BIM EXECUTION PLAN TEMPLATE
Notes
The applicants must establish, implement and document the processes and procedures required to achieve BIM objectives in the BIM Execution Plan (BEP), including the following:
1. BIM workflows and delivery methodologies
2. Individual discipline modelling
2.1Revision management
2.2Model orientation and site configuration
2.3Model division and structure
2.4Modelling guidelines
3. Inter-discipline collaboration
3.1Data sharing process, framework and protocol, including the
data information and models to be shared, file formats and frequency of data sharing
3.2Coordination review process and plan, including use of BIM in
coordination meetings
3.3Clash detection procedure, methodology and plan
Besides Items 1 – 3 above, BIM Fund applicants must fill up Items 4 – 9 below, which will be reviewed for BIM Fund assessment purposes. Applicants may use other templates, as long as the equivalent content of all Items 1 – 9 are included and any other relevant information.
4. Project InformationPage 2
5. Project MembersPage 2
6. Key Performance IndicatorsPage 3
7. Model Checklist for BIM CollaborationPage 4
8. BIM Objective and Responsibility MatrixPage 6
9. Model Elements for each DeliverablePage 6
- PROJECT INFORMATION
Project Owner
Project Reference Number
Project Title
Project Description
Contract Type
Estimated Project Size (GFA)
Estimated Project Value
- PROJECT MEMBERS
Title / Name / Company / Discipline / Remarks
1
- KEY PERFORMANCEINDICATORS
Key PerformanceIndicators are used to quantify the productive performance of the BIM project delivery.
Leading Indicators (see example below)
•Time taken to resolve RFIs (latency)
•No of RFIs trending over time
- MODEL CHECKLIST FOR BIM COLLABORATION
Notes
Applicants must fulfil at minimum the list below, in at least one of the following stages:
- Design stage before tender
- Before substructure construction
- Before superstructure construction.
7.1 All Control Elements
7.2 Any 3 clash-free pair of elements in each of the Architectural-Structural, Structural-MEP and Architectural-MEP matrix
(Applicant to submit a total of 9 pairs)
7.3 Any 3 elements in each of the 3 disciplines to meet intra-discipline quality standards 1 – 4
(Applicant to submit a total of 9 elements)
7.4Sample images
7.1 CONTROL ELEMENTSLOCATION AND ORIENTATION / Link models by "Origin to origin". All models must align.
GRIDS / Check in any floor plan if grids align in all models
LEVELS / Check if levels align in all models. (Note: it is acceptable for SFL to be different from FFL provided the difference in drops between both is logical and consistent, and there is a corresponding SFL for every FFL.)
7.2 INTER-DISCIPLINE / 7.3 INTRA-DISCIPLINE
COORDINATION CLASHES:
- Perform interference checks for all coloured boxes below
- There must be zero interferences
- Perform automated interference checks for the same element.
- There must be zero interferences
- Turn off visibility of all categories except for category to check.
- There must be no instance of any model element not belonging to this category.
- Open prepared schedule
- There must be no instance of any model type using "Generic", “Typical”, "Default", or any ambiguous type
- In same schedule, all model types must be named consistently
ARCHITECTURAL / STRUCTURAL / 1 / 2 / 3 / 4 / NAMING CONVENTION / REMARKS
Floor / Wall / Ceiling / Door / Window / (others) / Structural Column / Structural Foundation / Structural Framing / Structural Wall / Slab / (others)
ARCHITECTURAL / Floor / 00
Wall
Ceiling
Door
Window
Generic Models
STRUCTURAL / Structural Column
Structural Foundation
Structural Framing
Structural Wall
Slab
Generic Models
MEP / Mechanical Equipment
Ducts
Air Terminals
Pipe
Plumbing Fixtures
Cable Tray
Generic Models
7.4 SAMPLE IMAGES
Control Elements / Intra-Discipline / Inter-Discipline
Correct / Incorrect / Correct / Incorrect / Correct / Incorrect
Models located in the same coordinates /
Models not located in the same coordinates /
2 floor elements do not overlap / 2 floor elements overlap /
Slab openings for ducts /
No slab opening, thus ducts penetrate slabs
Grids are aligned /
Grids are not aligned /
Single plumbing fixture /
Duplicate plumbing fixture /
No clashes for pile cap /
Pipe clashing with pile cap
Levels are aligned /
Levels are not aligned /
Floor category consists of floors only /
Louvers modelled as floors / Beam and ceiling free of clashes /
Beam clashing with ceiling
- BIM Objective and Responsibility Matrix (Refer to Singapore BIM Guide Appendix B)
- Model elements within each deliverable (Refer to Singapore BIM Guide Appendix A)
1