I. FORMAT FOR REPORTING CONCLUDED PROJECTS

Project code and title / :
Project investigators / :
Project duration / :
Budget (Rs.)
Objectives/Goals / :
Findings/ Technology generated/ innovations made / Future course of action

II. FORMAT FOR REPORTING PROGRESS OF ONGOING PROJECTS/PROGRAMMES

Project code and title / :
Project investigators / :
Project duration / :
Objectives/goals / Status
Sub-project/ Expt. / Work to be completed/goals to be achieved / Expected outcome / Work actually completed / Actual outcome / Suggestions made if any during the previous meeting of RAC / Action taken on the suggestions / advise of the RAC / Remarks

III. FORMAT FOR NEW PROJECT PROPOSALS

  1. Title:
  2. Investigators:
  3. Relevance of the project / programme:
  4. Objectives:
  5. Duration:
  6. Project Cost:
  7. Methodology:
  8. Expected outcome:
  9. Referees comments

IV. FORMAT FOR TOT / EXTENSION COMMUNICATION PROGRAMMES / ACTIVITIES

A.PROGRESS OF OFT/OST OF TECHNOLOGIES AND FEED BACK (RSRS)

Name of the Centre / Name of the technology
INM -Mulberry / IPM-Mulberry / IPM-Silkworm / Composting / Poshan / Navinya / Nemahari
F (Nos) / Acres / F (Nos) / Acres / F (Nos) / Dfls / F (Nos) / Acres / F (Nos) / Acres / F (Nos) / Acres / F (Nos) / Acres
Total

Impact Analysis

Technology / Impact Analysis
INM / Reduction in soil pH; increased organic carbon content; 25% reduction in chemical fertilizers
IPM-Mulberry / Reduction in leaf weber and tukra infestation - 2.5% from 10%
IPM-Silkworm / Reduction in uzi incidence - 1.62% from 7.45%
Composting / Popularization of organic manures
Poshan / 16% higher leaf yield and improvement in leaf quality
Navinya / 70% recovery of the root-rot affected plants
Nemahari / 6-7.28% decrease in root-knot incidence and an improvement in leaf yield by around 10%

B.DETAILS OF EXTENSION ACTIVITIES CONDUCTED

Centre / Technology Demonstration / Group Discussion / Awareness Programmes / Field Day / Enlightenment Programme / Farmers Meet / Study Tour
Prg (Nos) / F (Nos) / Prg (Nos) / F (Nos) / Prg (Nos) / F (Nos) / Prg (Nos) / F (Nos) / Prg (Nos) / F (Nos) / Prg (Nos) / F (Nos) / Prg (Nos) / F (Nos)
Total

* Prg: No. of Programmes; F: No. of farmers

# / Name of the programme/Activity / Name of Centre/
Unit / Annual target / Achievements / Short fall, if any / Remarks
C / Expansion of new mulberry varieties (Both REC and CPP )
i / G2/G4/V1/Vishala/Anantha etc.
D / Popularization of Bivoltine Hybrids
CSR16 x 17, etc.
E / Popularization of New ICB( MV1XS8)
F / Cluster Promotion Programme
i / Captive- BV and CB
ii / IVLP Programme
G / HRD Prog- Farmers/Officials
i / ISDS
ii / TUP
iii / UPI
iv / Other
H / Revenue Generation
I / Any other activities

Referees comments:

#. / Particulars / Referee - 1 / Referee – 2 / Referee – 3
1 / Objectives
2 / Methodology
3 / Work Plan
4 / Relevance to Scientific excellence
5 / Product / process development
6 / Socio-economic importance
7 / Expertise
8 / Budget
9 / Recommendation