable Number 4: Retainage NHSIA State Self-Assessment, Data Cleanup and Conversion Plan and Interface Plans / 4/30/2016 / $178,521
Deliverable Number 6: Retainage CSESR Project Planning and IAPD Activities / 1/31/2017 / $267,783
Deliverable Number 8: Retainage CSESR RFP Development and Procurement Support / 6/30/2017 / $267,783
IV&V (6 months starting 4/1/2016) / Payments Monthly starting 4/1/2016 / $210,000
Total SFY16-17 / $3,517,972
Total Estimated Planning Deliverables and Expenses (SFY15-17) / $4,949,338
Table10–Planning BudgetbyMajorDeliverableorTypeofExpense
9.1.3Budget by State Fiscal Year (SFY15-17)
PlanningCostEstimatesDescription / SFY15 & Prior / SFY16 / SFY17 / Totals
Consulting Services - PMOVendor / $1,431,365 / $1,878,733 / $1,429,239 / $4,739,338
Consulting Services - IV&VVendor / $ 105,000 / $ 105,000 / $ 210,000
Hardware
Software
Total / $1,431,365 / $1,983,733 / $1,534,239 / $4,949,337
Table 11–PM Budget by SFY
Page 1 Child Support Enforcement Replacement (CSESR) Project PMP v2 – June 10, 2015
CSESR Project Management Plan
9.2AppendixB-ProjectPlanning Risks
ID / Category / Title / Risk Description / Status / Probability / Impact / Level of Control / Exposure / Priority / Opened By / Opened Date / Owner / Risk Response22 / Financial / Project Funding / There is a risk the project will be impacted by a reduction in state or federal funding. CSESR Project is a multi-year project that requires extensive resources and funding. Initial project planning phase is funded and will be used to complete needs assessment, requirements, feasibility study, IAPD and RFP. Additional funding will be requested and required for the Implementation Phase. This risk is for both State and OCSE Federal Funding. / Open / 3 / 4 / 4 / 3 / High / Tom Wallace / 1/7/2015 / Sean Pearson / Accept
23 / Project Management / Resources / There is a risk that limitations in state resources impact the project. System replacement projects are long-term efforts that require the necessary quantity and quality of resources. Resources must be skilled and prepared to handle complexities of the processes. Resource challenges for quantity include transfers, retirement, job changes or replacement. Resource challenges for quality include necessary skills, proper training and clear direction in tasks. This risk is for State staff. / Open / 3 / 4 / 3 / 4 / High / Tom Wallace / 1/7/2015 / Betina McCracken / Accept
24 / Technical / CSES Operational Impacts / There is an operational risk if state or federal law changes require legacy system development. The CSES system is stable and impacts to basic operations are minimal, however, if state or federal legislative mandates are required during the planning or implementation phase, the CSESR project could be impacted by both resources shortages and impacts to current operations capabilities. / Open / 3 / 4 / 3 / 4 / High / Tom Wallace / 1/7/2015 / Cat Thomas / Accept
25 / Technical / Enterprise Challenge / There is a risk that HHS enterprise technical visions impacts the project. New Mexico's strategic Enterprise vision includes leveraging components and data across the HHS environment. This includes CSESR, MMISR and Aspen; Analysis and realization of these enterprise benefits could have project impacts. First, the time required to adequately scope and plan could impact the current project schedule; Second, the ability to share data and components across the enterprise may have data governance and ownership considerations; third, will the vendor community be responsive to these efforts. / Open / 3 / 4 / 3 / 4 / High / Tom Wallace / 1/7/2015 / Sean Pearson / Accept
27 / Project Management / CSESR IAPD Deliverable Due Date / The IAPD approval is the final milestone for completion of Deliverable 6. The date is at risk due to the potential for the largest item, the feasibility study to exceed planned date. This risk is tied to Risk 22 funding and the extended time maybe required to refine the CSESR Replacement cost. Replacement costs are also tied to the enterprise approach and framework solution that is in progress. / Open / 4 / 4 / 3 / 5.3 / High / Tom Wallace / 5/30/2015 / Tom Wallace / Accept
Table12-InitialProjectRisksIdentified
ARiskRegisterwillbemaintainedontheprojectSharePointsitethroughouttheproject.
Page 1 Child Support Enforcement Replacement (CSESR) Project PMP v2 – June 10, 2015
CSESR Project Management Plan
9.3AppendixC-IndependentVerificationandValidation-IV&V
IV&VwillbeincludedontheCSESRprojectconsistentwithFederalOCSErequirements.
Consistentwiththeprojectcharter,thetablebelowisintroducedtoclarifytheuseofIV&Vonbothrequiredandoptionalsystemchanges:
Project/ProductArea / Transition+Enhancement
Include–Yes/No / Enhancements
Only
Include–Yes/No
ProjectManagement / Yes / Yes
QualityManagement / Yes / Yes
Training / Yes / No
RequirementsManagement / Yes / Yes
OperatingEnvironment / Yes / No
DevelopmentEnvironment / Yes / No
SoftwareDevelopment / Yes / Yes
SystemandAcceptanceTesting / Yes / Yes
DataManagement / Yes / No
OperationsOversight / Yes / No
BusinessProcessImpact / Yes / Yes
Table13-IndependentVerificationandValidation
Page 1 Child Support Enforcement Replacement (CSESR) Project PMP v2 – June 10, 2015