27th Jan.2012
(AACP)
IDA Cr. 4013
w.e.f. March 15, 2012 till end of Project
COMPILED FOR ALL LINE DEPARTMENTS BY PCU
Assam Agricultural Competitiveness Project (Additional Financing)
Implementing Department wise Summary Costs
Implementing Departments/ Agencies / % of Total Allocation (Cost) / Total Amount / Allocation (Cost) - Rs. lakhs / Govt+W.B. (Amt) - Rs. lakhs / Ben. Share (Amt) - Rs. lakhs
Agriculture / 55% / 31623.85 / 22293.85 / 9330.00
Public Works / 27% / 15280.00 / 15280.00 / 0
Fishery / 8% / 4635.61 / 3607.94 / 1027.67
Project Coordination Unit / 6% / 3309.51 / 3309.51 / 0
AH & Veterinary / 2% / 1076.42 / 1076.42 / 0
Forest / 1% / 740.40 / 740.40 / 0
Dairy / 1% / 567.00 / 567.00 / 0
Grand Total (Lakhs) / 100% / 57232.79 / 46875.118 / 10357.67
Grand Total (Million) / 5723.28 / 4687.51 / 1035.77
Savings of AACP about $25 million would be taken to AF as spillover / Percentage of Govt+W.B & Ben. Share / 82% / 18%
Cost Govt. + W.B. in US $ / 93.75 / Million
Conv. Rate US $1 = Rs.50/- / Credit in US $ / 75.00 / Million
Assam Agricultural Competitiveness Project (Additional Financing)
Project Sub-Component wise Summary Costs
Components / Allocation
2012 / 2013 / 2014 / Total / % over total / Govt +W.B. Share / Ben share
Table 1. Irrigation and Farm Mechanization / 8775.15 / 8709.25 / 2019.25 / 19503.65 / 34% / 10173.65 / 9330.00
Table 2. Fish Production / 2536.38 / 1969.51 / 129.72 / 4635.61 / 8% / 3607.94 / 1027.67
Table 3. Agriculture Extension Services / 1425.00 / 1425.00 / 0 / 2850.00 / 5% / 2850.00 / 0
Table 4. Livestock Development / 492.16 / 301.16 / 283.10 / 1076.42 / 2% / 1076.42 / 0
Table 5. Dairy Development / 91.95 / 70.89 / 404.16 / 567.00 / 1% / 567.00 / 0
Table 6. Forestry / 477.90 / 216.00 / 46.50 / 740.40 / 1% / 740.40 / 0
Table 7. Roads for Market Linkage / 13001.72 / 2096.72 / 181.56 / 15280.00 / 27% / 15280.00 / 0
Table 8. Market Infrastructure / 5493.40 / 3753.40 / 23.40 / 9270.20 / 16% / 9270.20 / 0
Table 9. Project Coordination Unit / 1118.10 / 1163.65 / 1027.76 / 3309.51 / 6% / 3309.51 / 0
Total / 33411.76 / 19705.58 / 4115.45 / 57232.79 / 100% / 46875.12 / 10357.67
Savings of AACP about $25 million would be taken to AF as spillover / Cost in Rs Million / 4687.51 / 1035.77
Reimbursement/ Credit Rs. / 3750.01 / Million
Conversion rate US $1.00=Rs.50 / World Bank Credit US $ / 75.00 / Million
Assam Agricultural Competitiveness Project (AACP): Additional Financing
IDA CR 4013PROCUREMENT PLAN
I. / General
1 / Project information:
a. Country: India
b. Borrower: Government of India for Government of Assam.
c. Project Name: Assam Agricultural Competitiveness Project (AACP)- Additional Financing
d. Credit No.: IDA CR 4013.
e. Project Implementing Agencies: AACP is a multi-sectoral project. The project is monitored & coordinated by the State level Project Coordination Unit (PCU) and implemented by 8-line departments/ agencies. These are departments of Agriculture, Animal Husbandry & Veterinary, Dairy Development, Fisheries, Public Works, Forest and Sericulture with their Project Implementation Units (PIU) at Guwahati and Agencies like Assam Agriculture University with its HQ at Jorhat, Assam Livestock Development Agency, and also by 11 ATMA Societies in the districts of Kamrup, Nagaon, Barpeta, Sonitpur, Jorhat , Hailakandi , Dhubri, Dibrugarh, Dhemaji, Nalbari and Karbi Anglong .
2 / Bank’s approval Date of the procurement Plan: [Original: ……...; Revision 1: ……….; Revision 2: ……….]
3 / Date of General Procurement Notice: June 12, 2004
4 / Period covered by this procurement plan: From March 15, 2012 till end of the Project
5 / Goods, Works & non-consulting services shall be procured in accordance with the provisions in the "Guidelines for Procurement under IBRD Loans and IDA Credits" published by the Bank in January 2011
6 / Services of Consultants shall be procured in accordance with the provisions in the "Guidelines for the Use of Consultants by World Bank Borrowers and by the World Bank as Executing Agency " published by the Bank in January 2011.
7 / Standard Bidding Documents/ Request for Proposals documents as finalized by the Government of India Task Force and amended from time to time, are be applicable for procurements.
8 / Cost Table and Procurement Plan: Year wise items to be procured under the project have been documented in the form of a Cost Table. However, all procurements under the project are to be undertaken as per the World Bank approved detailed Procurement Plan. This Plan would be shared with implementing agencies/ departments, and would also be uploaded in ARIAS Societies web site ( as well as in World Bank's external web site. The PP should be updated by the PCU annually with Bank’s approval.
II. / Procurement Methods and related World Bank’s review thresholds for Goods, Works and non-consulting services
1 / Prior Review Threshold (Goods, Works & non-consulting services): Procurement Decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines for Procurement are as shown in the table below:-(Note: Any amendments to post-review contracts, raising the contract value to prior review threshold, will also be subject to prior review by the World Bank)
Prior Review Threshold ** / Comments
a / Goods / Contract packages estimated to cost above US $ 1,000,000 / (Approximately: Rs.450.00 lakhs for each contract)
b / Works / Contract packages estimated to cost above US $ 10,000,000 / (Approximately: Rs.4500.00 lakhs for each contract)
c / Direct Contracting / All contracts valued above US $ 10,000 shall be prior reviewed by World Bank.*** / Only for items that will meet the requirements for direct contracting as given in the para 3.7 of the "Guidelines for Procurement under IBRD Loans and IDA Credits" published by the Bank in January 2011"
** World Bank Registration (WBR) No. will be obtained for all Prior Review contracts.
** In case of Prior Review of Goods/ Works contracts, prior concurrence of the Bank will be applicable for :- Invitation for bid (IFB); Bidding Document and it’s amendments, if any; Minutes of pre-bid conference (for Works only) if it leads to issuance of Corrigendum; Bid evaluation report prepared in the prescribed format of the Bank; Contract Agreement with Check List for obtaining WBR No
*** Direct Contracting (DC) Goods, Works & non-consulting services:- DC procedure may be adopted for items, which meet the requirement of para 3.7 of Procurement Guideline, and shall be restricted to cases when the justification for it is beyond contention and not as a routine matter.
2 / Other Procurement Arrangements/ methods and related thresholds are as shown below
Procurement Method / Methods of Procurement/ Thresholds / Comments
a / Goods: ICB: / Contract packages estimated to cost above US$ 5,00,000 / World Bank's Standard Bidding Document agreed with the Govt. of India Task Force shall be used for the procurements.
c / Goods: NCB: / Contract packages estimated to cost above US$ 50,000 and below US$ 500,000
d / Goods: National Shopping / Contract packages estimated to cost below US$ 50,000
e / Works: NCB:: / Contract packages estimated to cost above US$ 50,000;
f / Works: National Shopping: / Contract packages estimated to cost below US$ 50,000.
g / Force Account Works: / Works below US$ 10,000 depending on need / Only with prior approval of the World Bank with detailed justification and provided the same fulfills the requirements of clause 3.6 of the Procurement Guidelines of the Bank.
** Post Review requirements: The contract register incorporating, list of all Post Review Contracts is to be forwarded to the Bank on an Annual Basis or as requested by Bank.
3 / Pre-qualification. Not envisaged
4 / Procedures for Community Driven Development (CDD) Components (as per paragraph. 3.19 of the Guidelines)
a / CDD is firmly embedded in AACP’s design, this includes different levels of community involvement with decentralization decision-making, resource control, implementation, and monitoring in sub-projects related to fisheries, dairy, agriculture, forestry, watershed management etc. The goals of community driven development of AACP are to promote security, opportunity and empowerment by: (i) strengthening accountable, inclusive community groups; (ii) supporting broad-based participation by poor people in the strategies and decisions that affect them; (iii) facilitating access to information and linkages to the market
b / Community Participation. Goods, works and services consisting of investments in (i) drainage schemes; (ii) pond, tank and beel fisheries; and (iii) drilling tube wells; (iv) pumping equipment; (v) tractors; and (vi) power tillers, and accessories may be procured on the basis of community participation in accordance with the following procedures:-
(i) Fish production inputs: FOE procedure, i.e. procurement by community groups as per their choice from the approved reference price list along with local outlet/ or authorized dealer for fish inputs, to be published by the Director of Fisheries/ DACC following a floating of enquiry process;
(ii) Pump-sets and farm machinery:- FOE procedure (i.e. procurement by community groups as per their choice from the approved brands/ models from the manufacturer’s local outlet/ or authorized dealer out of an approved list of manufacturers, including the prices, to be published by the Director of Agriculture, Assam for irrigation pump-sets and farm machinery following a floating of enquiry process); and
(iii) Civil Works: Soliciting at least three quotations from qualified contractors or by the community on its own for civil works contracts.
5 / Reference to : Project Operational/Procurement Manual.
a / Operational Manual: A Project Operational Manual for the Project has been prepared for guidance of the implementing agencies of the project. This document may be seen/ downloaded from the web site
b / Procurement Manual: The Procurement Manual for the AACP, updated during AACP's MTR Mission would be used as a guidance by the implementing agencies of the project. This document may be seen/ downloaded from the web site Any deviation from the procurement manual is not permitted except with prior approval of PCU/World Bank. As far as threshold for procurement and procurement methods are concerned, the provisions laid down in this Procurement Plan shall prevail.
6 / Implementing Department wise details of Goods/ Works along with Selection Methods and Time Schedule is attached to this Procurement Plan
III / Selection of Consultants: Procurement Methods & Related World Bank Review Thresholds for Consulting Services:
1 / Applicable Methods of procurement: Quality and Cost Based Selection [QCBS]; Quality Based Selection [QBS]; Selection under a Fixed Budget [FBS]; Least Cost Selection [LCS]; Selection Based on Consultants Qualifications [CQS]; Single Source Selection [SSS]; Selection of Individual Consultant as per Para 5 of the Consultancy Guidelines. Details as provided in PAD & Project Agreement
2 / Prior Review Threshold: Selection decisions subject to Prior Review by World Bank, as stated in Appendix-1 to the Guidelines Selection and Employment of Consultants are as shown in the table below:- (Note: Any amendments to post-review contracts, raising the contract value to prior review threshold, will also be subject to prior review by Bank)
Selection of .. / Prior Review Threshold ** / Remarks
a / Consulting Firms / Contracts for employment of Consulting Firms estimated to cost more than US $ 500,000 / (Approximately: Rs.225.00 lakhs for each contract)
b / Individual Consultants / Contracts for employment of Individual Consultants estimated to cost more than US $ 50,000 / (Approximately: Rs.22.50 lakhs for each contract)
c / Single Source Consultants / All Single Source Consultancy assignments valued above US $ 10,000 / (Approximately: Rs.4.50 lakhs for each contract)
** ALL Terms of Reference (TOR) for consultancy assignments will be subject to prior technical concurrence by Task Team Leader of the World Bank
3 / Prior Review requirements:- In case of Prior Review Consultancy contracts, prior concurrence of the Bank will be applicable for the following: Expression of Interest (EOI); Short List; Request for proposal (RFP) and it’s amendments, if any; Minutes of pre-bid conference, if any and if it leads to amendment to the RFP; Technical Evaluation Report prepared in the prescribed format of the Bank; Draft Contract Agreement along with Combined Evaluation report; Final Contract along with prescribed Check List for obtaining WBR No
4 / Short List:- National Consultants: For consultancy contracts below US$ 500,000 the Short List of consultants may comprise entirely of national consultants.
5 / Post review assignments: All other consultancy assignments not subject to prior review by the World Bank would be Post Reviewed by the Bank.
6 / Other Special Selection Arrangements/ Requirement
a / Consultancy assignment with NGOs, may be procured through CQS procedure, in which qualification/ experience of atleast three NGOs would be considered.
b / Post Review requirements: List of all Post Review consultancy contracts is to be forwarded to the Bank on an Annual Basis. The Bank’s Staff contracts / Bank’s Audit Consultant would review these on a sample basis
d / Head of the line departments/ agencies will finalize and approve all contracts upto the national shopping limit.
e / World Bank Registration (WBR) No.: WBR No. will be obtained for all prior review contracts above US$ 500,000 accompanied by checklist;
7 / Implementing Department wise details of Consultancy Assignments along with Selection Methods and Time Schedule is attached to this Procurement Plan.
IV / Capacity Building Activities of implementing department are included in their respective tables and are also compiled and attached separately.
Assam Agriculture Competitiveness Project (AACP): Additional Financing
PROCUREMENT PLAN FOR CIVIL WORKS
SL No. / Package No. / Description of Works/Goods / Road Length in KM/ Quantity in Nos. / No of Bridges to be converted to RCC / Estt. Cost. (Rs. in Lakhs) / Method of Procurment ICB/ NCB / Selection of Roads/ Markets/ building sites / DPR Preparation (Date & Value) / Prepartion of Bid Document (Date) / PCU's No Objection to DPR & Bidding Document (Date) / Bid Invitation (Date) / Bid Open (Date) / BER prepared (Date) / PCU's No Objection to BER (Date) / Contract Sign (Date) / Cotract No. / Name of Contractor / WBR NO. / Remarks
1 / 2 / 3 / 4 / 5 / 6 / 7 / 8 / 9 / 10 / 11 / 12 / 13 / 14 / 15 / 16 / 17 / 18 / 19 / 20
Public Works Department (PWD: Rural Roads:
A. Upgradation of roads and bridges / 113.00 / 29 / 11300.00 / NCB / Selected / 31st Jan 2012 / 10th Feb. 2012 / 15th Feb 2012 / 20th Feb. 2012 / 20th Mar 2012 / 30th April 2012 / 15th May 2012 / 31st May 2012
1 / SN-9 / Chandamari Bengali to Dulungmukh Road / 12.90 / 2
2 / SN-11 / Jamuguri to Gomeripal Road / 6.50 / 1
3 / KMJ-2 / Chargola to Chandrapur via Kaliganj Bazaar Road / 13.70 / 1
4 / KMJ-7 / Kaliganj BTC to Srimanta Kanisail via Basla Bazar Road / 7.94 / 3
5 / NL-9 / Mukalmua Adattari via Nayanpur Road / 4.93 / 0
6 / GLP-1 / Dhumerghat Trangapur Road / 13.10 / 2
7 / DH-9 / Kathalbari Purandiara R0ad / 2.44 / 2
8 / NL-11 / Paikarkuchi link Road / 4.43 / 2
9 / NL-14 / Bhakatpukhuri Chowk to Pokhura via Solmara upto Bhojkuchi Tihu Road / 7.60 / 1
10 / GLP-3 / Daranggiri Nandeswar Road / 15.26 / 8
11 / GLP-8 / Nepalikhuti to Bhojmala Road (upto Krishnai) / 12.70 / 4
12 / GLP-10 / Maladhara Barobagan Road / 11.50 / 3
B. Road construction with Innovative Technology / 25.00 / TBI / 1250.00 / NCB / 31st Mar. 2012 / 30th April 2012 / 15th May 2012 / 31st May 2012 / 1st Jun. 2012 / 30th Jun. 2012 / 31st Jul. 2012 / 14th Aug. 2012 / 31st Aug. 2012
C. Roads for ensuring connectivity to Markets / 32.00 / TBI / 2133.44 / NCB / 1st Jun. 2012 / 31st Jul. 2012 / 14th Aug. 2012 / 31st Aug. 2012 / 15th Oct. 2012 / 15th Nov. 2012 / 15th Dec. 2012 / 31st Dec. 2012 / 15th Jan 2013
Agricultre Dept.: Market Infrastructure Development
D. Rural Hat (Av @ Rs. 100 lakhs/ Haat) / 30 Nos. / ` / 3000.00 / NCB / 31st Mar. 2012 / 30th April 2012 / 15th May 2012 / 31st May 2012 / 1st Jun. 2012 / 30th Jun. 2012 / 31st Jul. 2012 / 14th Aug. 2012 / 31st Aug. 2012
E. Whole Sale Market (Av @ Rs. 223 lakhs/ Haat) / 25 Nos. / ` / 5575.00 / NCB / 31st Mar. 2012 / 30th April 2012 / 15th May 2012 / 31st May 2012 / 1st Jun. 2012 / 30th Jun. 2012 / 31st Jul. 2012 / 14th Aug. 2012 / 31st Aug. 2012
F. Balance works of markets of AACP / 7 Nos. / ` / 480.00 / NCB / Selected / 31st Jan 2012 / 10th Feb. 2012 / 15th Feb 2012 / 20th Feb. 2012 / 20th Mar 2012 / 30th April 2012 / 15th May 2012 / 31st May 2012
Forest Department:
G. Construction of Range/beat offices / 3 Nos / ` / 45.00 / Selected / 31st Jan 2012 / 10th Feb. 2012 / 15th Feb 2012 / 20th Feb. 2012 / 20th Mar 2012 / 30th April 2012 / 15th May 2012 / 31st May 2012
Total / 23783.44
TBI: To be identified
AACP - Additional Financing
PROCUREMENT PLAN FOR GOODS- THROUGH ICB/ NCB
SL No. / Pkg.
No. / Description of Works/Goods / Estt. Cost. (Rs. in Lakhs) / Method of Procurment / Estimate prepared & Sanctioned (Date) / Prepartion of Bid Document (Date) / PCU's No Objection to Bidding Document (Date) / Bid Invitation (Date) / Bid Opening (Date) / Contract Award decided (Date) / PCU/ Bank's No Objection to Contract Award (Date) / Contract Signed (Date) / Contract No. / Name of Contractor / WBR NO. / Date of completion of contract / Expenditure incurred to Date.
1 / 2 / 3 / 4 / 5 / 6 / 7 / 8 / 9 / 10 / 11 / 12 / 13 / 14 / 15 / 16 / 17 / 18
1 / Agriculture
Ground Water Monitoring #1 / 1200.00 /
ICB
/ 15th June, 2012 / 20th June, 2012 / 30th June, 2012 / 1st Aug, 2012 / 6th Aug, 2012 / 16th Aug, 2012 / 17th Aug, 2012 / 15th Sept, 20122 / Dairy Development
Installation and commissioning of dairy plant at 10000 LPD capacity at Hojai /k / 200.00 / NCB / 30th June, 2012 / 5th July, 2012 / 15th July, 202 / 16th Aug, 2012 / 20th Aug, 2012 / 21st Aug, 2012 / 22nd Aug, 2012 / 16th Sept, 2012
Establishment of a demonstration farm in kathiatoli / 100.00 / NCB / 31st July, 2012 / 5th Aug, 2012 / 16th Aug, 2012 / 16th Sept, 2012 / 26th Sept, 2012 / 27th Sept, 2012 / 28th Sept, 2012 / 16th Oct, 2012
3 / Forest Department
Office furniture for project divisions / 40.00 / NCB / 20th April, 2012 / 25th April, 2012 / 5th May, 2012 / 5th June, 2012 / 15th June, 2012 / 16th June, 2012 / 17th June, 2012 / 5th July, 2012
4 / PCU
PCU-Mkt Extension
Market Hoardings [100 hoardings @ Rs.1,50,000 each] / 150.00 / NCB / 31st July, 2012 / 5th Aug, 2012 / 16th Aug, 2012 / 15th Sept, 2012 / 20th Sept, 2012 / 21st Sept, 2012 / 22nd Sept, 2012 / 15th Oct, 2012
Total / 1690.00
#1 / The details of this item are being worked out. The cost would include Goods, works, consultants, staff costs etc. As of now it is being kept under ICB, but depending on the final estimated cost, the procurement method may change in consultation with the World Bank
AACP - Additional Financing
PROCUREMENT PLAN FOR GOODS THROUGH SHOPPINGSL No. / Pkg No. / Description of Works/Goods / Unit / Quantity / Estt. Cost. (Rs. in Lakhs) / Method of Procurement ICB/NCB / Estimate preparation & Sanction to estimate (Date) / Collect Quotations (atleast three) / Compare quotations / Contract Award decided (Date) (Rs. Lakhs) / PCU's No Objection to Contract Award (Date) (Applicable for contracts above Rs.13.50 lakhs only) / Supply Order Issue (No. & Date ) / Supply Order Value (Rs. lakhs) / Name of Supplier / Contractor / Date of completion of Supply/ works / Expenditure incurred
1 / 2 / 3 / 4 / 5 / 6 / 7 / 8 / 9 / 10 / 11 / 12 / 13 / 14 / 15 / 16 / 17
Agriculture
1 / A-1V / Vehicles for field engineers (4 wheel Drive) / Nos. / 4 / 23.00 / Shopping / 20th April, 2012 / 27th April, 2012 / 30th April, 2012 / 5th May, 2012 / 10th May, 2012
2 / A-1V / Vehicles for field engineers (2 Wheel Drive) / Nos. / 5 / 22.00 / Shopping / 20th April, 2012 / 27th April, 2012 / 30th April, 2012 / 5th May, 2012 / 10th May, 2012
Purchase of computers and accessories / Sets / 14 / 5.60 / Shopping / 5th April, 2012 / 12th April, 2012 / 17th April, 2012 / 20th April, 2012 / 25th April, 2012
AH & Veterinary
Vaccination & anthelmintic / Nos. / 750 / 4.50 / Shopping / 15th May, ‘12 / 22nd May, ‘12 / 25th May, ‘12 / 30th May, ‘12 / 5th June, 2012
Dairy Development
Milk measuring and collection accessories /g / Nos. / 61 / 2.44 / Shopping / 20th April, ‘12 / 27th April, ‘12 / 30th April, ‘12 / 5th May, 2012 / 10th May, 2012
Milk pail, accessories and saaf kit /h / Nos. / 181 / 10.86 / Shopping / 1st May, 2012 / 7th May, 2012 / 10th May, ‘12 / 15th May, ‘12 / 20th May, 2012
Milk can 20 lts capacity with lid @ 3 cans per MPI / Nos. / 61 / 3.66 / Shopping / 15th May, 2012 / 22nd May, 2012 / 25th May, 2012 / 30th May, 2012 / 5th June, 2012
Milk collection and utility conveyance with a capacity of 1 ton / Nos. / 2 / 3.50 / Shopping / 1st June, 2012 / 7th June, 2012 / 10th June, 2012 / 15th June, 2012 / 20th June, 2012
Establish of milk selling booths in Nagaon and Hojai including deep freeze / Nos. / 10 / 10.00 / Shopping / 2nd Aug, 2012 / 9th Aug, 2012 / 12th Aug, 2012 / 16th Aug, 2012 / 20th Aug, 2012
Value addition inputs /k / Nos. / 30 / 21.00 / Shopping / 16th Aug, ‘12 / 23rd Aug, ‘12 / 26th Aug, ‘12 / 31st Aug, 2012 / 5th Sept, 2012
Small milk marketing utility conveyance 1 ton capacity for plant support / Nos. / 2 / 7.00 / Shopping / 1st Sept, 2012 / 7th Sept, 2012 / 10th Sept, ‘12 / 15th Sept, ‘12 / 20th Sept, 2012
Billboards on hygienic milk production & consumption / Nos. / 30 / 7.50 / Shopping / 15th Sept, ‘12 / 22nd Sept, v / 25th Sept, ‘12 / 30th Sept, v / 5th Oct, 2012
Preparation of extension material, newspaper advt & printing material / LS / LS / 17.00 / Shopping / 1st June, 2012 / 7th June, 2012 / 10th June, ‘12 / 15th June, ‘12 / 20th June, 2012
Fishery
Total Station and other survey equipments / Nos. / 2 / 10.00 / Shopping / 1st Sept, 2012 / 7th Sept, 2012 / 10th Sept, 2012 / 15th Sept, 2012 / 20th Sept, 2012
GPRS / Nos. / 5 / 6.25 / Shopping / 1st June, 2012 / 7th June, 2012 / 10th June, ‘12 / 15th June, v / 20th June, 2012
Laser Printer / Nos. / 2 / 0.30 / Shopping / 17th April, ‘12 / 24th April, ‘12 / 27th April, ‘12 / 2nd May, 2012 / 7th May, 2012
Scanner / Nos. / 2 / 0.48 / Shopping / 1st May, 2012 / 7th May, 2012 / 10th May ‘12 / 15th May ‘12 / 20th May, 2012
Digital Soil & water Testing Kit / Nos. / 12 / 13.20 / Shopping / 15th Sept, ‘12 / 22nd Sept, ‘12 / 25th Sept, ‘12 / 30th Sept, ‘12 / 5th Oct, 2012
100 KVA Generator set for HQ / Nos. / 1 / 10.00 / Shopping / 20th April, ‘12 / 27th April, ‘12 / 30th April, ‘12 / 5th May, ‘12 / 10th May, ‘12
Extension and Training