City of Barstow, CA
State of California Department of Water Resources
2014 Water-Energy Grant Program
Wastewater Treatment Plant Electrical Energy Offset and Water Waste Reduction Project
●Applicant Information/ Organization Name:
City of Barstow
220 E. Mountain View Street
Barstow, CA 92311
(760) 256-3531
●Tax ID: 95-6000675
●Point of Contact: Kody Tompkins
●Point of Contact Position Title: Chief Wastewater Treatment Plant Operator
●Proposal Name: Wastewater Treatment Plant Electrical Energy Offset and Water Waste Reduction Project
●Proposal Objective(s):
Project 1 (see Work Plan,) submitted under the water savings aspect of the 2014 Water-Energy Grant Program, includes replacement of water lines and appurtenances at the Wastewater Treatment Plant (WWTP).
Project 2 (see Work Plan,) submitted under the energy savings portion of the Program, proposes to reduce high electrical energy costs by providing an alternative renewable energy source at the WWTP.
Each project reduces waste of vital resources by lowering/offsetting energy costs, reducing GHGs (Project 2), creating public awareness of renewable energy, and reducing water waste throughout the treatment plant.
●Proposal Budget:
Other Contribution: 0
Local Contribution (Cost Share): 0
Federal Contribution: 0
In-kind Contribution: 0
Amount Requested (Grant Funds Requested): $3,046,395.00
Total Proposal Cost: $ 3,046,395.00
●Proposal Geographic Information:
Latitude: 34° 53’ 24” N
Longitude: 116° 59’ 46” W
Longitude/Latitude Clarification: N/A
Location: 2200 Riverside Drive, Barstow, CA 92311
County(ies): San Bernardino County
Groundwater Basins: Lower Mojave River Valley
Hydrologic Region(s): South Lahontan
Watershed(s): 161 9628 Mojave
●Legislative Information:
State Assembly District No. 33
State Senate District No. 183
U.S. Congressional District No. 8
●Disadvantaged Community Proposal: Yes
●Regional Proposal: No
●System Water Savings: See Attachment 2
●System Energy Savings: See Attachment 2
●Grant Total GHG Savings: See Attachment 2
●What is the statutory or other legal authority under which the applicant was formed and is authorized to operate? Municipality
●Does the applicant have legal authority to enter into a grant agreement with the State of California? Yes
PROJECT INFORMATION -- PROJECT #Project Name: Water Waste Vital Resource Reduction Project
Implementing Organization: City of Barstow
Secondary Implementing Organization: Wastewater Treatment Plant
Proposed Start Date:June 1, 2016
Proposed End Date:October 7, 2016
Project Representative: Charles C. Mitchell, City Manager, or designee
Project Manager: Kody Tompkins, Chief Plant Operator
PROJECT INFORMATION -- PROJECT #Project Name: Wastewater Treatment Plant Electrical Energy Offset
Implementing Organization: City of Barstow
Secondary Implementing Organization: Wastewater Treatment Plant
Proposed Start Date:June 1 , 2016
Proposed End Date:May 17, 2017
Project Representative: Charles C. Mitchell, City Manager, or designee
Project Manager: Kody Tompkins, Chief Plant Operator