BERNARDS TOWNSHIP SEWERAGE AUTHORITY

MEETING MINUTES

January 10, 2017

CALL TO ORDER

The chairperson called the meeting to order at 6:30 PM. Those assembled saluted the flag and the chairperson read the open public meeting statement in accordance with the law.

ROLL CALL

Present: Bianchi, Carpenter, Gaziano, Malay (arrived 7:21pm)

Absent: Pavlini

Also Present: Director Timko, Attorney John Belardo, Superintendent Raymond,

Township Administrator Bruce McArthur, CFO Johnson, Treasurer McCarthy, Mott MacDonald Consultant Wohlleb

Motion by Malay, second Carpenter to excuse Pavlini for family emergency.

All in favor; motion carried.

Motion by Carpenter, second Gaziano approve Resolution #1715- adjourn to closed session at

6:31 pm – T-Mobile, Lucas Construction and Beaver Electric.

All in favor; motion carried.

Motion by Carpenter, second Gaziano to return to open session at 6:40pm.

All in favor; motion carried.

APPROVAL OF MINUTES

Motion by Carpenter, second Gaziano to approve the Regular Meeting Minutes of December 13,

2016 and Closed Session minutes, not for release.

All in favor; motion carried.

Motion by Carpenter, second Gaziano to approve the 2017 Rate Hearing Minutes.

All in favor; motion carried.

CORRESPONDENCE

None

PUBLIC COMMENT

None

ACTION/DISCUSSION ITEMS

a.  Resolution #1716 – Award PSC – Nisivoccia LLP – Auditor-$15,315

Motion by Carpenter, second Gaziano to approve resolution #1716.

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Abstain:

Motion Carried

b. Resolution #1717 – Award PSC – Richard P. Flaum – DiFrancesco Bateman Kunzman, Davis, Lehrer & Flaum, P.C.-Labor Counsel-Not to Exceed $10,000

Motion by Carpenter, second Gaziano to approve resolution #1717.

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Abstain:

Motion Carried

c. Resolution #1718 – Allocation Agreement – Genesis Property Management, LLC, Block 11201, Lot 4, 140 Allen Road

Motion by Carpenter, second Gaziano to approve resolution #1718.

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Motion Carried

d. Resolution - #1719 – Change Order #1 – DeSantis Construction, LLC-+$18,927.77

Motion Carpenter, second Gaziano to approve Resolution #1719.

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Abstain:

Motion Carried

e. Discussion – Benefits of a Utility vs Authority

CFO Johnson gave a presentation outlining the advantages of changing the Authority to a utility. CFO Johnson, Director Timko, and Attorney Belardo answered questions and discussed various topics including pension liability, budget, public meetings, management structure, fees, accounting method, and savings and efficiencies.

f. Resolution - #1720 – Approving the Design of the Lagoon Valves Project.

Motion Carpenter, second Gaziano to approve Resolution #1720.

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Abstain:

Motion Carried

g. Resolution - #1721 – Approving the Construction of the Lagoon Valves Project.

Motion Carpenter, second Gaziano to approve Resolution #1721.

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Abstain:

Motion Carried

h. Resolution #1722 – Approving the Design of the Oxidation Ditch Aerator Replacement Project.

Motion by Carpenter, second Gaziano to approve Resolution #1722.

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Abstain:

Motion Carried

i. Resolution #1723 – Approving the Construction of the Oxidation Ditch Aerator Replacement Project.

Motion by Carpenter, second Gaziano to approve Resolution #1723.

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Abstain:

Motion Carried

10. Consulting Engineer’s Report

BTSA ENGINEER’S REPORT
January, 2017 Meeting

AUTHORITY PROJECTS:

Monarch Circle (Crown Court) Pump Station

The Contractor has completed roof framing and shingling. He is currently completing the building cladding, soffits, and fascia. Excavation work on the new precast structures is starting the week of January 11, 2017, weather permitting. The contractor’s updated construction schedule proposes a completion date of April 2017, approximately 100 days past the contract completion date. Mott MacDonald is continuing shop drawing review and site inspection.

Harrison Brook STP Flow Metering Improvements

The Contractor is currently completing calibration services for the new effluent meter and is working with the SCADA integrator to connect the meter readings for the influent and effluent to the SCADA system for communications.

Sewer Rehabilitation 2016

The Contractor has completed the Contract and additional areas of work requested by BTSA. The Contractor was completed with lining work on December 5, 2016 and completed contract work on December 22, 2016. All other requested work by BTSA was also completed in December. Mott MacDonald has reviewed the submitted post lining inspection videos and will advise the Authority of any deficiencies in the contract work which the Contractor will need to correct before final completion. A request for additional construction phase services is currently being prepared for review by the BTSA based upon additional work performed that was not previously anticipated at the time of project proposal.

Harrison Brook STP-RAS/WAS Rehabilitation

Work on the final design for this project will proceed once final input is made by BTSA on the pump selection recommended by Mott MacDonald.

11. TOWNSHIP OF BERNARDS SEWERAGE AUTHORITY

OPERATOR’S REPORT

January 2017 Meeting

December 2016 Report

FLOWS

Total Flow 55,844,000 Gallons

Average Flow 1,801,000 Gallons

Maximum Flow 2,638,000 Gallons

Minimum Flow 1,144,000 Gallons

OPERATION

Suspended Solids Dry Weight NJDEP Limit

Influent 1468 Kg

Effluent 29 Kg 280 Kg/Day

Net 1439 Kg 98.0 % Removed 85%

Suspended Solids in Effluent 5.0 Mg/l 30 Mg/l

CBOD Dry Weight NJDEP Limit

Influent 692 Kg

Effluent 18 Kg 75.7 Kg/Day

Net 674 Kg 97.0 % Removed 85%

CBOD in Effluent 3.0 Mg/l 8 Mg/l

Phosphorus Dry Weight NJDEP Limit

Influent 22.0 Kg

Effluent 1.0 Kg

Phosphorus in Effluent 0.22 Mg/l 5.0 Mg/l

Remarks

Hypochlorite Used: 662 Gals. Sulfur Dioxide Used: 560 Lbs. Alum Used: 6130 Gals.

Influent pH: 7.6 S.U. Effluent pH: 7.3 S.U. Caustic Used: 1253 Gals.

Total Precipitation 8.91 Inches

Comments

·  Accepted delivery of 2017 F250 utility body service truck.

·  Alex Ortiz returned to full duty.

·  Juniper Way comminutor installed.

·  East Oak comminutor being repaired.

·  Fieldstone Drive comminutor being repaired. Replaced riser ring JW-00-10.

·  Jetted Cooper Drive and Harcourt Lane. Inspected frames and covers on both roads.

·  TV inspection of Juniper Way area.

·  Installed new service water pump #2. (Installation performed by plant personnel saving BTSA approx. $1200.00).

·  Investigated possible blockage at #30 Stockmar Drive, our line was clear.

·  Investigated possible blockage at #182 Morristown Road, our line was clear.

·  Scum pump #2 out for repair.

·  Checked syphons.

·  Changed carbon at Juniper.

·  Checked Barons.

·  Exercised plant and station generators.

·  Monthly storm drain inspections.

·  Exercised sluice gates.

·  Routine work and samples completed.

·  We continue to meet permit parameters without any problems.

SAFETY

·  Safety Director attended NJUA 12/15/16 meeting.

·  Monthly safety inspections completed.

·  Lost time accident free for 205 days.

·  Annual fire safety inspection and training 12/20/16.

PROJECTS

I&I: No report

Manhole Rehab/Pipe lining: Tri State completed pipe lining, working on punch list.

Grit Unit Upgrade: Shop drawing review.

Monarch Circle: Roof replaced, wet well delivered, reviewing shop drawings.

Plant Flow Meters: Effluent meter still being calibrated. Influent meter start up completed and personnel trained with project nearing completion. The contractor is working on punch list.

Plant Paving: Completed and working on punch list.

12. Resolution 1724 - Approval of Bill List Dated: January 10, 2017

Motion by Carpenter, second Gaziano to approve Resolution #1724-Bill List Dated

January 10, 2017 - $361,294.19

ROLL CALL

Aye: Bianchi, Carpenter, Gaziano

Nay:

Abstain:

Motion Carried

13. Member/Staff Comments

·  Interviews for the available operator position are ongoing.

14. ADJOURNMENT

Motion by Gaziano, second Malay, to adjourn at 7:28 pm.

All in flavor; motion carried.

Respectfully submitted,

Lorraine J DeGrande