City of Seattle Invitation to Bid #SPU-624

Addendum

Updated on: 11/30/2016

The following is additional information regarding Invitation to Bid # SPU-624 titled Difficult/Limited Access Drilling Services released on 11/14/2016. The due date and time for responses is now 12/07/2016; 3:00PM (Pacific). This addendum includes both questions from prospective proposers and the City’s answers and revisions to the ITB. This addendum is hereby made part of the ITB and therefore, the information contained herein shall be taken into consideration when preparing and submitting a bid/proposal.

Item # / Date Received / Date Answered / Vendor’s Question / City’s Answer / RFP Revisions
1 / 11/17/2016 / 11/21/2016 / What do I need to do to get access to the locations for this job? / The site is just outside the Tolt watershed, within a gated, SPU-employee access-only area. No site visit is anticipated. The locations are neither marked nor cleared at this time. We expect vendors to have the expertise to utilize the map we have provided (showing elevation contours, horizontal distances, topographical features) and the assurance vendor specifications will be met by the City (pad clearing and rough leveling for drilling equipment, minimum diameter of chimney to drop equipment, water supply for drilling, etc.).
The 2 locations nearest the road are roughly 250 feet downslope; The location nearest the river is approximately 500 feet downslope. Distances are horizontal. Due to the steepness of the terrain, and the density/growth of the forest, vendors should anticipate traversing downslope to the locations only with small tools/lightweight gear, with all major parts of drilling equipment delivered via helicopter.
2 / N/A / 11/23/2016 / The City of Seattle will move the due date for this bid to 12/02/2016 at 3:00 PM Pacific. / See revised Solicitation Schedule. / Event / Date
ITB Issued / 11/14/2016
Pre-Bid Conference (Optional) / 11/16/2016; 10:00AM
Deadline for Questions / 11/18/2016
Sealed Bids Due to the City / 12/02/2016; 3:00PM
3 / 11/23/2016 / 11/30/2016 / We may have scheduling impacts which prevent the ability to complete the work by 2/28/17 as noted in the RFP. Would any consideration be made to allow that date to extend further into March or April? / See Page 4, Section 5 Specifications and Scope of Work
Schedule, Orders, Delivery
Project Completion:
Replace entire section with “Anticipated project completion date is 2/28/2017 or TBD as negotiated.”