KWTPL Monthly Progress Report Dec’ 2014

Contents

CHAPTERS

Chapter Description Page No.

1.  Executive Summary 03 – 07

2.  Project Overview 08 – 11

3.  Project Financials 12 – 13

4.  Pre-Construction Activities 14 – 15

5.  Designs & Drawings 16 – 17

6.  Mobilization 18 – 21

7.  Construction Activities 22 – 23

8.  Project Progress 24 – 25

9.  Change of Scope 26 – 27

10.  Quality Control 27 – 27

11.  Road Safety, Traffic Management & Accident Data 27 – 27

12.  Details of Submittal and Approvals 28 – 29

13.  Correspondence exchanged during the month 29 – 29

14.  Visits and Meetings 30 – 30

TABLES

Table Description Page No.

1.1 Details of land handed over to Concessionaire till 14.03.2013 04 – 04

1.2 Summary of Road Progress-Four lane completed 05 – 05

1.3 Physical Progress of Road (MCW) 05 – 05

1.4 Physical Progress of Road (S.R.) 05 – 05

1.5 Progress of Works – Structures 06 – 06

1.6 Physical & Financial Progress 07 – 07

2.1 Project Milestone as Per Schedule G 10 – 10

2.2 Pavement Composition 11 – 11

2.3 Rigid Pavement Composition 11 – 11

3.1 Break of Total Project Cost 12 – 12

3.2 Source of Project Fund 13 – 13

3.3 Lender Details of Contribution 13 – 13

3.4 Expenditure / Contribution made by agency as on date Dec, 2014 13 – 13

4.1 Details of land handed over to Concessionaire as on Dec, 2014 14 – 14

5.1 Summary of Design and Drawings Status 16 – 17

6.1 Status of Plants / Crushers 18 – 18

6.2 Summary of Machineries / Vehicles Mobilization 18 – 19

6.3 Project Monitoring and Quality Control Team 20 – 20

6.4 List of Key Personnel of EPC Contractor 21 – 21

8.1 Drawn down Schedule 24 – 24

8.2 Comparison of Financial Progress against planned vs achieved 24 – 25

8.3 IPC Certified as on date of EPC Contractor 25 – 25

12.1 Source Approvals 28 – 29

14.1 Visits 30 – 30

14.2 Meetings 30 – 30

ANNEXURES

Annexure Description

1.0  Project Location Map

4.1  List of Obstacles and Encroachments

4.2  Details of Tree Cutting

4.3  Status of Electrical Shifting

4.4  Status of Water Pipe Line Shifting

6.1  Line Diagram of the Project

6.2  List of Machinery and Vehicles

6.3  List of Manpower

6.4  SPV Organization chart

6.5  EPC Organization chart

7.1  Status of Pipe & Box Culverts, Minor Bridges, Underpasses, Major Bridges and Grade Separators

7.2  Highway Physical Progress Chart

7.3  List of Lab Equipments

7.4  Statement of Monthly Quality Control Conducted

7.5  Weather Report

8.1  “S” Curve

8.2  Progress Vs Achievement against Scope

8.3  Progress Vs Achievement against Scope (Service Road)

8.4  Linear Wise LHS & RHS Main Carriageway Status

8.5  Linear Wise LHS & RHS Service Road Status

8.6  Pictorial Drawings of Structures

8.7  Strip Chart of Project Highway

10.0  RFI Status

11.0 Accident Report

12.0  Correspondence exchanged during the month

13.0 Photographs on Site Activities

CHAPTER 1: EXECUTIVE SUMMARY

1.1  Brief Description of Project

National Highway No.47 (NH-47) is a 620 Km long highway running from Salem to Kanyakumari is an important artery passing through the States of Tamilnadu and Kerala and it passes through important towns such as Salem, Coimbatore, Palakkad, Thrissur, Kochi, Alappuzha, Kollam, Thiruvananthapuram, Nagerkoil and Kanyakumari. To provide better level of service to the vehicular traffic, the existing 2 lane carriageway road has been proposed to be widened to four lane dual carriage way including strengthening of the existing 2 lane carriage way.

Ministry of Shipping, Road Transport & Highways, Government of India, through National Highways Authority of India, have been contemplating to enhance the traffic capacity and safety of goods and passenger traffic on selected, heavy traffic dense corridors in India, and had identified one such stretch of road in Kerala State i.e., existing 2 lane highway of NH-47 between Walayar -Vadakkancherry Km. 182+250 to Km. 240+000, (approx. 54 Kms.) to 4 laning under NHDP Phase II. Project Location Map enclosed as Annexure 1.

Accordingly, NHAI invited Requests for Proposal (RFP) from short listing of Bidders in RFQ for 4 laning of above stretch of highway, on Design, Build, Finance, Operate and Transfer (“DBFOT”) Toll Basis, M/s. KNR Constructions Ltd. submitted their bid on 30th June, 2010, and become highest bidder.

National Authority of India (NHAI) has awarded the contract of four laning of existing road on NH-47 between Km.182.250 to Km.240.000, approximately 54 Km, under North – South Corridor (NHDP Phase-II), package KL2 on DBFOT (Toll) Basis in the State of Kerala, vide their letter no NHAI/Tech/NS-2/NH-47/BOT/KL-2/2006/07 dated 03.08.2012 by issuing Letter of Acceptance to the KNR Constructions Limited.

Consequent to the above, a Special Purpose Vehicle (SPV) was formed in the name of M/s. KNR Walayar Tollways Private Ltd., for implementation/execution of the project, registered under the companies act on 16th August 2012 and Concession Agreement dated 17th September 2012 is signed between M/s KNR Walayar Tollways Private Ltd (KWTPL) the Concessionaire. And M/s National Highways Authority of India (NHAI), the Employer.

NHAI Vide their letter No NHAI/Tech/NS-2/NH-47/BOT/KL-2/IE/2006/131 dated 21st May 2013 declared the appointed date as 18th May 2013 and was scheduled to be completed by 13th Nov 2015 (Construction period of 910 days).

Further NHAI Vide their letter No NHAI/11033/154/CGM(fin)/2013 dated 17th July 2013 declared the Financial closer for the project is achieved on 7th June 2013.

Subsequently, M/s. KWTPL, awarded Design and Execution of project to M/s. KNR Constructions Ltd. (Herein after called as “KNRCL”, as EPC Contractor, to execute the project under their Agreement dated: 28th November 2012 on Lum-sum Turnkey Basis.

1.2  Salient Features of the Project

The salient features of the project are as under:

·  Date of agreement : 17-09-2012

·  NHAI TPC : Rs. 682 crores

·  Concession Period : 20 years including construction period.

·  Appointed Date : 18-05-2013

·  Scheduled date of completion : 13-11-2015

·  Construction period : 910 days

·  Project Length : 53.885 Kms (from Km 182.250 to Km 240.00)

·  Client : National Highways Authority of India

·  Consultant (IE) : Artefact Projects Limited

·  Concessionaire : KNR Walayar Tollways Private Limited

·  EPC : KNR Constructions Limited

·  Date of EPC agreement : 28-11-2012

·  Date of financial closure : 16-03-2013 (Scheduled)

·  Date of financial closure : 13-05-2013 (Actual)

·  EPC cost : Rs. 790.50 Crores

·  Loan amount : 500 Crores

·  Grant : 264.60 Crores

·  Project Equity Capital : 135.91 Crores

·  Concessionaire’s TPC : Rs. 900.51 crores

·  Lead Banker : Central Bank of India

1.3  Status of Land Acquisition

The details of land handed over till is as given under detailed description is given Chapter 4 of this report.

Table 1.1 Details of land handed over to Concessionaire upto 14.03.2013

S. No. / Description / Area in Sqm / In %
1 / Required area to be made available / 2608539 / 100.00%
2 / Made available area at site as on 14.03.13 / 2406765 / 92.00%
3 / Area of ROW not made available / 201773 / 8.00%

1.4  Physical Progress - Road

EPC contractor has taken up works in almost all hindrance free lands along the stretch. The Detailed status of physical progress of various items of road works is described in Chapter 7 and the summary of road progress in Main Carriageway is as given below:

Table 1.2 Summary of Road Progress-Four lane completed

Sl. No. / Item / Total (Kms) / Completed (Kms) / Balance (Kms) / Percentage of Completion
1 / Embankment / 53.885 / 51.468 / 2.417 / 95.51%
2 / Subgrade / 53.885 / 47.650 / 6.235 / 88.43%
3 / Granular Sub Base / 53.885 / 39.900 / 13.985 / 74.05%
4 / Wet Mix Macadam / 53.885 / 38.500 / 15.385 / 71.45%
5 / Dense Bituminous Macadam / 53.885 / 37.750 / 16.135 / 70.06%
6 / Bituminous concrete / 53.885 / 30.400 / 23.485 / 56.42%

Table 1.3 Physical Progress of Road (MCW)

Sl No. / Item / Left Side / Right Side
Length
(Kms) / Comp.
(Kms) / Bal.
(Kms) / Length
(Kms) / Comp.
(Kms) / Bal.
(Kms)
1 / Embankment / 53.885 / 52.650 / 1.235 / 53.885 / 50.285 / 4.000
2 / Subgrade / 53.885 / 47.650 / 6.235 / 53.885 / 47.650 / 6.235
3 / Granular Sub Base / 53.885 / 39.950 / 13.935 / 53.885 / 39.850 / 14.035
4 / Wet Mix Macadam / 53.885 / 38.950 / 14.935 / 53.885 / 38.050 / 15.835
5 / Dense Bituminous Macadam / 53.885 / 38.150 / 15.735 / 53.885 / 37.350 / 16.535
6 / Bituminous concrete / 53.885 / 31.900 / 21.985 / 53.885 / 28.900 / 24.985

Table 1.4 Physical Progress of Road (Service Road)

Sl No. / Item / Left Side / Right Side
Length
(Kms) / Comp.
(Kms) / Bal.
(Kms) / Length
(Kms) / Comp.
(Kms) / Bal.
(Kms)
1 / Embankment / 25.695 / 21.250 / 4.445 / 23.885 / 16.540 / 7.345
2 / Subgrade / 25.695 / 10.850 / 14.485 / 23.885 / 6.040 / 17.845
3 / Granular Sub Base / 25.695 / 10.450 / 15.245 / 23.885 / 5.940 / 17.945
4 / Wet Mix Macadam / 25.695 / 10.350 / 15.345 / 23.885 / 5.940 / 17.945
5 / Dense Bituminous Macadam / 25.695 / 7.800 / 17.895 / 23.885 / 5.340 / 18.545
6 / Semi Dense Bituminous Concrete / 25.695 / 0.000 / 25.695 / 23.885 / 0.000 / 23.885

1.5  Physical Progress – Structures

Work on Culverts (Pipe & Box), Bridges (Major and Minor), Flyover, Vehicular Underpasses and Cattle Underpasses have been started. Almost 186 Nos. of Pipe & Box Culverts have been completed, which works out to 96.37% of the total scope of 193 Nos., and the quality of works has been found to be satisfactory.

Grade Separator/Flyover at Km. 203+900 have been completed

2 Major Bridges at Km. 198+875 & 207+900, have been completed.

All the 12 Nos. of Minor Bridges have been completed.

Similarly, all the 4 No’s of CUPs and 7 Nos. of VUPs (i.e. including 3 No’s of VUP’s under Change of Scope) have been completed.

The cumulative progress of structural works till end of is as shown in the Table below:

Table 1.5. Progress of works – Structures

Sl. No / CD Work / Bridges / Total
in Nos. / Completed
in Nos. / Balance
in Nos.
1 / Culverts
I / Pipe culverts / 51 / 49 / 2
II / Box Culverts – Widening / 122 / 120 / 2
III / Box Culverts – Reconstruction / 20 / 17 / 3
2 / Grade Separators @ Km. 203+900
I / Foundation / 16 / 16 / -
II / Sub structure / 16 / 16 / -
III / Super structure / 15 / 15 / -
IV / Approach slab, Crash Barrier / 2 / - / 2
3 / Major Bridges
(A) / Km.198+890
I / Foundation / 5 / 5 / -
II / Sub structure / 5 / 5 / -
III / Super structure / 4 / 4 / -
IV / Approach slab, Crash Barrier / 2 / 2 / -
(B) / Km.207+900
I / Foundation / 9 / 9 / -
II / Sub structure / 9 / 9 / -
III / Super structure / 8 / 8 / -
IV / Approach slab, Crash Barrier / 2 / 2 / -
4 / ROB
I / Foundation / 2 / 2 / -
II / Sub structure / 2 / 2 / -
III / Super structure / 1 / 1 / -
IV / Approach slab, Crash Barrier / 2 / - / 2
5 / Minor Bridges – 12 numbers
I / Foundation / 33 / 33 / -
II / Sub structure / 33 / 33 / -
III / Super structure / 21 / 21 / -
IV / Approach slab, Crash Barrier / 24 / 10 / 14
6 / VUP
I / Foundation / 26 / 26 / -
II / Sub structure / 26 / 26 / -
III / Super structure / 13 / 13 / -
IV / Approach slab, Crash Barrier / 26 / 4 / 22
7 / CUP
I / Foundation / 8 / 8 / -
II / Sub structure / 16 / 16 / -
III / Super structure / 8 / 8 / -
IV / Approach slab, Crash Barrier / 16 / 12 / 4

1.6  Change of Scope

Concessionaire identified the COS and value of Change of Scope proposed and recommended by NHAI. Detailed description on change of scope is given under Chapter 9 of this report.

1.7  Equity Support from NHAI (Grant)

Ø  Concessionaire submitted request for release of 1st tranche of Grant for Rs. 89,90,44,650/- vide letter No. KWTPL/HO/NHAI/KL-2/2014/169, Dated: 15.02.2014 with all required supporting documents. NHAI examined, verified and recommended for release of Rs. 89,90,00,728/- and forwarded to the Regional Office, Thiruvananthapuram for approval. The same is received.

Ø  Concessionaire has submitted request for release for 2nd tranche Grant for Rs. 59,47,14,693/- vide letter No. KWTPL/HO/NHAI/KL-2/2014-15/1165, Dated: 13.08.2014 with all supporting documents. PD, NHAI, PIU, Palakkad examined, verified and recommended for release of Rs. 59,47,14,693/- and forwarded to the CGM (T) & Regional Officer, Thiruvananthapuram for approval vide letter No. NHAI/PD/Palakkad/NH 47/KL-2/Grant/1618, Dated: 22.08.2014. In turn CGM (T) & Regional Officer, Chennai, Addl. Charge, RO-Kerala, has been accorded approval vide letter No. NHAI/RO-Kerala/PIU-Palakkad/KL-2/Grant/307, Dated: 25.08.2014.