Blue text = from G83 (and G59 where equivalent)

Purple text = from G59 definitions

Brown text = from Requirement for Generators(RfG)

Green text = from other EU documents eg EN 50438

Black text = Changes/ additional words

To incorporate the EU Network Code Requirement for Generators (RfG) with existing GB documentation a number of new Engineering Recommendations are being drafted.

G98 Part 1 covers the connection procedure and technical requirements for Type Tested Generating Units up to 16A per phase which are referred to as Micro-generators. (G83/2 single premises)

G98 Part 2 covers the connection procedure and technical requirements for (1) multiple Type Tested Micro-generating Plants in a Close Geographic Region and connected at Low Voltage within the Customer’s Installationsand (2) Type Tested Generating Units greater than 16 A per phase with a maximum capacity of up to 1 MW and connected at Low Voltage within the Customer’s Installation. (G83/2 multiple premises and G59/3 <50kW but expanded for Type A threshold).

G99 covers the connection procedure and technical requirements for all non-Type Tested Generating Units that G59/3 covers at present.

This draft references EN 50438 which is the EU equivalent of G83/2. This is to demonstrate GB coming more into line with the EU. CENELEC are developing a new standard EN50549-which will supersede EN 50438. This document should be reviewed prior to the removal of EN 50438.

It is intended to have text in the Distribution Code similar to the existing DPC7.1.3 which sends the appropriate reader to G98 Part 1 and removes any further Distribution Code obligations in respect of generation to which this document is applicable.

This EREC G98 Part 2 draft uses text from a number of sources and is therefore colour coded to demonstrate where the words have come from as follows.

Blue text = from G83 (and G59 where equivalent)

Purple text = from G59 definitions

Brown text = from Requirement for Generators (RfG)

Green text = from other EU documents eg EN 50438

Black text = Changes/ additional words

Ricardo Energy & Environment is undertaking the drafting on behalf of the Energy Networks Association. Please send any comments to .

Engineering Recommendation G98 Part 2

Connection procedure and technical requirements for (1) multiple Type Tested Micro-generating Plants in a Close Geographic Region and connected at Low Voltage within the Customer’s Installations and (2) Type Tested Generating Units greater than 16 A per phase with a maximum capacity of up to 1 MW and connected at Low Voltage within the Customer’s Installation. (G83/2 multiple premises and G59/3 <50 kW but expanded for Type A threshold connected at LV).

1

Blue text = from G83 (and G59 where equivalent)

Purple text = from G59 definitions

Brown text = from Requirement for Generators(RfG)

Green text = from other EU documents eg EN 50438

Black text = Changes/ additional words

1.Foreword

1.1This Engineering Recommendation (EREC) G98 Part 2is published by the Energy Networks Association (ENA) and comes into effect on17 May 2019 for the following Micro-generating PlantsandGenerating Unitsfirst installed on or after that date:

(1)MultipleType TestedMicro-generating Plants in a Close Geographic Regionand connected at Low Voltagewithin the Customer’s Installation, and

(2)Type TestedGenerating Unitsgreater than 16A per phase with aMaximum Capacity of up to1 MW and connected at Low Voltagewithin the Customer’s Installation;

The definition of Micro-generating plantsand Generating Unitswithin this document includes electricity storage devices and hence this document also applies to electricity storage devices.

1.2It has been prepared and approved under the authority of the Great Britain Distribution Code Review Panel.This EREC G98 Part 2has been written to take account of the EU Network Code on Requirements for Grid Connection of Generators 14 April 2016.

1.3Generating Unitsthat meet all of the requirements set out in this document can be considered to be Type Tested, provided that there is proof that the requirements have been met. EREC G99 applies to those that do not meet all the requirements of this document.

1.4For one or more Type TestedMicro-generators forming a Micro-generating Plant in single premises not installed in a Close Geographic Region under a planned programme of work, reference should be made toEREC G98 Part 1.

1.5In order to comply with this EREC G98 Part 2,installations shall comply with the requirements of EN 50438 and the requirements set out in this document. The purpose of this EREC G98 Part 2 is to explain the technical requirements for connection of Generating Unitsfor operation in parallel with a DistributionNetwork, by addressing all technical aspects of the connection process from standards of functionality to onsite commissioning.

1.6The procedures described are designed to facilitate the connection of Generating Units whilst maintaining the integrity of the GBpublic low-voltageDistribution Network, both in terms of safety and supply quality.

1.7This EREC G98 Part 2provides sufficient information to allow:

a) Manufacturers of Generating Units to design and market a product that is suitable for connection to the GB public low-voltageDistribution Network;

b) Customers, Manufacturers and Installers of Generating Units to be aware of the requirements of the Distribution Network Operator (DNO) before the Generating Unit installation will be accepted for connection to the DNO’s Distribution Network.

2.Legal Aspects

2.1Generating Units which do not meet the requirements set out in EREC G98 Part 1or EREC G98 Part 2can only beconnected under the procedure set out in EREC G99.

2.2A DNO is under a legal obligation to disallow the connection of a Micro-generator unless it complies with this EREC G98 Part 2 and relevant legal requirements.

2.3In addition to the requirements specified in this document which allows connection to the GB public low-voltageDistributionNetwork, the Generating Unit and all of its components shall comply with all relevant legal requirements including European Directives and CE marking.

2.4This document does not remove any statutory rights of an individual or organisation; equally it does not remove any statutory obligation on an individual or organisation.

3.Scope

3.1ThisEREC G98 Part 2provides guidance on the GBtechnical requirements for the connection of Type TestedGenerating Unitsin parallel with DistributionNetworks.The requirements set out in this EREC G98 Part 2 are in addition to those of European standard EN 50438 which should be complied with in full.

3.2Generating Unitscovered in this EREC G98 Part 2are:

(1)MultipleType TestedMicro-generating Plants in a Close Geographic Regionunder a planned programme of work and connected at Low Voltagewithin the Customer’s Installations, and

(2)Type Tested Generating Unitsgreater than 16A per phase with aMaximumCapacity of up to1 MW and connected at Low Voltagewithin the Customer’s Installation; provided that any existing connected Generating Units are also Type Tested.[1]

3.3For the purposes of this EREC G98 Part 2a Micro-generator is a source of electrical energy rated up to and including 16 Ampere per phase, single or multi- phase, 230/400 V AC. This corresponds to 3.68 kilowatts (kW) on a single-phase supply and 11.04 kW on a three-phase supply. The kW rating shall be based on the nominal voltage (i.e. 230 V) as defined in BS EN 50160 and the Electrical Supply Quality and Continuity Regulations (ESQCR).

3.4Where Generating Units form part of a combined heat and power facility the impact on the DNO’s Distribution Network shall be assessed on the basis of their electrical Maximum Capacity.

3.5Where the Generating Unit includes an Inverter,its rating is deemed to be the Inverter’s continuous steady state rating.[2]

3.6For the avoidance of doubt where an installation comprises a single ConnectionPoint and more than one Inverter, which have an aggregate rating of less than 16 Amperes per phase, single or multi phase, 230/400 VAC; the installationshall be considered as a single Micro-generator.

3.7The connection of one or more Type TestedMicro-generatorsforming a Micro-generating Plant in a single premiseis covered by EREC G98 Part 1, except where being installed as part of a programme of work in a Close Geographic Region.

3.8This EREC G98 Part 2 only specifies the requirements applicable to those Generating Unitinstallations that are designed to normally operate in parallel with a public low-voltageDistributionNetwork. Those installations that are designed to operate in parallel with the DNO’s Distribution Network for short periods (i.e. less than 5 minutes per month) or as an islanded installation are considered to be out of scope, on the basis that it is not possible to devise generic rules that will ensure safe operation under all operating conditions.

3.9Generating Units that are not Type Tested to conform to the requirements of this document can only be connected inaccordance withthe process set out in EREC G99.

3.10EN 50438 Annex Dtogether with Annex A1 of this EREC G98 Part 2 describe a methodology for testing various types of electrical interface between the Generating Unitand the public low-voltageDistributionNetwork. The purpose of the type testsset out in EN 50438 Annex Dis to demonstrate compliance with the requirements of EN 50438 and hence thegeneric requirements of this EREC G98 Part 2. The Generating Unit can be considered an approved Generating Unit for connection to the GB public low-voltageDistribution Networkby:

  • satisfying the test conditions set out in EN 50438 Annex D,
  • satisfying the supplementary tests in Annex A1 of this EREC G98 Part 2 and
  • completing the Type TestVerification Reportin Appendix 5 of this EREC G98 Part 2.
  1. The Appendices contain pro forma that relate to the connection, commissioning, type testing, and decommissioning of Generating Units.
  2. Connection Agreements, energy trading and metering are considered to be out of scope. These issues are mentioned in this document only in the context of raising the reader’s awareness to the fact that these matters might need to be addressed.
  3. For Generating Units classified as emerging technology some clauses of this EREC G98 Part 2shall not apply. Details of emerging technology and their requirements are given in Appendix 1.
  4. The structure of this document is as follows:

Section / Subject / Applicable parties
1 / Foreword / All
2 / Legal Aspects / All
3 / Scope / All
4 / References / All
5 / Terms and Definitions / All
6 / Connection Process and Testing Requirements / Customer, Installer, Manufacturer, DNO
7 / Certification Requirements / Customer, DNO
8 / Operation and Safety / Customer, Installer, DNO, Manufacturer
9 / Commissioning, Notification and Decommissioning / Customer, Installer, DNO
10 / General Technical Requirements / Manufacturer
11 / Interface Protection / Manufacturer
12 / Quality of Supply / Manufacturer, DNO
13 / Short Circuit Current Contribution / Manufacturer, DNO
Appendix 1 / Emerging Technologies Exceptions / Emerging Technology Manufactures
Appendix 2 / Connection Procedure Flow Chart / Customer, Installer, DNO
Appendix 3a / Application for connection of multiple Micro-generator installations / Customer, Installer, DNO
Appendix 3b / Application for connection of Type Tested Generating Units with a Maximum Capacity of up to 1 MW / Customer, Installer, DNO
Appendix 4a / Installation Document / Customer, Installer, DNO
Appendix 4b / Site summary form / Customer, Installer, DNO
Appendix 5 / Type Test Verification Report / Customer, Installer, DNO
Appendix 6 / Decommissioning Confirmation / Customer, Installer, DNO
Appendix 7 / Not used / -
Appendix 8 / Example calculations to determine if unequal generation across different phases is acceptable or not / Installer, DNO
Annex A1 / Requirements for Testing / Manufacturer

4.References

4.1The following referenced documents, in whole or part, are indispensable for the application of this document. It is expected that it will be appropriate to use the most recent version of the documents below. Where any conflict arises the version in place at the time of commissioning of the Micro-generatorshall take precedence.

4.2Standards publications

BS 7671 Requirements for Electrical Installations

IEE Wiring Regulations.

BS EN 50160

Voltage characteristics of electricity supplied by public electricity networks.

EN 50438

Requirements for the connection of micro-generators in parallel with public low-voltage distribution networks.

BS EN 60034-4

Rotating electrical machines. Methods for determining synchronous machine quantities from tests.

BS EN 60255 series*

Measuring relays and protection equipment.

BS EN 60664-1

Insulation coordination for equipment within low-voltage systems – Part 1: Principles, requirements and tests (IEC 60664-1:2007).

BS EN 60947 series*

Low-voltage switchgear and controlgear.

BS EN 61000 series*

Electromagnetic Compatibility (EMC).

BS EN 61000-3-2

Limits for harmonic current emissions (equipment input current up to and including 16 A per phase).

BS EN 61000-3-3

Electromagnetic compatibility (EMC)Limits – Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage supply systems, for equipment with rated current < 16A per phase and not subject to conditional connection.

BS 7430

Code of Practice for Earthing

BS EN 61896-2

Instrument Transformers Additional requirements for current transformers

BS EN 61508 series*

Functional safety of electrical/ electronic/ programmable electronic safety-related systems.

BS EN 61810 series*

Electromechanical Elementary Relays.

BS EN 62116

Test procedure of islanding prevention measures for utility-interconnected photovoltaic Inverters.

IEC 60364-7-712

Electrical installations of buildings – special installations or locations – Solar photovoltaic (PV) power supply systems

IEC 60725

Considerations or reference impedances for use in determining the disturbance characteristics of household appliances and similar electrical equipment.

IEC 60909 series*

Short circuit currents in three-phase AC systems. Calculation of currents

IEC 62282-3-2 ed1.0

Fuel cell technologies - Part 3-2: Stationary fuel cell power systems - Performance test methods.

*Where standards have more than one part,the requirements of all such parts shall be satisfied, so far as they are applicable.

4.3Other publications

Health and Safety at Work etc Act (HASWA)

The Health and Safety at Work etc Act 1974 also referred to as HASAW or HSW, is the primary piece of legislation covering occupational health and safety in the United Kingdom. The Health and Safety Executive is responsible for enforcing the Act and a number of other Acts and Statutory Instruments relevant to the working environment.

Electricity Safety, Quality and Continuity Regulations (ESQCR)

The Electricity Safety, Quality and Continuity Regulations 2002 - Statutory Instrument

Number 2665 -HMSO ISBN 0-11-042920-6 abbreviated to ESQCR in this document.

Electricity at Work Regulations (EaWR)

The Electricity at Work regulations 1989 abbreviated to EaWR in this document.

Engineering Recommendation G5/4-1

Planning levels for harmonic voltage distortion and the connection of non-linear equipment to transmission and distribution networks in the United Kingdom.

Engineering Recommendation G98 part 1

Requirements for the connection of Type Tested Micro-generators (Up to and including 16A per Phase) in Parallel with Low-Voltage Distribution Systems

Engineering Recommendation G99

Requirements for the connection of non-Type Tested Generating Plant, and Generating to the Distribution systems of Licensed Distribution System Operators at less than 110kV

Engineering Recommendation P28

Planning limits for voltage fluctuations caused by industrial, commercial and domestic equipment in the United Kingdom.

Engineering Recommendation P29

Planning limits for voltage unbalance in the UK for 132kV and below.

Engineering Recommendation G74

Procedure to meet the requirements of IEC 60909 for the calculation of short-circuit currents in three-phase AC power systems.

COMMISSION REGULATION (EU) No 2016/631

Establishing a network code on Requirements for Grid Connection of Generators

Directive 2009/72/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

Concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC

Regulation (EC) No 714/2009 of the European Parliament and of the Council

on conditions for access to the network for cross-border exchanges in electricity and repealing Regulation (EC) No 1228/2003

Regulation (EC) No 765/2008 of the European Parliament and of the Council

Setting out the requirements for accreditation and market surveillance relating to the marketing of products and repealing Regulation (EEC) No 339/93

5.Terms and Definitions

Active Power Frequency Response / An automatic response of active power output, from aGenerating Unit, to a change in systemfrequency from the nominal systemfrequency;
Close Geographic Region / Either:
a) The area typically served by a single Low Voltage feeder circuit fed from a single distribution transformer; or
b) An area confirmed by the DNO on request; or
c) An area that meets at least one of the following criteria:
1) The postcodes of any of the premises where a Micro-generator installation is planned by the same organisation are the same when the last two letters are ignored…ie AB1 2xx, where xx could be any pair of letters or where x could be any letter.
2) The premises where a Micro-generator installation is planned by the same organisation are within 500m of each other.
Connection Agreement / A contract between the Distribution Network Operator and the Customer, which includes the relevant site and specific technical requirements for the Generating Unit.
Connection Point / The interface at which the Generating Unit or Customer’s Installation is connected to a Distribution Network, as identified in the Connection Agreement.
Customer / Any person supplied or entitled to be supplied with electricity at any premises within Great Britain but shall not include any person (other than the DNO in its capacity as an operator of a Distribution Network) who is authorised to generate, participate in the transmission of, distribute or supply electricity,in their capacity as such.
Customer’s Installation / The electrical installation on the Customer's side of the Connection Pointtogether with any equipment permanently connected or intended to be permanently connected thereto.
Direct Current or DC / The movement of electrical current flows in one constant direction, as opposed to Alternating Current or AC, in which the current constantly reverses direction.
Distribution Code Review Panel / The standing body established under the Distribution Code.
Distribution Network / An electrical network for the distribution of electrical power from and to third party[s] connected to it, a transmission or another Distribution Network.
Distribution Network Operator (DNO) / The person or legal entity named in Part 1 of a distribution licence and any permitted legal assigns or successors in title of the named party. A distribution licence is granted under Section 6(1)(c) of the Electricity Act 1989 (as amended by the Utilities Act 2000 and the Energy Act 2004).
Droop / The ratio of the steady-state change of frequency, referred to as nominal frequency, to the steady-state change in active power output, referred to as Maximum Capacity, expressed in percentage terms;
DNO’s Distribution Network / The systemconsisting (wholly or mainly) of electric lines owned or operated by the DNO and used for the distribution of electricity
Electricity Safety, Quality and Continuity Regulations (ESQCR) / The statutory instrument entitled The Electricity Safety, Quality and Continuity Regulations 2002 as amended from time to time and including any further statutory instruments issued under the Electricity Act 1989 (as amended by the Utilities Act 2000 and the Energy Act 2004) in relation to the distribution of electricity.
Generating Plant / Sum of Generating Units connected at one point of connection, including auxiliaries and all connection equipment.
Generating Unit / An indivisible set of installations which can generate electrical energy running independently and which can feed this energy into a Distribution Network. This includes Micro-generators. For the avoidance of doubt this definition of Generating Units includes electricity storage devices.
Great Britain or GB / The landmass of England & Wales and Scotland, including internal waters.
Installation Document / A simple structured document containing information about a Generating Unitand confirming its compliance with the relevant requirements set out in this EREC G98 Part 2.
Installer / The person who is responsible for the installation of the Generating Unit(s).
Interface Protection / The electrical protection required to ensure that anyGenerating Unitis disconnected for any event that could impair the integrity or degrade the safety of the Distribution Network. The Interface Protection is typically not installed at the interface between the DNO and Customer’s Installation.
Inverter / A device for conversion from Direct Current to nominal frequency Alternating Current.
Limited Frequency Sensitive Mode - overfrequency (LFSM-O) / AMicro-generator operating mode which will result in active power output reduction in response to a change in systemfrequency above a certain value. In GB this value is 50.4Hz.
Low Voltage or LV / A voltage normally exceeding extra-low voltage (50V) but not exceeding 1000V AC or 1500V DC between conductors or 600V AC or 900V DC between conductors and earth.
Manufacturer / A person or organisation that manufactures Generating Unitsand also‘packages’ components manufactured by others to make Generating Units which can be Type Tested to meet the requirements of this EREC G98 Part 2.
Maximum capacity / The maximum continuous active power which a Generating Plant can feed into the network as defined in the Connection Agreementor as agreed between the DNO and the Customer.
Meter Operator / A person, registered with the registration authority, appointed by either a Supplier or Customer to provide electricity meter operation services.
Micro-generating Plant / An electrical installation with one or more Micro-generators with nominal currents in sum not exceeding 16 A per phase. For the avoidance of doubt this definition of Micro-generating Plant includes electricity storage devices.
Micro-generator / Source of electrical energy and all associated interface equipment able to be connected to a regular electric circuit in a Low Voltage electrical installation and designed to operate in parallel with a public Low Voltage Distribution Networkwith nominal currents up to and including 16 A per phase.
For the avoidance of doubt this includes electricity storage devices.
Network / Plant and apparatus connected together in order to transmit or distribute electricity.
Supplier / (a) A person supplying electricity under an Electricity Supply Licence; or
(b) A person supplying electricity under exemption under the Electricity Act 1989 (as amended by the Utilities Act 2000 and the Energy Act 2004);
in each case acting in its capacity as a Supplier of electricity to Customers.
Type Tested / AMicro-generatoror Generating Unit design which has been tested to ensure that the design meets the requirements of this EREC G98 Part 2, and for which the Manufacturer has declared that all similar products supplied will be constructed to the same standards, will have the same performance. The Manufacturer’s declaration will define clearly the extent of the equipment that is subject to the tests and declaration. In the case where protection functionality is included in the tested equipment, all similar products will be manufactured with the same protection settings as the tested product.

6.Connection Processand Testing Requirements

6.1Thisdocument is aimed at two generation installation scenarios: